Dales, Mapperley and St Ann's Area Committee approved this item on Tuesday 3 March 2020. Below is the council's own wording, with the papers it was decided on.
Resolved to: (1) Approve the new schemes prioritsed by Ward Councillors since the last area committee meeting as detailed below: St Ann’s LTP Schemes Location Type Councillor/Prioritsed Estimated Details St Ann’s Parling phase 5 TRO Prioritse 06/02/2020 £105,000 parking schemes at identified locations across the ward - lead service: Traffic Management St Ann’s Parling phase 5 Singange Prioritse 06/02/2020 £8,000 contingency funding in case of additional signage costs - lead service: Traffic Management Total new LTP schemes £113,000 Previously approved LTP schemes £0 Total LTP schemes £113,000 St Ann’s Public Realm Schemes Location Type Councillor/Prioritsed Estimated Details Windmill Lane Link footpath Walls Prioritse 06/02/2020 £17,000 Repair of wall on link footpath between Windmill Lane and Spalding Road - lead service: Environmental Health St Ann’s ward Safety Prioritse 06/02/2020 £10,000 pothole repairs across the estate - lead service: Highway Maintenance St Ann’s Ward Boundary Prioritse 06/02/2020 £70,000 Boundary improvements Total new Public Realm schemes £27,000 Previously approved Public Realm schemes £20,000 Total Public Realm schemes** £47,000 2019 - 2020 LTP allocation £78,500 LTP carried forward from 2018 - 2019 £46,764 2019 - 2020 Public Realm allocation £47,000 Public Realm carried forward from 2018 – 2019 £56,546 Total Available 2019 - 2020 ACF £228,810 *Less LTP schemes - £113,000 **Less Public Realm schemes - £117,000 ***Decommitted funds + £20,000 Remaining available balance £18,810 LTP element remaining £12,264 Public Realm element remaining £6,546
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Dales, Mapperley and St Ann's Area Committee
Dales, Mapperley and St Ann’s Area Committee 3rd March 2020
Title of paper: Area Capital Fund – 2019/20 Programme
Director(s)/ Andrew Errington Wards affected: Corporate Director(s): Director of Community Protection Dales, Mapperley, St Ann’s Report author(s) and Greg Foister contact details: Neighbourhood Development Officer – Dales Ward 0115 8839807 [email protected]
Michelle Graley Neighbourhood Development Officer – St Ann’s Ward 0115 8839808 [email protected]
Other colleagues who Nancy Hudson, Projects Officer, Highways Services have provided input: Tel: 0115 8765633 [email protected]
Greg Foister Neighbourhood Management Operations Manager [email protected] Tel 88309807 Date of consultation with Portfolio Holder(s) N/A (if relevant)
Relevant Council Plan Key Theme: Nottingham People X Living in Nottingham X Growing Nottingham X Respect for Nottingham Serving Nottingham Better X
Summary of issues (including benefits to citizens/service users): This report provides Councillors with latest spend proposals under the Area Capital Fund including highways and footways.
Recommendation(s): 1 To approve new schemes prioritised by Ward Councillors since the last Area Committee meeting, as detailed in Appendix 1 (shown as non-shaded)
2 Note the monies available to Dales, Mapperley and St Ann’s Wards for 2019/20 as outlined in appendix1. 1 Reasons for Recommendations
1.1The Nottingham LTP strategy 2011-2026 maintains a commitment to deliver local transport improvements across Nottingham’s neighbourhoods and prioritises small-scale transport improvements of importance to local communities.
1.2As part of the budget process Nottingham City Council approved at the Executive Board meeting on 19 February 2019 an LTP capital allocation of £1.25 million citywide between 2019 -20 was approved. At the same meeting a citywide allocation of General Fund Element (public realm) of £750,000 was agreed.
2 Background (including outcomes of consultation)
2.1The Area Capital Programme was established to improve the environment of the neighbourhoods and to create a sense of place for residents in order to improve the quality of life of local people. Since its establishment in 2006 to meet the then corporate priority of ‘Transforming Neighbourhoods’, the Area Capital Fund has included a total programme expenditure portfolio of £40 million. The improvements that have been carried out to date using the programme have included footpath construction and repairs, fences, visual enhancements to public realm, refurbishment of parks and improvements to public buildings.
2.2Resources are allocated from the Nottingham City council general fund, the Local Transport Plan (LTP) and from the Housing Revenue Account. To achieve a joint approach to environmental improvements in neighbourhoods, a greater degree of flexibility has been established to prioritise and deliver improvements so that there is a synergy in local solutions for local issues across neighbourhoods.
2.3The programme of works is a rolling programme. There have been instances where schemes are started, with strong community involvement and interest, only to be altered at a later stage due to changing circumstances such as economic conditions and changes in land values.
2.4The Area Committee, particularly community representatives, are invited to comment specifically on those schemes identified in the proposals column and to consider whether certain schemes can be linked to other programmes of work in order to generate best value and create a greater impact on the local area.
3 Other options considered in making recommendations
3.1None.
4 Finance comments (including implications and value for money/VAT)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Dales, Mapperley and St Ann's Area Committee at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.