Nottingham Fire and Rescue Authority - Finance and Resources noted this item on Friday 31 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved 1) to endorse the Service ’ s approach to managing the key risks to the Authority; 2) to note the most recent version of the Corporate Risk Register (attached at Appendix A to the report) specifically the risk area of Mobilising, Budgets and Pensions that are rated as ‘ very high ’ and new risk area of Service Reputation; 3) to approve the removal of the following risk areas from the CRR and endorse these risks will now be monitored at departmental level: • Emergency Services Network • Legal Knowledge • Programme Governance • Environmental; 4) to approve that the corporate risk management report returns to a six-monthly reporting frequency following the de-escalation of three areas of risk previously reporting as ‘v ery high’.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Nottingham Fire and Rescue Authority - Finance and Resources
Nottinghamshire and City of Nottingham Fire and Rescue Authority Community Safety Committee
CORPORATE RISK MANAGEMENT Report of the Chief Fire Officer
Date: 31 March 2023
Purpose of Report: To provide Members with an overview of the corporate risk management process including the current version of the Corporate Risk Register.
Recommendations: It is recommended that:
• Members endorse the Service’s approach to managing the key risks to the Authority;
• Members note the most recent version of the Corporate Risk Register, specifically the risk areas of mobilising, budgets and pensions that are rated as ‘very high’, and new risk area of Service reputation;
• Members approve the removal of the following risk areas from the Corporate Risk Register and endorse these risks will now be monitored at departmental level:
• Following the de-escalation of three areas of risk previously reporting as ‘very high,’ Members approve the recommendation for this report to return to a six- monthly reporting frequency. CONTACT OFFICER Michael Sharman Name: Assistant Chief Fire Officer Tel: 0115 967 0880
1.1A report detailing the Service’s approach to corporate risk management that outlined a number of escalating areas of risk, was presented to the Policy and Strategy Committee on 14 October 2022. Due to the report outlining several risk areas deemed as ‘very high’, the Committee Chair asked that this report be presented to the full Fire Authority in December 2022 to ensure a wider awareness.
1.2At the request of full Fire Authority, due to the current levels of risk facing the Authority, this report will now be presented to the Finance and Resources Committee on a quarterly basis to allow for oversight and scrutiny.
1.3The Authority continues to follow a robust risk management process, enabling the consideration of key external and internal risks as part of the management decision-making process.
1.4By establishing a systematic approach to identifying, assessing and managing risk, Nottinghamshire Fire and Rescue Service (NFRS) intends to continually improve the Authority’s governance, increase accountability and enhance overall performance.
1.5This report provides Members with an oversight of the corporate risk management process and the key risks to which the Authority is exposed.
2. REPORT
2.1The Authority’s Corporate Risk Register (CRR) details those risks that are significant enough to warrant management by a Principal Officer. Specific risk control measures are put in place to reduce the likelihood and impact of a risk occurrence where this is felt to be practicable and appropriate.
2.2A copy of the Service’s CRR can be found at Appendix A. This has undergone a full review in each of the risk areas.
2.3Much of the risk to the Authority is driven by external forces. The decision of the Fire Brigade’s Union (FBU) membership to accept the national pay offer has meant that three areas of risk, namely Mobilising (Risk 3), Employee Engagement (Risk 4) and Availability of Resources (Risk 9), all previously reporting as ‘very high, have been reduced. The ongoing situation with the Service’s mobilising supplier and replacement mobilising system is covered in the review of the ‘Mobilising’ risk.
2.4A high level summary of current risks facing the Authority, based on the residual risk ratings, is as follows: Risk Risk Title Risk Reference Rating Risk 1 Balanced Budget 16 very high Risk 2 Firefighters Pension Scheme 16 very high Risk 3 Mobilising 16 very high
Risk 15 Service Reputation 12 high Risk 9 Availability of Resources 12 high Risk 6 Preventable Deaths 10 high Risk 4 Employee Engagement 9 high Risk 5 Workforce Sustainability 9 high
Risk 7 Health, Safety and Welfare 8 medium Risk 9 Availability of Resources 8 medium
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Nottingham Fire and Rescue Authority - Finance and Resources at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ...
Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.