REVENUE, CAPITAL AND PRUDENTIAL CODE MONITORING REPORT TO 30 NOVEMBER 2019

Noted Finance 1 paper

Nottingham Fire and Rescue Authority - Finance and Resources noted this item on Friday 17 January 2020. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

Resolved to 1) note the report; 2) approve the transfer of £170k CCTV in vehicles project funding, to fund the PPE helmets to enable them to be purchased in 2019/20 rather than 2020/21 as originally anticipated; 3) approve slippage of £160k for the CCTV in vehicles capital project.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Nottingham Fire and Rescue Authority - Finance and Resources

Purpose of report

To report to Members on the financial performance of the Service in the year 2019/20 to the end of November 2019.

Recommendations: It is recommended that Members:

 Note the contents of this report.  Approve the transfer of £170k CCTV in vehicles project funding to fund the PPE helmets to enable them to be purchased in 2019/20 rather than 2020/21 as originally anticipated.  Approve slippage of £160k for the CCTV in vehicles capital project.

CONTACT OFFICER Becky Smeathers Name : Head of Finance Tel : 0115 967 0880

Email : [email protected] Media Enquiries Therese Easom Contact : (0115) 967 0880 [email protected] 1. BACKGROUND

1.1Budget monitoring is a key aspect of financial management for the Fire Authority. Regular reporting of spending against the revenue budgets is a check that spending is within available resources and, if necessary, allows for financial resources to be re-assigned to meet changing priorities.

1.2For this report, those key areas with a higher risk of significant variance are reported on. An assessment of this risk has been made in the light of the size of the budgets selected and/or previous experience of variances, as well as the emergence of actual variances. It is vital that an overview of the budgetary position during the year is maintained so that appropriate action can be taken in respect of significant variances and the budget is managed as a whole.

1.3Monitoring against the prudential indicators set out by the Fire Authority in February 2019 is also included in this report, as required in the Prudential Code published by the Chartered Institute of Finance and Accountancy (CIPFA).

2 REPORT

REVENUE BUDGET

2.1The revenue monitoring position is set out in Table 1 below. It shows a forecast outturn position of £42.028m, a £0.890m underspend against the revised budget of £42.918m. The revised budget reflects the planned use of £221k earmarked reserves (net of contributions to earmarked reserves). A summary position of expenditure and funding is shown in the table below:

Table 1 – Summary Expenditure and Funding Position 2019/20 Revised Forecast Variance Budget Budget Outturn £’000 £’000 £’000 £’000 Expenditure 42,697 42,918 42,028 (890)

Income (41,457) (41,457) (41,457) 0 General Fund (1,240) (1,240) (350) 890 Reserves Earmarked Reserves (0) (221) (221) 0 Total 0 0 0 0

2.2A more detailed analysis of expenditure can be found at Appendix A. 2.3 The underspend position has changed significantly since that reported to September Fire Authority which reported an expected underspend position of £1.165m. The main reason for this change in anticipated levels of government grant. The revenue budget included a £163k refund of revenue support grant. However, this money was received earlier than expected (at the end of March 2019) and so was accounted for in the 2018/19 financial year.

2.4Despite the reduction in underspend outlined in Section 2.3, the underspend of £0.89m remains significant. The monitoring report considered by the Finance and Resources Committee on 11 October 2019 provided details of significant one-off items causing the underspend. These are summarised below:

 The budgets contained a contingency of £200k to support the day crewing project should it be in a position that it was unable to go live in April 2019. The project was delivered on time and this was not needed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REVENUE, CAPITAL AND PRUDENTIAL CODE MONITORING REPORT TO 30 NOVEMBER 2019Report 593 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 7 attended
AM
Adrian MannClerk, absent
TN
Councillor Toby NealCommittee Member, present
NR
Councillor Nick RaineCommittee Member, present
JC
Councillor John ClarkeChair, present
AB
Councillor Andrew BrownCommittee Member, present
MQ
Councillor Mike Quigley MBECommittee Member, apologies (personal reasons)
JL
Councillor John LongdonSubstitute, present as substitute

On this subject at Nottingham

Search all
  1. REVENUE, CAPITAL AND PRUDENTIAL CODE MONITORING REPORT TO 30 NOVEMBER 2019This decision
  2. 2025/26 Revenue and Capital OutturnApproved
  3. Revenue and Capital Monitoring Report to 30 April 2026Approved
  4. Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Approved
  5. Revenue, Capital and Prudential Code Monitoring Report to 30 November 2025Noted
  6. 2024/25 Revenue and Capital OutturnNoted

More from Nottingham Nottingham Fire and Rescue Authority - Finance and Resources

All decisions
MeetingDecisionOutcome
19 Jun 2026 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... Approved Open
19 Jun 2026 Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... Approved Open
19 Jun 2026 External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... Decided Open
19 Jun 2026 Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d... Noted Open
27 Mar 2026 Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies