BUDGET PROPOSALS FOR 2015/2016 TO 2017/2018 AND OPTIONS FOR COUNCIL TAX
NotedFinance1 paper
Nottingham Fire and Rescue Authority - Finance and Resources noted this item on Friday 16 January 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED (1) to note: (i) the Capital and Revenue Budgets for 2015/2016; (ii) the outline Capital and Revenue Budgets for 2016/2017 and 2017/2018; (2) to recommend that the full Fire Authority, subject to more in-depth complete and longer term information being available, including from Central Government, consider the following two funding options for the Service; (i) a zero increase in Council Tax; (ii) an increase in Council Tax below the referendum ceiling.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Nottingham Fire and Rescue Authority - Finance and Resources
Purpose of report
To allow Members to consider the options for the recommendation of a balanced revenue budget over the next three years to the Fire Authority for acceptance. Implications for Council Tax are also considered.
CONTACT OFFICER Neil Timms Name : Strategic Director of Finance and Resources
1.1The Finance and Resources Committee is charged with considering the financial position of the Authority and proposing revenue and capital budgets to the Fire Authority for approval. The Fire Authority will also decide upon levels of Council Tax for the coming year and will consider the recommendations of the Finance and Resources Committee in doing so.
1.2In late December, the government announced the provisional grant settlement for 2015/2016 but made no estimates in respect of 2016/2017 or 2017/2018. This means that there can be no certainty around budget plans for the years beyond 2015/2016 and therefore best estimates have needed to be used.
2. REPORT
CAPITAL BUDGET PROPOSALS 2015/2016 TO 2017/2018
2.1The Authority maintains a sustainable Capital Programme that has been planned out over an extended period. This programme seeks to replace appliances and vehicles when they are approaching the end of their useful life, maintains a rolling programme of ICT replacements and a property programme that will both ensure that property remains fit for purpose, is appropriately located and can be contained within the internal capacity of the organisation to complete.
2.2The overall programme also reflects elements of estimated slippage from 2014/2015 as set out in the following table.
The proposed Capital Programme for 2015/2016 to 2017/18 is therefore as follows:
Total Estimated 2015/2016 2015/2016 2016/2017 2017/2018 Slippage £000’s £000’s £000’s £000’s Transport Rescue Pump 253,020 623,860 876,880 937,695 939,615 Replacement Special Appliances 272,000 0 272,000 75,000 0 Command Support 120,000 0 120,000 0 0 Unit Appliance Eqpt 36,405 16,960 53,365 25,440 25,440 Light Vehicles 394,500 381,020 775,520 479,240 205,405 Total Transport 1,075,925 1,021,840 2,097,765 1,517,375 1,170,460
Property Retention - Retford FS 0 60,000 60,000 0 0 Retention - London 0 0 0 0 60,000 Road Construction of 0 4,000,000 4,000,000 439,400 0 London Road Fire Station Project 0 75,000 75,000 0 0 Initial Design- Worksop Fire Station Project 0 75,000 75,000 0 0 Initial Design - Newark Fire Station Project 0 75,000 75,000 0 0 Initial Design - Hucknall Purchase of Land 0 400,000 400,000 Construction Stage of 0 1,400,000 1,100,000 New Station (Assumed commence in Sept 2016) Construction Stage of 0 800,000 New Station (Assumed commence in Nov 2017) Property Total 0 4,285,000 4,285,000 2,239,400 2,360,000
IT Systems Agresso Upgrade 0 70,000 70,000 0 0 Tranman 0 25,000 25,000 11,000 0 Payroll System 0 40,000 40,000 0 0 IT Systems Total 0 135,000 135,000 11,000 0
Total Programme 1,297,925 5,656,840 6,954,765 3,927,775 4,290,460 2.3 Rescue pump renewals budget changes the usual practice of replacing four appliances each year and reduces this to two in 2015/2016 taking account of the reducing fleet. This rises to a steady three per annum from 2016.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Nottingham Fire and Rescue Authority - Finance and Resources at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ...
Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.