Water management in the Coalville Strategic Growth area - Recommendations of the Community Scrutiny Committee

Decided Executive 4 papers

AI summaryNorth West Leicestershire Cabinet backs scrutiny calls for Severn Trent Water to tackle Coalville sewer capacity and for political push on SuDS adoption.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedLetters to STW and local MP requested
MoneyNo direct financial implicationsStaffing managed within existing resources
What happens nextLetters to STW and local MPPlus planning and comms team engagement
Who it affectsCoalville residents, developers, STWAnd the River Sence environment

What was decided

Cabinet requested the Strategic Director for Planning to write to Severn Trent Water seeking a review of its approach to planning applications and further engagement during the Regulation 19 Local Plan consultation starting in July 2026, and noted the financial risk of planning appeals being overturned. Report P13, P14

Cabinet accepted Recommendation 2 and asked the Strategic Director of Place to write to Severn Trent Water requesting additional interim mitigation measures to reduce pollution impacts on people and the local environment. Report P20

Cabinet agreed the Chief Executive should write to the local MP backing enactment of Schedule 3 of the Floods and Water Management Act 2010, with officers to raise SuDS resourcing and long-term maintenance liabilities in those representations. Report P31

Why

A Community Scrutiny Task and Finish Group found the Coalville sewer system is over capacity, with storm overflows discharging sanitary waste and polluting the River Sence, and that Severn Trent Water engagement with planning has historically been limited. Report 1.1, 1.4, 2.5, 2.8, 2.17

Severn Trent Water has committed to long-term investment by 2030, but the Group judged the current situation untenable and worsened by development already permitted and being built out over the next four years. Report 2.8

What happens next

The Strategic Director for Planning and the Strategic Director of Place will write to Severn Trent Water on planning engagement and interim pollution mitigation respectively. Report P13, P20

The Chief Executive will write to the local MP supporting enactment of Schedule 3 of the Floods and Water Management Act 2010 and the designation of SuDS Approval Bodies. Report P31

The Council's Planning and Development Team and Communications Team will engage with Severn Trent Water on SuDS evidence and joint public messaging about what should not be flushed. Report P25, P37

Options considered

  • Chosen: Reject or impose Grampian conditions on new development where sewer capacity is lacking, using Severn Trent Water evidence. Cabinet to press STW for robust evidence; financial appeal risk noted Report 2.5, P11, P13, P14
  • Chosen: Request Severn Trent Water to provide additional interim mitigation measures beyond its 2030 long-term plan. Cabinet accepted in full Report 2.8, 2.9, P20
  • Chosen: Use additional planning conditions, such as a SuDS validation statement, to ensure future SuDS match approved designs. Planning and Development Team to engage with STW; Planning Committee to consider separately as non-executive function Report 2.11, 2.12, P25
  • Chosen: Make political representations to the local MP supporting enactment of Schedule 3 of the Floods and Water Management Act 2010 and SuDS Approval Bodies. Supported with ask to flag SuDS resourcing and long-term liabilities Report 2.14, P31
  • Chosen: Council and STW joint public messaging on what should not be flushed into the sewer system. Communications Team to engage with STW Report 2.17, P37

Implications

  • Legal: Where planning refusals rely on water company evidence and are overturned at appeal, the Council rather than the water company could be liable for costs. Report P11
  • Financial: Future designation as a SuDS Approval Body would carry ongoing maintenance liabilities, with possible Developer commuted sums suggested as mitigation. Report 3.2, P31
  • Equalities: The review was prompted by resident complaints about sewerage pollution along the River Sence linked to new housing development. Report P42
  • Climate: Recommendations aim to reduce water environment pollution, support biodiversity and enhance the District's appearance, aligned with the Zero Carbon Roadmap. Report P40, P45
  • Staffing: Any staffing implications from the recommendations will be managed within existing resources. Report 3.1
  • Risk: No additional risks identified beyond the financial risks set out above. Report P47, 3.2

Who and where

  • Residents of Coalville and North West Leicestershire affected by sewerage pollution along the River Sence Report P42, P43
  • Local ward members and residents who gave evidence to the Task and Finish Group Report 1.4
  • Severn Trent Water as the responsible water and sewerage company Report 1.4, 2.5
  • Developers building out the SE Coalville Strategic Growth Area, including SuDS provision Report 2.11, P29
  • The Lead Local Flood Authority, which advises on planning applications but does not check completed SuDS Report P24
  • The local MP, who will receive the Council's representations on Schedule 3 Report P31

Timeline

  • 26 June 2025: Community Scrutiny Committee established the Task and Finish Group Report 1.1
  • October 2025 to May 2026: Four Task and Finish Group meetings held with officers, Lead Local Flood Authority, residents, ward members and Severn Trent Water Report 1.4
  • 25 June 2026: Community Scrutiny Committee agreed the final report and recommendations Report 2.1
  • July 2026: Regulation 19 Local Plan consultation commencing, in which STW engagement is sought Report P13
  • By 2030: Severn Trent Water commitment to fix current Coalville sewer capacity issues through investment Report 2.8
  • Next four years: Period over which development already permitted in Coalville is expected to be built out Report 2.8
  • 28 July 2026: Cabinet considered and approved the recommendations at this meeting

Plain English for the jargon

  • STW: Severn Trent Water, the water and sewerage company for the area
  • LPA: Local Planning Authority, in this case North West Leicestershire District Council
  • SuDS: Sustainable Urban Drainage Systems, schemes that manage surface water runoff on development sites
  • SAB: SuDS Approval Body, a public body that would formally adopt SuDS once Schedule 3 of the 2010 Act is enacted
  • Grampian condition: A planning condition that prevents development proceeding until a specified off-site matter, such as sewer capacity, is in place
  • Regulation 19 Local Plan consultation: The formal publication stage of the Council's Local Plan before it is submitted for examination
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item42

Resolved

RESOLVED THAT: 1. The Strategic Director with responsibility for Planning be requested to write to Severn Trent Water and requests a review of their approach taken in responding to planning applications and seek further engagement between Planning Officers and STW in this matter, including the Regulation 19 Local Plan consultation commencing in July 2026. 2. The Strategic Director of Place writes be requested to write to Severn Trent Water to request ... view the full minutes text for item 42.
Word for word from the decision North West Leicestershire published for this meeting. Source: minutes-1.nwleics.gov.uk

Follow this further

Built from North West Leicestershire's papers

What the report saysPro

Report to Cabinet

Background

1.1The Task and Finish Group was established by the Community Scrutiny Committee at its meeting on 26 June 2025, the scope of the group is detailed within the committee report which is listed in the background papers above

1.2The Group membership was agreed as Councillors M Ball, A Barker, T Eynon, R Morris, E Parle and J Simmons. Councillor T Eynon was appointed as Chair of the Group.

1.3The Group was supported in the review by Stuart Young and Andrew Pritchard from East Midlands Councils.

1.4The Group held four meetings over the period from October 2025 to May 2026, which included attendance from Council officers, Lead Local Flood Authority, local residents, ward members and Severn Trent Water who was invited to give evidence.

2.0RECOMMENDATIONS OF THE TASK AND FINISH GROUP

2.1Attached at Appendix A is the final report of the Task and Finish Group which includes a series of recommendations that were agreed at the meeting of the Community Scrutiny Committee on 25 June 2026. Appendix B contains a copy of the minute of that meeting.

2.2Set out below are the recommendations from the Scrutiny Committee to Cabinet alongside a response and suggested approach to each recommendation for Cabinet’s consideration and decision. For clarity each scrutiny recommendation is set out in italics with the suggested response set out in plain text.

2.3As some matters relate to Planning Committee functions which are non-executive functions, these matters will need to be considered by the Planning Committee.

2.4Scrutiny Recommendation 1

2.5We have concluded that it is legally possible for the Local Planning Authority (LPA) to reject or to impose ‘Grampian conditions’ on new development where it is acknowledged that a lack of sewer or water treatment capacity exists – if it has sufficient evidence from the water company. As a result, the Council should ask Severn Trent Water (STW) to review its approach to responding to full and outline planning applications in NW Leicestershire to ensure that robust technical evidence is made available which reflects STW’s publicly stated view that the sewer system in Coalville is currently over capacity. The Council should ask STW to provide a full response on water infrastructure requirements through the regulation 19 Local Plan consultation process. 2.6 Response:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
of Appendix AAppendix 2 4.3 MB Download
PDF
Appendix AAppendix A 1.2 MB Download
PDF
Appendix BAppendix B 193 KB Download
PDF
Water management in the Coalville Strategic Growth area: Recommendations of the Community Scrutiny CommitteeMinutes 354 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
RB
Councillor Richard BluntChair, present
MW
Councillor Michael WyattDeputy Chair, present
TG
Councillor Tony GillardCommittee Member, present
KM
Councillor Keith Merrie MBECommittee Member, present
TS
Councillor Tony SaffellCommittee Member, present
AW
Councillor Andrew WoodmanCommittee Member, present
AT
Allison ThomasOfficer, in attendance
JA
James ArnoldOfficer, in attendance
AB
Andy BartonOfficer, in attendance
AC
Anna CrouchOfficer, in attendance, virtual
JI
Jon IllingworthOfficer, in attendance
BL
Beth LeonardDemocratic Services Officer, in attendance

All 17 on the meeting page

On this subject at North West Leicestershire

Search all
  1. Water management in the Coalville Strategic Growth area - Recommendations of the Community Scrutiny CommitteeThis decision
  2. Recommendations of the Water Management in the Coalville Strategic Growth Area Task and Finish GroupAgreed
  3. Establishment of Water Management in the Coalville Strategic Growth Area Task and Finish GroupAgreed
  4. River Mease Special Area of Conservation Water Quality Management Plan - Developer Contribution Scheme 2Approved

More from North West Leicestershire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesRESOLVED THAT: The minutes of the meetings held on the 25 August 2026 be approved and signed by the Chair as an accur... Approved Open
22 Sep 2026 Allocation of Resources for Corporate Landlord FunctionRESOLVED THAT: 1) The proposal to create two additional posts within the Property Services Team be noted. 2) The fund... Noted Open
22 Sep 2026 Minutes of the Coalville Special Expenses Working Party - 18 August 2026RESOLVED THAT: The minutes of the Coalville Special Expenses Working Party at Appendix 1 be noted. Reason for decisio... Noted Open
22 Sep 2026 Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra... Agreed Open
22 Sep 2026 Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules... Approved Open