Cabinet, Tuesday 16 June 2026 at 7.30pm

2025-26 Q4 COUNCIL PLAN UPDATE

Noted Executive 3 papers

AI summaryNorth Herts Cabinet notes 2025-26 delivery plan progress, approves 2026-27 targets, carries incomplete projects forward and adds Royston Learner Pool.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCarry forward incomplete projects, add Royston Learner Pool
MoneyNoneNo direct financial implications from this report
What happens nextMonitor 2026-27 projects and KPIsQuarterly updates to Cabinet
Who it affectsCouncil projects, KPIs, residentsCareline users, callers, council tax payers

What was decided

Cabinet noted progress on Council Delivery Plan projects and approved changes to milestones set out in Appendix 1. Report 2.1

Cabinet noted KPI performance and confirmed actions for the three red and five amber indicators. Report 2.2, 8.3

Cabinet approved the 2026/27 KPI targets set out in Appendix 2, and agreed to carry forward incomplete projects and add the Royston Learner Pool project. Report 2.3, 2.4, 8.6, 8.7

Why

The end of year report gives Cabinet a view of progress against projects and KPIs, and sets the scope for 2026/27 monitoring; Overview and Scrutiny can use it to set their work programme. Report 3.1

Three projects have an amber status because milestone due dates have passed, and two green projects need extended target dates; revised milestones are recommended. Report P3, P4, 8.2

Three KPIs are red (Careline 5 and 10 day installations, and Customer Service Centre calls answered in 45 seconds) and require specific management actions. Report P5, 8.4, 8.5

What happens next

Directors and Service Managers will continue to track projects and KPIs through 2026/27, with quarterly Cabinet updates and ongoing risk and performance reporting through Ideagen. Report 4.1, 5.1, 8.8

Customer Service Centre capacity will be strengthened, with continued promotion of digital and self-service options to reduce avoidable contact. Report 8.4

Recovery action on Council Tax and Business Rates has recommenced, with improved collection performance expected in 2027/28. Report 8.5

Options considered

  • Chosen: Approve the recommendations as set out. Standard end of year governance process agreed for CDP updates. Report 4.1

Implications

  • Legal: No specific legal implications from the report itself; the Council's best value duty under Section 3 of the Local Government Act is supported by the delivery plan and its monitoring. Report 9.1, 9.2, 9.3
  • Financial: No direct financial implications from this report; project efficiencies or investments are covered in budget proposals and monitored through quarterly finance reports. Report 10.1
  • Equalities: No direct equalities implications arising from the report. Report 12.2
  • Risk: Local Government Reorganisation work is identified as an over-arching risk that may affect the ability to manage other projects. Report 8.6
  • Staffing: Short-term absence is rising, and could increase further with workload and Local Government Reorganisation implications; managers will continue to be supported on absence prevention. Report 8.5, 15.1
  • Other: No environmental or social value implications apply to this report; individual projects are assessed as needed. Report 13.1, 14.1

Who and where

  • Careline service users, where 5-day and 10-day installation performance fell short of 90% and 100% targets respectively. Report 8.4
  • Residents contacting the Customer Service Centre, with 56% of calls answered within 45 seconds against an 80% target. Report 8.4
  • Council Tax and Business Rates payers, with in-year collection at 96.93% and 94.57% against 97% and 96% targets. Report 8.5
  • Households served by the waste service, with 58.67% of household waste sent for reuse, recycling and composting against a 59% target. Report 8.5
  • Staff, with short-term absence at 4.45 days per FTE against a 4 day target. Report 8.5

Timeline

  • Early May 2026: Report prepared, reflecting latest project and KPI position at that time. Report P1, 8.1
  • May 2026: Draft of the Council Delivery Plan provided to the Risk and Performance Management Group. Report 5.2
  • 2025/26: Customer Service Centre answered over 99,000 calls across the year. Report 8.4
  • 2026/27: New monitoring period begins with the carryforward projects, the added Royston Learner Pool project, and the approved KPI targets. Report 2.3, 2.4, 8.6
  • 15 May 2026: Key Executive decision first notified in the Forward Plan. Report 6.1

Plain English for the jargon

  • Council Delivery Plan (CDP): The Council's document bringing together projects, risks, and performance indicators for monitoring.
  • KPI: Key Performance Indicator, used to measure the Council's overall performance, rated green, amber or red.
  • Ideagen: The Council's performance and risk software, previously known as Pentana.
  • LGR: Local Government Reorganisation, identified as an over-arching risk for the Council.
  • RPMG: Risk and Performance Management Group, consulted on a draft of the Council Delivery Plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That Cabinet: (1) Noted the progress against projects as set out in the Council Delivery Plan and approved the changes to the milestones (Appendix 1). (2) Noted the performance against the Key Performance Indicators and confirms the actions for those with a red or amber status. (3) Approved the Key Performance Indicators and targets for 2026/27 (Appendix 2). (4) Approved that the existing incomplete projects on the Council Delivery Plan are carried forward into 2026/27, and that the Royston Learner Pool project is added. REASON FOR DECISIONS: The Council Delivery Plan (CDP) report provides Cabinet with the opportunity to monitor progress against the key Council projects and KPIs, including any overall trends. This end of year report also sets the scope (projects and KPIs) for 2026/27 monitoring. Overview and Scrutiny can use these reports to help with setting their work programme. That Cabinet: (1) Noted the progress against projects as set out in the Council Delivery Plan and approved the changes to the milestones (Appendix 1). (2) Noted the performance against the Key Performance Indicators and confirms the actions for those with a red or amber status. (3) Approved the Key Performance Indicators and targets for 2026/27 (Appendix 2). (4) Approved that the existing incomplete projects on the Council Delivery Plan are carried forward into 2026/27, and that the Royston Learner Pool project is added. REASON FOR DECISIONS: The Council Delivery Plan (CDP) report provides Cabinet with the opportunity to monitor progress against the key Council projects and KPIs, including any overall trends. This end of year report also sets the scope (projects and KPIs) for 2026/27 monitoring. Overview and Scrutiny can use these reports to help with setting their work programme.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 7 pages

Executive summary

A year end update on progress against the Council Delivery Plan for 2025-26. Whilst this is a year end update it generally reflects progress as at the time the report was prepared (early May 2026).

The report also recommends the Key Performance Indicator (KPI) targets for 2026/27, and that the current incomplete Delivery Plan projects are retained for 2026/27. The Royston Learner Pool project will be added to the Council Delivery Plan.

Three projects (Phase 2 of Council building decarbonisation, Local Plan Review and Museum Collection Facility) have an amber project status. This reflects that milestone due dates have passed. In each case it is recommended that a new milestone target date is agreed.

Two projects (Leisure Centre Decarbonisation and Town Centre Strategy) have a green status, but it is recommended that new target dates are agreed that would extend the overall project timetable.

Three KPIs have a red status (Careline installations within both 5 and 10 working days, and Customer Service Centre calls answered within 45 seconds. Five KPIs have an amber status).

Recommendations

2.1That Cabinet notes the progress against projects as set out in the Council Delivery Plan, and approves the changes to the milestones (Appendix 1).

2.2That Cabinet notes the performance against the Key Performance Indicators and confirms the actions for those with a red or amber status.

2.3That Cabinet approves the Key Performance Indicators and targets for 2026/27 (Appendix 2).

2.4That Cabinet approves that the existing incomplete projects on the Council Delivery Plan are carried forward into 2026/27, and that the Royston Learner Pool project is added. 3. REASONS FOR RECOMMENDATIONS

3.1The Council Delivery Plan (CDP) report provides Cabinet with the opportunity to monitor progress against the key Council projects and KPIs, including any overall trends. This end of year report also sets the scope (projects and KPIs) for 2026/27 monitoring. Overview and Scrutiny can use these reports to help with setting their work programme.

Alternative options considered

4.1In developing the CDP, it was agreed that Cabinet would receive quarterly updates.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Directors and Service Managers have provided the relevant information to enable the collation of this report and will also have made the relevant Executive Member aware of progress.

5.2A draft of the Council Delivery Plan was provided to Risk and Performance Management Group (RPMG) in May. The Group has a standing invite to Executive Member for Resources, the Chair of Overview and Scrutiny and the Chair of Finance, Audit and Risk Committee. Other members of either Committee and Cabinet are also welcome to attend. There were no specific issues raised by the RPMG.

6. FORWARD PLAN

6.1This report contains a recommendation on a key Executive decision that was first notified to the public in the Forward Plan on the 15 May 2026.

Background

7.1The CDP brings together projects, risks, and performance indicators together in one document. The projects and performance indicators to be included are agreed by Cabinet in June each year, although can be added to during the year.

8. RELEVANT CONSIDERATIONS

2025/26 Council Delivery Plan

8.1Appendix 1 provides an update on the progress made in delivering the Council Delivery Plan 2025-26. Whilst it is labelled as a Quarter 4 (end of year) update, it generally reflects the latest position at the time that the report was written (early May). Milestones are set as far ahead as possible but are not included where there is too much uncertainty over the scope or timing of the milestone. In some cases, the expected actions are included, but without a target date.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025-26 Q4 COUNCIL PLAN UPDATEReport 7 pages DownloadRead as text
PDF
Council Delivery Plan 2025-26: Year-End Monitoring Report FINALAppendix A 36 pages Download
PDF
KPI Targets for 2026-27 FINALAppendix B 12 pages Download

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. 2025-26 Q4 COUNCIL PLAN UPDATEThis decision
  2. Corporate peer challenge action plan updateNoted
  3. Local plan - content and evidence base consultationNoted
  4. Strategic planning matters reportNoted
  5. 2026-27 q1 council delivery plan updateNoted
  6. Response to planning application for hitchin town hall gymnasium and workman's hall trustNoted

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open