CHURCHGATE REGENERATION PROJECT UPDATE & NEXT STEPS - PART 1
ApprovedCommittee1 paper
AI summaryCouncil approved additional funding to appoint a regeneration partner for the Churchgate site in Hitchin through a single competitive procurement structured in two phases. The specific sum is set out in a separate Part 2 report.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedTwo phase procurement for partner
MoneyAmount detailed in Part 2 report
What happens nextSingle competitive procurementPhase 1, gateway, then Phase 2
Who it affectsChurchgate Regeneration ZoneHitchin town centre area
What was decided
Council approved additional capital or revenue funding to support a single competitive procurement, in two phases, of a partner to assist with the next stage of the Churchgate Regeneration Project. Report 2.1
The approval covers funding for Phase 1 only; any move to Phase 2, a development agreement, or scheme implementation will need further Member approval. Report 8.25, 9.4
Why
The Council has completed significant technical work, specialist studies and preliminary market engagement to inform the next stage. Report 3.1
Findings show that further feasibility, viability and delivery planning work is needed before decisions on the preferred delivery model. Report 3.2
The additional funding is sought so future decisions rest on robust technical, commercial and financial evidence. Report 3.3
What happens next
Run a single competitive procurement to appoint a regeneration partner, with a formal gateway between Phase 1 and Phase 2. Report 2.1, 8.22
Phase 1 will cover feasibility, viability, master-planning and delivery planning; Phase 2 will cover detailed development planning, planning and consenting, development agreement support and implementation planning, all subject to Member approval. Report 8.23, 8.30
Procurement is timed from mid 2026, with the project team factoring Local Government Reorganisation arrangements into planning and decision making. Report P63, P64
Options considered
Chosen: Single competitive procurement in two phases. Provides continuity, reduces procurement duplication and maintains momentum while preserving Council control. Report 2.1, P8, 8.22
Rejected: Not progressing with further feasibility and delivery planning work. Council would not obtain evidence required to inform future decisions on the site. Report 4.1, P7
Rejected: Separate procurements for the feasibility phase and any subsequent delivery support. Preliminary market engagement indicated a single competitive procurement with phased gateways would give greater continuity and reduce procurement duplication. Report P8
Rejected: Delaying the project pending Local Government Reorganisation. Would delay the evidence base and may reduce the Council's ability to progress before local government transition. Report P9
Implications
Financial: Revenue funding is required at this stage; a capital budget for the scheme will be subject to future viability work. Report 10.1, 10.2
Legal: Full Council approval is required under Section 4.3 of the Constitution for changes to the revenue and capital budgets. Report 9.1, 9.2
Legal: The Council is relying on the general power of competence under Section 1 of the Localism Act 2011. Report 9.5
Legal: Procurement will follow the Council's Contract Procurement Rules and applicable procurement legislation. Report 9.3
Risk: From May 2027, financial decisions on the scheme may need prior consent from the new Shadow Authority under a Section 24 direction. Report 8.33, 8.34
Risk: Project is monitored through the Council's Ideagen system, with quarterly reviews by the Performance and Risk Officer. Report 11.2
Equalities: The Public Sector Equality Duty applies; no specific equalities impacts are identified at this stage. Report 12.1
Other: Social Value will be considered in any future procurement, depending on value and scope; no known environmental or HR impacts at this stage. Report 13.1, 14.1, 15.1
Who and where
Hitchin town centre, including residents, businesses and visitors Report 7.3
Churchgate Shopping Centre leasehold, acquired by the Council in 2022 Report 7.4
Existing market in Hitchin and any future market offer Report 7.2, 8.5, 8.6
St Mary's Church and surrounding heritage assets Report 8.13
Portmill Lane car parks and the wider parking strategy
Future Unitary Authority and Shadow Authority Report 8.35
Timeline
2022: Council acquired the Churchgate Shopping Centre leasehold. Report 7.4
July 2025: Council considered development options and identified a preferred mixed use option for feasibility testing. Report 7.6
April and May 2026: Three All Member Briefings were held on project progress, findings and next steps. Report 5.1
15 May 2026: Report was first notified in the Forward Plan. Report 6.1
Late 2026 or early 2027: Structural Changes Order for Local Government Reorganisation expected to take legal effect. Report 8.32
May 2027: Elections to new Unitary Authorities scheduled; significant financial decisions may need Shadow Authority consent from then to 31 March 2028. Report 8.33, 8.34
2027 to 2028: Masterplanning, planning application and Development Agreement work, subject to Phase 1 outcomes. Report P64, P65
Plain English for the jargon
CRZ (Churchgate Regeneration Zone): The Churchgate site, adjoining Hitchin town centre core, the River Hiz corridor and the existing market area.
LGR (Local Government Reorganisation): Restructuring of local government, with decisions on new unitary structures expected in 2026 and elections in May 2027.
PME (Preliminary Market Engagement): Early engagement with the development and investment sector used to inform procurement, delivery and partnership decisions.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item28
Resolved
That Council approved the additional capital/revenue funding set out in the Part 2 report to support the single competitive procurement, comprising of two phases of a partner to assist the Council with the next stage of the Churchgate Regeneration Project. REASONS FOR RECOMMENDATION: (1) The Council has undertaken significant technical work, specialist studies and preliminary market engagement to inform the next stage of the Churchgate Regeneration Project. (2) The findings indicate that further feasibility, viability and delivery planning work is required before future decisions can be taken regarding the preferred delivery model and implementation of the regeneration proposals. (3) Approval is therefore sought for the additional funding required to undertake this next phase of work, enabling future decisions to be informed by robust technical, commercial and financial evidence.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
Since the previous update to Members, further work has been undertaken to assess the viability, deliverability and regeneration potential of the Churchgate site. This report provides an update on that work and seeks approval for the additional funding required to support the next phase of the project.
Recommendations
2.1Council approves the additional capital/ revenue funding set out in the Part 2 report to support the single competitive procurement, comprising of two phases of a partner to assist the Council with the next stage of the Churchgate Regeneration Project.
Reasons for recommendations
3.1The Council has undertaken significant technical work, specialist studies and preliminary market engagement to inform the next stage of the Churchgate Regeneration Project.
3.2The findings indicate that further feasibility, viability and delivery planning work is required before future decisions can be taken regarding the preferred delivery model and implementation of the regeneration proposals.
3.3Approval is therefore sought for the additional funding required to undertake this next phase of work, enabling future decisions to be informed by robust technical, commercial and financial evidence.
Alternative options considered
4.1The following alternative options were considered:
• Not progressing with further feasibility and delivery planning work. This option was discounted as the Council would not obtain the evidence required to inform future decisions regarding the regeneration of the site.
• Undertaking separate procurements for the feasibility phase and any subsequent delivery support. This option was considered but is not recommended as preliminary market engagement indicated that a single competitive procurement structured around phased gateway approvals are likely to provide greater continuity, reduce procurement duplication and maintain project momentum whilst preserving the Council’s decision- making control.
• Delaying the project pending Local Government Reorganisation. This option was discounted as it would delay the development of the evidence base required to inform future decisions and may reduce the Council’s ability to progress the regeneration project prior to local government transition.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1The Executive Member and Shadow Executive Member(s) have been kept regularly informed throughout the development of this proposal through Project Board meetings and scheduled Executive Member briefings. The project team also hosted three All Member Briefings during April and May 2026 to provide updates on project progress, emerging findings and next steps.
6. FORWARD PLAN
6.1This report was first notified to the public in the Forward Plan on the 15th May 2026.
Background
7.1The Churchgate Regeneration Zone (CRZ) represents one of the most significant long- term regeneration opportunities within Hitchin town centre. The site occupies a prominent and strategically important location adjoining the historic core, the River Hiz corridor and the existing market area.
7.2The Churchgate area performs an important role within the town centre but also faces several long-standing challenges relating to asset condition, public realm quality, accessibility, connectivity, parking, market provision and the overall visitor experience.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.