RESOLVED THAT CABINET Delegates authority to award the groundworks contract to the Strategic Director of Place in consultation with the Planning and Infrastructure Portfolio Holder and Section 151 Officer. Reason for decision : The level of expenditure for the contract exceeds the authority level in the scheme of delegation.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
Title of Report RIVER MEASE DEVELOPER CONTRIBUTION EXPENDITURE FOR CONTRACTORS COSTS ASSOCIATED WITH A SCHEME NEAR MEASHAM
Presented by Councillor Richard Blunt Leader of the Council
Background Papers Public Report: Yes
Key Decision: Yes
Financial Implications Up to £250,000 of Section 106 developer contributions to be authorised for groundworks contractor costs to deliver a large phosphate mitigation scheme in accordance with the Developer Contribution Strategy. This expenditure is available from Section 106 contributions secured by the Council and has been approved by the River Mease Programme Board.
Signed off by the Section 151 Officer: Yes
Legal Implications Contributions have been secured through Section 106 Agreements in accordance with the Councils approved Developer Contribution Strategy. Signed off by the Monitoring Officer: Yes
Staffing and Corporate None identified Implications Signed off by the Deputy Head of Paid Service: Yes
Purpose of Report To request Cabinet delegate authority to the Strategic Director of Place to award the Groundworks contract on receipt and evaluation of the tender submissions.
Reason for Decision The level of expenditure for the contract exceeds the authority level in the scheme of delegation.
Recommendations THAT CABINET DELEGATES AUTHORITY TO AWARD THE GROUNDWORKS CONTRACT TO THE STRATEGIC DIRECTOR OF PLACE IN CONSULTATION WITH THE PLANNING AND INFRASTRUCTURE PORTFOLIO HOLDER AND SECTION 151 OFFICER. 1.0 BACKGROUND
1.1The Developer Contribution Strategy (DCS) was set up in 2012 as a requirement of the Water Quality Management Plan for the River Mease Special Area of Conservation (SAC). The DCS requires contributions to be made for every development which contributes additional wastewater via mains sewerage treatment discharge into the River Mease SAC. The fund is then used for projects which reduce the amount of phosphate in the River Mease as mitigation to the development.
1.2The overall cost for the delivery of all phosphate removal measures identified in DCS1 was calculated to be £640,000 and for DCS 2 it was £840,000. The Council has currently collected approximately £600,000 through Section 106 agreement contributions. Trent Rivers Trust (TRT) were contracted in 2019 to deliver these mitigation schemes using the DCS funds to deliver the actions identified in DCS1 and DCS2. In that time TRT have developed a number of schemes within the catchment with some delivery taking place from 2020 with phosphate reductions starting to be made.
1.3A large sediment trapping scheme has been developed near Measham which has the capacity to collect high levels of phosphate to be removed from the catchment as an appropriate DCS mitigation. The scheme is proposed to be delivered between July and September 2021, the timing is dictated by the fish breeding season as in channel works are restricted in these periods. The scheme will require 10-12 weeks for delivery working to specific methods to avoid negative impacts on the SAC.
1.4The scheme has been approved by the River Mease Programme Board whose members include Natural England, Environment Agency, Severn Trent Water, the local planning authorities from North West Leicestershire, South Derbyshire, and Lichfield District Councils, as well as Trent Rivers Trust.
1.5The large scheme will be a flagship scheme for the DCS. It will be one of the larger schemes to be delivered and will achieve delivery and conservation objectives for the DCS, the River Mease Water Quality Management Plan (WQMP). The WQMP is the strategy set out under the Habitats Directive to reduce phosphate levels within the River Mease, and is what led to the development of the DCS.
2.0PROCUREMENT AND FINANCIAL IMPLICATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.