District Heating Network Replacement Programme - Key Decision

Approved Executive 1 paper

Executive Board approved this item on Tuesday 17 March 2015. Below is the council's own wording, with the papers it was decided on.

Item104

Resolved

RESOLVED to: 1) approve a 5 year forward capital works programme provision of £6.293m as described in the report, and to delegate authority to the Portfolio Holder for Energy and Sustainability to commit expenditure over the 5 years; 2) approve the management and delivery of all construction works through the Highway & Energy Infrastructure in-house delivery teams supported by specialist sub-contractors (under approved framework) as required; 3) delegate authority to the Strategic Director of Commercial & Neighbourhood Services to award contracts for specialist work activities under the established OJEU (Official Journal of the European Union) compliant Highway Procurement Framework supporting the delivery of this programme. Reasons for decision An investment and maintenance programme will improve the overall condition and life expectancy of the Council owned asset, and reduce risk of service failure and the dependency on reactive maintenance resources to respond to network failures. The programme will support Council objectives to provide affordable heating, reduce Council CO2 emissions by 31% by 2020, and create local jobs. Other options considered Not having a planned forward maintenance programme was rejected, as it is essential some works be completed in-year. Not progressing with planned works was rejected, as this would increase the risk of more costly emergency works, cause increased disruption to road users, and risk service failure, particularly over winter periods.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

EXECUTIVE BOARD – 17 March 2015

Subject: District Heating Network Replacement Programme

Corporate John Kelly, Corporate Director Communities Director(s)/ Andy Vaughan, Strategic Director of Neighbourhood Services Director(s): Portfolio Holder(s): Councillor Alan Clark, Portfolio Holder for Energy and Sustainability Report author and Chris Keane, Head of Highway & Energy Infrastructure contact details: 0115 8761363 Key Decision Yes No Subject to call-in Yes No Reasons: Expenditure Income Savings of £1,000,000 or Revenue Capital more taking account of the overall impact of the decision Significant impact on communities living or working in two or more Yes No wards in the City Total value of the decision: £6.293m Wards affected: Citywide Date of consultation with Portfolio Holder(s): 27 February 2015 Relevant Council Plan Strategic Priority: Cutting unemployment by a quarter Cut crime and anti-social behaviour Ensure more school leavers get a job, training or further education than any other City Your neighbourhood as clean as the City Centre Help keep your energy bills down Good access to public transport Nottingham has a good mix of housing Nottingham is a good place to do business, invest and create jobs Nottingham offers a wide range of leisure activities, parks and sporting events Support early intervention activities Deliver effective, value for money services to our citizens Summary of issues (including benefits to citizens/service users):

This report outlines the requirements for the City Council to replace its district heating network; the Council is in a privileged position to own its own district heating network, providing a green heating solution to a significant number of households and businesses.

The district heating scheme is at the heart of public service provision, supporting our role as a leading Energy City, meeting the needs of citizens and commercial customers who rely on district heating for the provision of heat and hot water provision.

Enviroenergy has been through a radical transformation over the last 2 years from previously operating at a loss to providing the City with significant income following a successful insourcing programme and management leadership under Commercial & Neighbourhood Services. This not only contributes to the Medium Term Financial Plan (MTFP) but provides opportunity to invest in this essential asset.

The City has a contractual obligation to maintain its assets to a satisfactory standard and in order to do so an effective asset management strategy has been developed with the introduction of quality survey data combined with operational expertise and local knowledge. The end result is targeted maintenance in order that spend is best placed in order to minimise service failure and disruption to our domestic and commercial customers. The report proposes that the Council invests £6.293m over the next five years to undertake the necessary mains renewal programme, with the Council being reimburse for the costs of these works by Enviroenergy through an agreed repayment plan. The report identifies works and seeks approval to agree a 5 year programme (2014/15- 2018/19) in the sum of £6.293m.

An assessment of the network identifies immediate essential works required to be completed in- year with significant risk of potential service failure over the 2015-16 winter period should these works not take place. This would have an adverse impact on citizens and businesses. In addition an indicative forward programme of investment is identified based on asset condition surveys and further investigatory inspections.

Delivery of the programme will be managed by Highway & Energy Infrastructure Team, core to this service is great service delivery and in-house delivery supporting the creation of local jobs, training opportunities, further stimulates the local economy through these activities. This will be demonstrated through skilling up in-house delivery teams and supporting the 2015 apprenticeship scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
District Heating Network Replacement Programme: Key DecisionDecisions 214 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 15 attended
JB
John BannOfficer, in attendance
GC
Councillor Graham ChapmanVice Chair, apologies (work commitments)
AC
Councillor Alan ClarkCommittee Member, present
JC
Councillor Jon CollinsChair, apologies (council business)
NH
Councillor Nicola HeatonCommittee Member, apologies (council business)
DL
Councillor Dave LiversidgeCommittee Member, present
NM
Councillor Nick McDonaldCommittee Member, present
DM
Councillor David MellenCommittee Member, present
AN
Councillor Alex NorrisCommittee Member, present
GO
Glen O'ConnellOfficer, in attendance
SP
Simon PetersOfficer, in attendance
DT
Councillor Dave TrimbleCommittee Member, present

All 15 on the meeting page

On this subject at Nottingham

Search all
  1. District Heating Network Replacement Programme - Key DecisionThis decision
  2. District Heating Strategy UpdateAgreed

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies