RESOLVED to: 1) approve the Stage 1 submission from the Local Education partnership, noting the evaluation as set out in appendix 1; 2) authorise progress to Stage 2 for both the primary and year 7 base ; 3) delegate authority to the Director of Legal and Democratic Services to approve Stage 2, subject to a satisfactory review by the Project Team and a robust value for money assessment from advisors, allowing the project to proceed to Financial Close. Reasons for decision To allow the continued progress of the expansion scheme at Nottingham Academy which will provide urgently needed additional school places for primary age children in the Sneinton area. Other options considered Expanding a different school was rejected, as other schools have site constraints. Using an alternative provider to the Local Education Partnership was rejected, as a feasibility study showed that an alternative contractor was unable to deliver the project within budget.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Project Title: Nottingham Academy primary expansion and Year 7 base replacement
Lead Department: Major Programmes
Nottingham Academy primary expansion and Year 7 Base Stage 1 Submission: Evaluation Report March 2015 Appendix 1
1. Introduction
Context
Nottingham City Council has delivered a series of school and leisure projects using the Local Education Partnership (LEP) which was procured in June 2008, initially to deliver the Building Schools for the Future programme. This procurement route is being used to deliver two projects on behalf of Greenwood Academy Trust (GAT); firstly to expand their primary provision by building a new 420 place primary school on the Sneinton Boulevard site and secondly to demolish and reinstate the existing Year 7 base on an area of land adjacent to the Greenwood Road site. These two projects are being delivered in parallel and are known as the Nottingham Academy projects. The primary school element is being funded by the City Council and the GAT is funding the replacement of the Year 7 base.
The contractual relationship between the City Council and the LEP includes the Strategic Partnering Agreement (SPA) which sets out the process for developing new schemes i.e. New Project Proposal process. This also sets out the process for delivering projects through the LEP with two Stages that require approval by Nottingham City Council.
The City Council received the Stage 1 Submission for the two Nottingham Academy projects on 25 February 2015. This has since been reviewed by the City Council and its advisors. Clarifications have been requested as part of this review process and these have been satisfactorily responded to by the LEP.
This Evaluation Report incorporates feedback on the main elements of the Stage 1 Submission and then goes on to outline the next steps in the process.
1.2School Current Position and Vision
Greenwood Academy Trust (GAT), operating as Nottingham Academy, provides places for pupils from primary up to post 16 education across two sites in Nottingham. Primary and secondary are located on Greenwood Road site with Year 7 and post 16 located on the Sneinton Boulevard site.
Both sites have benefited in the past from Building Schools for the Future money, however further investment is now needed as Nottingham City Council require additional primary placements. Two bulge years of 60 pupils each have already been accommodated within Greenwood Road primary, which was initially designed for a 90 intake per year and was already operating at capacity. It is therefore requested that a new Nottingham Academy primary be developed. To facilitate this Greenwood Academy Trust have purchased an ex Public House located adjacent to Sneinton Boulevard and across the road from the Greenwood Road site. It is proposed that this site be used for a Year 7 Base freeing up accommodation for a new build primary on the Sneinton Boulevard site.
2. Project Proposals
2.1Planning Consultation Statement
Site and office meetings have been held with the Planning Authority and the Highways Team to enable the design team to get early advice on the outline
Nottingham Academy primary expansion and Year 7 Base Stage 1 Submission: Evaluation Report March 2015 Appendix 1
proposals and establish any risks. In principle, support was given to the project in a letter of comfort issued by the planning team dated 19 February 2015. A further email from the Highways Team on 4 March 2015 confirms that there have been discussions about the potential impact of the project and that the design team have discussed mitigation measures for this.
2.2Outline Architectural Strategy
Primary School
The main aims of the project are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.