RESOLVED THAT: Authority be delegated to the Strategic Director to award the Covid Recovery Support Contract for home improvement work in consultation with the Section 151 Officer and Portfolio Holder be approved. Reason for decision: The level of expenditure on the proposed contract exceeds the authority level in the Scheme of delegation.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
1.1The Housing Improvement Programme (HIP) delivers an annual programme of component renewals and improvements to Council homes, which contributes towards ensuring tenants live in Decent high quality affordable home and, in part, reduces the tenants energy usage which also benefits the environment. 1.2 Since 2018/19 the Housing Improvement Programme has been wholly undertaken by Housing Commercial Services In-house Repair Team (IRT), All of that work has been undertaken within the IRT establishment with no requirement for a support contract with a sub-contractor.
2.0ISSUES
2.1Since the start of the Covid pandemic non-emergency work, such as HIP, has been affected by Covid. This has included periodically ceased, modified or delivery impacted by Covid-safe working practices to protect tenants and staff, staff absences of those that are clinically vulnerable or a requirement to self-isolate due to sickness or being a close contact and access issues when tenants report Covid symptoms in the household. Those same issues have affected our materials supply chain, the asbestos surveying company and our own waste services team that remove the waste to complete each job.
2.2As the prolonged length of the Covid pandemic wasn’t anticipated at the end of 2020/21, it was agreed to carry forward a total of £2.4m of work to be completed over a number of future years. Consequently, a budget of £800k was carried forward to the HIP budget of £4.5million for the 2021/22 financial year.
2.3The Covid pandemic continued during this financial year and continued to affected the delivery of the Home Improvement Programme. It is not considered desirable or prudent to continue to carry forward slippage of capital improvement works over a number of future years, as that may lead to:
tenants dissatisfaction with the quality of their homes; more costly reactive repairs before the replacement of components takes place; and increase the number of Council Homes that are non-decent
2.4As the IRT establishment has been established to deliver £4.5m of Home Improvement work next year, and in subsequent years, there are insufficient trades operatives to deliver this delayed improvement work. It is not considered prudent to attempt to recruit a large number of temporary/agency staff to deliver the delayed work as sustained engagement of those workers cannot be guaranteed.
2.5It is therefore proposed to let this “catch up” work to an external contractor as a sub- contract to the IRT.
3.0PROPOSED PROCUREMENT
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.