REVENUE AND CAPITAL MONITORING REPORT TO FEBRUARY 2015

Noted Finance 1 paper

Nottingham Fire and Rescue Authority - Finance and Resources noted this item on Friday 17 April 2015. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

RESOLVED (1) to note the report; (2) to approve an additional capital budget of £90,000 within the 2015/16 Capital Programme for the provision of an Incident Command Training Facility at Service Head Quarters, to be financed from Capital Earmarked Reserve; (3) for members of the Authority to receive a briefing note outlining the opportunities available through the Service’s provision of Prince’s Trust Scheme, including the process for referring eligible young people.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Nottingham Fire and Rescue Authority - Finance and Resources

Purpose of report

To report to Members on the financial performance of the Service in the year 2014/15 to the end of February 2015. This report focuses of those key areas where outturn variances are likely to occur.

CONTACT OFFICER

Neil Timms Name : Strategic Director of Finance and Resources

Tel : 0115 967 0880

Email : [email protected]

Media Enquiries Bridget Aherne Contact : (0115) 967 0880 [email protected] 1. BACKGROUND

1.1Budget monitoring is a key aspect of financial management for the Fire and Rescue Authority. Regular reporting of spending against both the revenue and capital budgets is a check that spending is within available resources and, if necessary, allows for financial resources to be re-assigned to meet changing priorities.

1.2For this report, those key areas with a higher risk of significant variance are reported on. An assessment of this risk has been made in the light of the size of the budgets selected and / or previous experience of variances, as well as the emergence of actual variances.

1.3In this financial year, the overall revenue budget is at its lowest level since 2007/08 and it is more important than ever that an overview of the budgetary position during the year is maintained so that appropriate action can be taken in respect of significant variances and the budget is managed as a whole.

2 REPORT

REVENUE BUDGET

2.1Headlines: The total revenue budget is £42.9m, and the forecast outturn variance at this stage in the year is an underspend of £556k, which represents an overall variance of 1.%.

The additional cost of industrial action by the Fire Brigades Union for 2014/15, as reported in the finance system, is £342k. These costs are shown “below the line” in the table in paragraph 2.20 as there is no budget to cover this expenditure and the overspend will be funded from General Reserves if required. The forecast underspend of £682k excludes the impact of industrial action and there are further transactions anticipated in respect of the February 2015 strike period. This means that overall there is likely to be a relatively small underspend at the year end.

2.2Wholetime Pay: An estimated outturn underspend of £480k is anticipated at this stage and this is due to a number of reasons: the number of employees on development rates of pay is higher than assumed in the budget (causing an underspend), the number of employees in a pension scheme is lower than assumed in the budget (causing an underspend) and although the total number of wholetime employees is now in line with the budgeted establishment, there are vacancies for some roles and over-establishment for other roles. This means that pre-planned overtime is being used to maintain crewing (causing an overspend). Expenditure to date on pre-planned overtime is £186k and it is assumed that there will be no further pre-planned overtime for the remainder of the year. An element of contingency is built into the wholetime pay budget to cover temporary over-establishment, so the net result is an overall forecast underspend. 2.3 The removal of one wholetime and one retained appliance, as approved by the Combined Fire Authority on 26 September 2014, has resulted in further underspends this year as the number of occupied posts has fallen below the budgeted establishment. This managed underspend will translate into budget reductions in 2014/15.

2.4Retained Pay: In 2013/14, the Retained pay budget underspent by a total of £338k and the 2014/15 budget has been reduced by £200k. This year there is a projected outturn underspend of around £157k.

The Retained call outs for the current financial year are 2,408 compared to the same period 2013/14 of 2,936 and this factor will have contributed to the underspend.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REVENUE AND CAPITAL MONITORING REPORT TO FEBRUARY 2015Report 303 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
MW
Councillor Malcolm WoodChair, present
JA
Councillor John AllinCommittee Member, present
CB
Councillor Chris BarnfatherCommittee Member, present
JC
Councillor John ClarkeCommittee Member, present
GW
Councillor Gordon WheelerCommittee Member, present
BG
Councillor Brian GrocockAdvisory Member, in attendance
CZ
Catherine Ziane-PryorClerk, present
SM
Sue MaycockOfficer, present
PH
Peter HurfordOfficer, present
NT
Neil TimmsOfficer, present
AC
Andy CardozaOfficer, present

On this subject at Nottingham

Search all
  1. REVENUE AND CAPITAL MONITORING REPORT TO FEBRUARY 2015This decision
  2. 2025/26 Revenue and Capital OutturnApproved
  3. Revenue and Capital Monitoring Report to 30 April 2026Approved
  4. Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Approved
  5. Revenue, Capital and Prudential Code Monitoring Report to 30 November 2025Noted
  6. 2024/25 Revenue and Capital OutturnNoted

More from Nottingham Nottingham Fire and Rescue Authority - Finance and Resources

All decisions
MeetingDecisionOutcome
19 Jun 2026 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... Approved Open
19 Jun 2026 Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... Approved Open
19 Jun 2026 External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... Decided Open
19 Jun 2026 Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d... Noted Open
27 Mar 2026 Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies