Central Lincolnshire Joint Strategic Planning Committee approved this item on Monday 25 April 2016. Below is the council's own wording, with the papers it was decided on.
That the be approved as a 'live' document to support the Local Plan through examination; 2. That the IDP's foreword be approved; and 3. That authority be given to the Chief Executive Officer of the accountably body for the Joint Strategic Planning Committee, to carry out further additions and/or minor changes to the IDP.
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Report to Central Lincolnshire Joint Strategic Planning Committee
Appendices
1. IDP Schedule 2. IDP Costs and Funding by Theme 3. Availability of / Demands for Funding Executive Summary
The Infrastructure Delivery Plan (IDP) identifies physical, social and green infrastructure needs to support the vision for Central Lincolnshire over the period of the Local Plan, which can be viewed in full at the Central Lincolnshire website1. The IDP and Local Plan should also be considered with the whole plan viability assessment2, prepared with consultancy support from Peter Brett Associates (PBA).
The type, scale and distribution of infrastructure in the IDP has been informed by the level, location and phasing of development identified in the Local Plan. The IDP identifies the costs of infrastructure required to support growth, proposed sources of infrastructure funding, known funding gaps, proposed delivery mechanisms and proposed delivery partners as summarised in the table on the following page.
Priorities contained within this document may change over time and as detailed assessment is undertaken in relation to specific developments. The IDP and changing infrastructure requirements will be monitored and reviewed.
Infrastructure schemes have been prioritised under high, medium and low categories, taking out projects which have guaranteed funding. These categories are set out in more detail in section 3, below. The categories have been identified for IDP purposes and for ease of reference. The identification of an item in those categories should not necessarily in all cases be seen as a suggestion that an item should or should not be funded by developer contributions (either planning obligation or CIL).
As indicated above, the IDP considers three main themes:
Physical Infrastructure; including Utilities, Waste and Transport; Social Infrastructure; including Education, Emergency Services and Community Facilities; and Green Infrastructure
Infrastructure considerations for the three urban areas, Lincoln, Gainsborough and Sleaford, focus for most development, are set out in section 4.50, 4.51 and 4.52
1 Table 1: Summary of Infrastructure Consideration The following table provides a summary of both the IDP text and schedule. Further information on the schedule should also be considered, attention is drawn particularly to 'Delivery Year' column in the schedule.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Central Lincolnshire Joint Strategic Planning Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
Election of Vice-Chairman 2026/27That Councillor Brockway be elected Vice-Chairman of the Central Lincolnshire Joint Strategic Planning Committee for ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies