Cabinet, Tuesday 28 July 2026 at 5.00pm

Acquisitions and disposals - Section 106 acquisition

Approved Executive 1 paper

AI summaryCabinet backed adding £3.7m to the housing capital programme to buy 22 Section 106 properties from Bloor Homes at Money Hill over three years, subject to full Council approval on 15 September 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedEndorsed addition to capital programme, single contract approved
Money£3.7mFunded from Right to Buy receipts
What happens nextCouncil decision 15 September 2026Full Council to approve capital addition
Who it affectsNot stated

What was decided

Cabinet endorsed adding £3.7m to the Housing Revenue Account Capital Programme, funded from Right to Buy receipts, and recommended it to Council for approval on 15 September 2026. Report 3.1

Subject to that approval, a single contract will be entered with Bloor Homes to acquire 22 properties of varying types for £3.7m over three years. Report 2.1, 2.3

Authority was delegated to the Strategic Director for Housing to finalise all legal and contractual documents needed to deliver the purchase.

Why

The Council's constitution requires Cabinet approval for spending over £100k, and the Council must spend Right to Buy receipts within their statutory timeframes. Report 1.1

The Council has committed to acquiring at least ten properties a year to partly replace homes lost through Right to Buy and disposals. Report 1.1

The developer offer is for Section 106 affordable housing units, providing a discount in excess of 25% of open market value. Report 1.2, 3.2

What happens next

Full Council to consider the £3.7m capital addition on 15 September 2026.

Strategic Director of Housing to finalise and sign the contract and supporting legal documents.

Bloor Homes to deliver the 22 properties in phases across 2026/27, 2027/28 and 2028/29. Report 2.3, P10

The money

  • £3.7m Addition to HRA Capital Programme, funded from Right to Buy receipts Report 3.1
  • £3,692,254 Total project cost Report P19
  • £3,214,104 Acquisition cost Report P19
  • £295,083 Fees including legal, Stamp Duty Land Tax, valuation, clerk of works and developer/admin fees Report P19
  • £168,313 Interest Report P19
  • £14,754 Contingency Report P19
  • £1,436,556 Spend in 2026 to 2027 Report P20
  • £418,005 Spend in 2027 to 2028 Report P20
  • £1,837,693 Spend in 2028 to 2029 Report P20
  • £3.5m Existing approved 2026/27 HRA New Supply budget, earmarked for other developments Report 3.1
  • in excess of 25% of open market value Discount applied under the Section 106 agreement Report 3.2
  • £235 per unit per annum Service cost assumption in the 50 year appraisal Report 3.4
  • £843 per unit per annum Maintenance cost assumption in the 50 year appraisal Report 3.4
  • £305 per unit per annum Management cost assumption in the 50 year appraisal Report 3.4

Options considered

  • Chosen: Acquire 22 Section 106 properties from Bloor Homes via single contract for £3.7m. Section 106 discount over 25% and replaces stock lost to Right to Buy Report 1.2, 2.1, 3.2
  • Rejected: Buy back former Council properties. Papers note this as a recognised alternative but not selected here Report 1.1
  • Rejected: Off the shelf purchase. Papers note this as a recognised alternative but not selected here Report 1.1
  • Rejected: Self delivery of new housing. Papers note this as a recognised alternative but not selected here Report 1.1

Implications

  • Financial: 100% Right to Buy receipt funding gives the highest Net Present Value of £4,218,163 and the earliest loan repaid in year 1, against lower funding shares. Report 3.6, P17
  • Financial: Sufficient Right to Buy reserve currently available, but timing of other developments may need review if those costs rise. Report 3.9
  • Legal: Section 131 of the Housing Act 1985 limits the Right to Buy discount by reference to a cost floor, reducing the risk of low value resale. Report 1.3, 4.0
  • Legal: Strategic Director of Housing is delegated to complete all necessary legal and contractual steps.
  • Equalities: Properties will be allocated through the Choice Based Lettings System under the Council's Allocations Policy. Report P24
  • Climate: All properties have solar panels and an expected Energy Performance Certificate rating of B. Report 2.2, P24
  • Risk: Risk register covers developer price changes, specification changes, appraisal assumptions, service delays and post-purchase Right to Buy sale. Report 4.0, P23
  • Other: No tenant or community consultation was carried out by the Council before this decision. Report P24

Who and where

  • Households on the housing register in North West Leicestershire Report 1.1, P24
  • Future tenants of the 22 new council properties at Money Hill, Ashby de la Zouch Report P5, 2.1
  • Bloor Homes as the developer counterparty Report 2.1
  • Council tenants in the district through stock replacement after Right to Buy losses Report 1.1

Timeline

  • 2026-07-28: Cabinet decision to endorse the acquisition and capital addition
  • 15 September 2026: Full Council to consider approval of the £3.7m HRA Capital Programme addition
  • 2026/27: First release of properties, totalling 8 completions (one 2 bed 4 person houses) Report 2.3, P10
  • 2027/28: Second phase of completions, totalling 3 (one 4 bed 6 person house and two 2 bed 4 person houses) Report P10
  • 2028/29: Final phase of completions, totalling 11 (one 2 bed 4 person houses and two 2 bed 3 person bungalows) Report P10

Plain English for the jargon

  • HRA: Housing Revenue Account, the ringfenced account for council housing income and spending
  • RTB: Right to Buy, the statutory scheme allowing eligible council tenants to buy their home
  • Section 106: Planning obligation under which developers provide affordable housing or contributions as part of a planning consent
  • MHCLG: Ministry of Housing, Communities and Local Government
  • NPV: Net Present Value, the sum of discounted future cash flows used to appraise the project
  • EPC: Energy Performance Certificate, rating the energy efficiency of a property
  • CPI: Consumer Price Index, used in the appraisal to uplift costs and rents
  • NWLDC: North West Leicestershire District Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item41

Resolved

RESOLVED THAT: 1. The addition to the Council’s Housing Revenue Account (HRA) Capital Programme of £3.7m be endorsed, funded from right to buy receipts, and this expenditure be recommended to Council for approval at its meeting on 15 September 2026. 2. Subject to (1) above, a single contract be entered into with Bloor homes (the developer) to acquire twenty-two properties of varying archetypes for £3.7m over three years, as set out in the report, subject to council approving the addition to the capital programme. 3. Authority be delegated to the Strategic Director responsible for Housing to finalise and agree all necessary legal and contractual documents and take all appropriate procedural and operational steps to deliver the above. Reason for decision: To comply with the constitution of the Council as this report requires Cabinet approval as it is in excess of £100k and to ensure Right to Buy Receipts are spent within their statutory timeframes.
Word for word from the decision North West Leicestershire published for this meeting. Source: minutes-1.nwleics.gov.uk

Follow this further

Built from North West Leicestershire's papers

What the report saysPro

Report to Cabinet

Background

1.1The Council has committed to acquiring at least ten properties per year to partially mitigate loss of stock via Right to Buy (RTB) and disposals. Acquisition via buy-back of former Council properties, off the shelf purchase and self-delivery are all recognised as viable options for new housing supply.

1.2In this case, as a Registered Provider of affordable housing, the Council has been approached by a developer to offer on properties that have been built and made available as part of the Section 106 agreement with the planning authority.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Acquisitions and disposals: Section 106 acquisitionMinutes 264 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
RB
Councillor Richard BluntChair, present
MW
Councillor Michael WyattDeputy Chair, present
TG
Councillor Tony GillardCommittee Member, present
KM
Councillor Keith Merrie MBECommittee Member, present
TS
Councillor Tony SaffellCommittee Member, present
AW
Councillor Andrew WoodmanCommittee Member, present
AT
Allison ThomasOfficer, in attendance
JA
James ArnoldOfficer, in attendance
AB
Andy BartonOfficer, in attendance
AC
Anna CrouchOfficer, in attendance, virtual
JI
Jon IllingworthOfficer, in attendance
BL
Beth LeonardDemocratic Services Officer, in attendance

All 17 on the meeting page

More from North West Leicestershire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesRESOLVED THAT: The minutes of the meetings held on the 25 August 2026 be approved and signed by the Chair as an accur... Approved Open
22 Sep 2026 Allocation of Resources for Corporate Landlord FunctionRESOLVED THAT: 1) The proposal to create two additional posts within the Property Services Team be noted. 2) The fund... Noted Open
22 Sep 2026 Minutes of the Coalville Special Expenses Working Party - 18 August 2026RESOLVED THAT: The minutes of the Coalville Special Expenses Working Party at Appendix 1 be noted. Reason for decisio... Noted Open
22 Sep 2026 Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra... Agreed Open
22 Sep 2026 Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies