That an Infrastructure Delivery Board and associated working groups for the Central Lincolnshire Area be established; 2. That the constitution of the Infrastructure Delivery Board be agreed; 3. That the board meet in advance of the terms of reference being agreed at the next Joint Planning Committee Meeting; and 4. That approval be sought from the partner authorities to prepare jointly aligned Community Infrastructure Levies in advance of the necessary legislation to create a single Community Infrastructure Levy for Central Lincolnshire.
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Report to Central Lincolnshire Joint Strategic Planning Committee
Purpose of report
To obtain Joint Committee approval for:
• Setting up an Infrastructure Delivery Board and associated working groups for the Central Lincolnshire Area; • The constitution of the Infrastructure Delivery Board; • The board to meet in advance of the terms of reference being agreed at the next Joint Planning Committee Meeting; • Seeking approval from the partner authorities to prepare jointly aligned Community Infrastructure Levy's in advance of the necessary legislation to create a single Community Infrastructure Levy for Central Lincolnshire.
Summary
Background
1.1To demonstrate the Core Strategy as ‘sound’ the authorities will need to provide information on how policies within it can be delivered, and how infrastructure that supports these proposals will be managed through the life of the strategy.
1.2This will be achieved through the development of an Infrastructure Delivery Plan (IDP) that will consider, amongst other issues, infrastructure needs and costs, who will fund and provide the infrastructure, and how it will relate to development.
1.3This process will need to be managed effectively via the creation of an Infrastructure Board to oversee the delivery of the IDP and Community Infrastructure Levies. To be robust this process must take into account the budget plans of all infrastructure providers and as such the board will not just be responsible for preparing a document to support the adoption of the LDF but one that will also debate investment in infrastructure across the piece. This will allow decision on infrastructure investment and new development to inform each other.
1.4It should be noted that the Planning Inspectors consider such arrangements to be a sign of deliverability and it was evident at neighbouring Examinations in Public that this approach is seen as positive. Such arrangements are more important in Central Lincolnshire because of joint-working. 2.0 Programme Board
2.1The purpose of the board will be to deliver the best value infrastructure, particularly in support of development proposed in the Core Strategy. In the short term, the existence of the group will demonstrate deliverability at Core Strategy Examination in Public by showing a group accountable for the management and monitoring of the items listed in the IDP.
2.2The Board would not be a formal decision making body, it would report to/from the Joint Planning Committee (JPC) and the four authorities, and it should have a clear terms of reference agreed to by the relevant Councillors.
2.3The JPC would be responsible for formally endorsing the IDP schedule and it is proposed that this is done on the recommendation of the IDP Board. The JPC and relevant partners (through partnership/governance structures) will be asked to agree to deliver the relevant items within the IDP, where these relate to their organisation.
3.0Role of the Project Board
3.1It is proposed that the role of the project board should be to: -
• provide clear direction to the IDP project; • identify solutions to infrastructure barriers; • agree development assumptions (development scenarios) to test with infrastructure providing partners; • act as a route into the corporate management of the four authorities and other partners; • identify opportunities to link wider corporate activity to the IDP work; • ensure consistency of objectives across different corporate activities (“all pulling in the same direction”); • monitor delivery; • ensuring effective timing of different elements of the delivery programme; and, • act as a “sounding board” for proposals such as cross-district distribution of Community Infrastructure Levy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Central Lincolnshire Joint Strategic Planning Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
Election of Vice-Chairman 2026/27That Councillor Brockway be elected Vice-Chairman of the Central Lincolnshire Joint Strategic Planning Committee for ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.