Central Lincolnshire Joint Strategic Planning Committee agreed this item on Monday 8 April 2013. Below is the council's own wording, with the papers it was decided on.
That the priorities set out in option B in the report (priorities 1, 2a, 2b, 2c and 3) be agreed. 2. That the Chairman and Vice-Chairman of the Central Lincolnshire Joint Strategic Planning Committee be authorised to endorse Infrastructure Delivery Plan changes as a result of the agreement on option B priorities. 3. That further assessment of the ability of the Authorities and public sector partners to fund IDP items be supported. 4. That in future reports and publications making reference to the IDP it be stated that the JPU would have an expectation that where the “Bowls Bonus” has been paid to parish councils the parish council would assist in paying for the lower level of infrastructure provision.
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Report to Central Lincolnshire Joint Strategic Planning Committee
Purpose of report
The report presents the draft Infrastructure Delivery Plan (IDP) which is appended. It is recommended that the IDP is endorsed ready for consultation alongside the summer consultation on the Core Strategy. The IDP will be monitored regularly and updated annually.
1. Introduction to this report
This report outlines progress on IDP evidence. A separate report is provided on CIL. The IDP work has implications for Central Lincolnshire’s growth objective of 42,800 new dwellings and 210 hectares of employment land and the future delivery of strategic infrastructure to 2031. Previous IDP/CIL reports have been presented to all four Authorities’ Committees as well as the JSPC.
2. Infrastructure Delivery Plan (IDP) and infrastructure priorities
The CLJSPC is responsible for the IDP, which will form part of the Core Strategy evidence base. The IDP contains current, available evidence ready for formal submission in September 2013. The draft IDP identifies infrastructure costs and known funding availability and allows for the authorities to determine what infrastructure to prioritise for CIL funding and planning obligations, informed by an overall framework.
As previously discussed at the JSPC, the IDP needs to include priorities. Two alternatives are suggested: -
Option A Option B Included in the IDP text IDP text may need updating, subject to JSPC Detailed schedule at appendix 2 Detailed schedule review, subject to JSPC 0 – Assumed 100% funded without CIL or 0 – Assumed 100% funded without CIL or section 106: for example, utility connections. section 106: for example, utility connections. 1 – High priority: critical transport and essential 1 – High priority – critical transport and flood resilience measures essential flood resilience measures 2 – High/ medium priority: education provision 2a – High/ medium: education, GP surgeries 3 – Medium: GP surgeries, dentists, other 2b – Medium: dentists, non-critical transport transport measures, fire stations, sport / measures, fire stations, sport / community community centres, high participation sports centres, high participation sports pitches, pitches, green infrastructure and carbon green infrastructure and carbon reduction reduction measures. measures. 4 – Medium/ low: facilities for lower 2c – Medium/ low: facilities for lower participation sports; longer term transport participation sports; longer term transport measures measures 5 – Low: only pharmacies are included at this 3 – Low: pharmacies stage. Councillors’ attention is drawn to the text in the IDP that explains the context to these categories: executive summary (page 4) and section on priorities (from page 9).
3. Major infrastructure items in the IDP
Within the context of the identified priority areas above and the limited infrastructure funding likely to be available, some major infrastructure items are worthy of more detailed discussion, as identified below: -
The Lincoln Eastern Bypass The Lincoln Eastern Bypass (LEB) is a fundamental part of the Lincoln Transport Strategy (LTS). Significant LCC and Department for Transport funding is in place. The current draft IDP schedule includes the £34m pay-back for LEB costs. It is assumed to be paid for by CIL, although agreement with the individual district councils (as CIL charging authorities) will be sought. The cost of borrowing is an important consideration and clearly the longer the £34m is outstanding, the more will be paid in interest.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Central Lincolnshire Joint Strategic Planning Committee at North Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
Election of Vice-Chairman 2026/27That Councillor Brockway be elected Vice-Chairman of the Central Lincolnshire Joint Strategic Planning Committee for ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.