Noted Finance 1 paper

AI summaryNottingham Fire and Rescue Authority's Finance and Resources Committee accepted a substantial assurance opinion on its 2025/26 governance, risk and internal control arrangements, noted the new Global Internal Audit Standards, and approved the 2026/27 Internal Audit Plan.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedGovernance, risk management and internal control for 2025/26
MoneyNot stated
What happens nextIncomplete audits to future meetingReports back to Finance and Resources Committee
Who it affectsFire Authority members and staffInternal audit work and wider control system

What was decided

Members noted the new Global Internal Audit Standards (GIAS) and the associated CIPFA Application Note, which now direct the work of the Internal Audit Team. Report 10.1

Members scrutinised the 2025/26 Internal Audit Annual Report and accepted the substantial assurance opinion on the arrangements for governance, risk management and internal control. Report 10.2

Members noted progress on 2025/26 audits and accepted the completed audit outcome, with remaining audits to be reported to a future meeting of the Finance and Resources Committee. Report 10.3

Why

Internal audit is a mandatory function for fire authorities, set out in the Local Government and Finance Act 1988 and the Accounts and Audit Regulations 2015. Report P8

The annual report lets Members see the work of internal audit and its contribution to the overall system of internal control. Report P9

What happens next

Audits not yet completed in 2025/26 will be reported to a future meeting of the Finance and Resources Committee. Report 10.3

The 2026/27 Internal Audit Plan is now in force, alongside the new Global Internal Audit Standards. Report 10.4, 10.1

Options considered

  • Chosen: Note new Global Internal Audit Standards and CIPFA Application Note Report 10.1
  • Chosen: Accept substantial assurance opinion for 2025/26 Report 10.2
  • Chosen: Note audit progress and accept the completed audit outcome Report 10.3
  • Chosen: Accept the 2026/27 Internal Audit Plan Report 10.4

Implications

  • Legal: Internal audit is a mandatory function for the Fire Authority under the Local Government and Finance Act 1988 and the Accounts and Audit Regulations 2015. Report P8
  • Risk: Internal audit forms part of the Authority's wider system of internal control covering financial and some non-financial risk. Report P9
  • Equalities: No equality impact assessment was carried out because the report covers performance rather than new or amended policy; no ethical implications were identified. Report P5
  • Staffing: No human resources or learning and development implications arise from the report, though indirect implications from policy updates and staff training are noted. Report P1, P3
  • Climate: No environmental or sustainability implications arise directly from the report. Report P7

Who and where

  • Members of the Nottingham Fire and Rescue Authority Report P9
  • The Internal Audit Team Report 10.1
  • Nottinghamshire County Council, which provides the internal audit service Report P11

Timeline

  • 2026-06-19: Finance and Resources Committee meeting where the report was considered.
  • 2025/26: Period covered by the Internal Audit Annual Report and audit opinion of substantial assurance. Report 10.2
  • 2026/27: Period covered by the Internal Audit Plan now in place. Report 10.4
  • Future meeting: Outstanding 2025/26 audits will be reported to a future Finance and Resources Committee meeting. Report 10.3

Plain English for the jargon

  • GIAS: Global Internal Audit Standards, the new standards now directing the Internal Audit Team's work.
  • CIPFA Application Note: The application note from CIPFA associated with the Global Internal Audit Standards.
  • Substantial assurance: The audit opinion given on the Authority's governance, risk management and internal control arrangements for 2025/26.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now direct the work of the Internal Audit Team. (2) Scrutinise and gain assurances on the outcome of the Internal Audit Annual Report for 2025/26 including the audit opinion of substantial assurance for the arrangements for governance, risk management and internal control. (3) Note the progress on the audits which have been carried out in 2025/26. Scrutinise and gain assurances on the outcome of the completed audit and note that those that are not yet completed will be reported to a future meeting of the Finance & Resources Committee. (4) Scrutinise and gain assurances on the 2026/27 Internal Audit Plan.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Nottingham Fire and Rescue Authority - Finance and Resources

Nottinghamshire and City of Nottingham Fire and Rescue Authority Finance and Resources Committee

INTERNAL AUDIT ANNUAL REPORT 2025/26 Report of the Chief Fire Officer There are two appendices to this report which are exempt from publication under Paragraph 3 of Schedule 12A of the Local Government Act 1972 because they contain information which relates to the financial and business affairs of the organisation and other parties.

The public interest in maintaining an exemption outweighs the public interest in disclosing the information because it contains information referring to the future business of another organisation not yet in the public domain.

Date: 19 June 2026

Purpose of Report: To present the Head of Internal Audit’s Annual Report for 2025/26. The report identifies the key outcomes arising from the work of Internal Audit for 2025/26 and provides an audit opinion on the adequacy and effectiveness of the Authority’s arrangements for governance, risk management and internal control. The Annual Report also includes the Internal Audit Plan for 2026/27. This report also provides an update on the five audits carried out during the 2025/26 audit plan year.

Recommendations: It is recommended that Members: • Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now direct the work of the Internal Audit Team. • Scrutinise and gain assurances on the outcome of the Internal Audit Annual Report for 2025/26 including the audit opinion of substantial assurance for the arrangements for governance, risk management and internal control. • Note the progress on the audits which have been carried out in 2025/26. Scrutinise and gain assurances on the outcome of the completed audit and note that those that are not yet completed will be reported to a future meeting of the Finance & Resources Committee. • Scrutinise and gain assurances for the 2026/27 Internal Audit Plan. CONTACT OFFICER Maria Fox Name : Head of Finance and Treasurer to the Fire Authority (Section 151 Officer) Tel : 0115 8388100

Email : [email protected]

Media Enquiries Corporate Communications Contact : 0115 8388100 [email protected] 1. BACKGROUND

1.1Under the Local Government Finance Act 1988, Section 112 and the Accounts and Audit (England) Regulations 2015 (as amended), the Authority as a “relevant body” has a responsibility to maintain an adequate and effective internal audit function and to annually review the effectiveness of its arrangements for Internal Audit. Nottinghamshire County Council has provided an Internal Audit service to the Fire and Rescue Authority since its formation in 1998.

1.2Since 2017, the Public Sector Internal Audit Standards (PSIAS) have provided the basis for internal audit in the public sector, which were published by the Chartered Institute of Public Finance and Accountancy. (CIPFA). However, the Global Institute of Internal Auditors (the GIIA) published new Global Internal Audit Standards (GIAS) which became effective from 9th January 2025 and are applicable to both private and public sector worldwide.

1.3The GIAS and associated CIPFA Application Note came into effect for UK local government on 1st April 2025 and so has been the basis for all internal audits during 2025/26. The CIPFA GIAS Application Note sets out the interpretations and requirements which need to be applied to the GIAS requirements, in order for make them suitably relevant to the UK public sector. The authority for setting standards for internal audit in the UK public sector rests with the Relevant Internal Audit Standard Setters (RIASS). These comprise HM Treasury for central government, Dept of Health and Social Care for the health sector, and CIPFA for the local government sector, which includes fire.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Annual Report 2025/26Report 325 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 13 attended
JC
Councillor John Clarke MBEChair, present
TC
Councillor Terry CoxCommittee Member, absent
KD
Councillor Kevin DaleSubstitute, present as substitute
AK
Councillor Anwar KhanCommittee Member, present
PK
Councillor Pavlos KotsonisCommittee Member, present
JL
Councillor Johno LeeCommittee Member, absent
JS
Councillor John SemensCommittee Member, apologies, sent representative (personal reasons)
JS
Councillor Jody StollCommittee Member, present
LB
Leila BerryOfficer, in attendance
MT
Malcolm TownroeOfficer, absent
MF
Maria FoxOfficer, in attendance
TS
Thomas StrawOfficer, in attendance

All 13 on the meeting page

On this subject at Nottingham

Search all
  1. Internal Audit Annual Report 2025/26This decision
  2. Internal Audit Q1 progress updateNoted
  3. Internal Audit Annual PlanApproved
  4. Internal Audit Annual Report & OpinionDecided
  5. Internal Audit 3 Year PlanApproved
  6. Internal Audit Annual Report 2024/25Noted

More from Nottingham Nottingham Fire and Rescue Authority - Finance and Resources

All decisions
MeetingDecisionOutcome
19 Jun 2026 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... Approved Open
19 Jun 2026 Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... Approved Open
19 Jun 2026 External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... Decided Open
27 Mar 2026 Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... Approved Open
27 Mar 2026 Final 2024/25 Accounts and Audit Completion ReportResolved to note the report of the Treasurer to the Authority, and the contents of the External Auditors Final Comple... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies