Stock Condition Surveys - key decision

Approved Executive 1 paper

Commissioning and Procurement Executive Committee approved this item on Tuesday 11 June 2024. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

Resolved to: (1) approve a direct award to Savills under ‘Places for People Group Limited’ framework (contract Notice reference: 2002/S 000-029646, published 20 October 2022), and enter into a contract to enable delivery of a full Stock Condition Survey up to 31 July 2025, with an option to extend for 2 years if required; and (2) delegate authority to the Assistant Director of Asset Management to set up the required Contract Purchase Agreements to cover the works to be delivered and approve the raising of purchase orders under the signed contract for the duration of the contracts. Reasons for recommendations g) The Council is required to ensure that all of its social housing homes meet the Government’s Decent Homes standard; obligations under the newly introduced Building Safety Act 2022 and Fire Safety Act 2021; and the forthcoming Awaabs Law to ensure that social housing is free from damp and mould, disrepair, Housing Health and Safety Rating System hazards and is structurally sound and safe. The Council is required to demonstrate its compliance using the consumer standards, specifically for property the safety and quality standard. A stock condition survey is needed to ensure that the Council can meet these requirements because current data is based on old surveys. This survey will help ensure the Council is fully compliant with regulations and if not make the Council aware of where it needs to invest to bring failing properties up to standard. Other ... view the full minutes text for item 14.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Commissioning and Procurement Executive Committee

Commissioning and Procurement Executive Committee – 11 June 2024

Subject: Stock Condition Surveys

Corporate Director: Sajeeda Rose - Growth and City Development

Executive Member: Cllr Jay Hayes – Housing and Planning

Report author and Steve Edlin, Assistant Director of Asset Management. contact details: [email removed]

Other colleagues who David Worthington – Finance have provided input: Geetha Blood - Finance Beth Brown – Legal Jeremey Delderfield – Procurement Alison Brown – Director of Property Services Geoff Wharton - Consultant Strategic Director of Housing

Key Decision Yes No Subject to call-in Yes No Reasons: Expenditure Income Savings of £750,000 or more Revenue Capital taking account of the overall impact of the decision Significant impact on communities living or working in two or more Yes No wards in the City Type of expenditure: Revenue Capital

Total value of the decision: £3,600,000 Section 151 Officer expenditure approval Has the spend been approved by the Section 151 Officer? Yes No N/a Spend Control Board approval reference number: 1176 Commissioner Consideration Has this report been shared with the Commissioners’ Office? Yes No Any comments the Commissioners wish to provide are listed in section 6 below. Wards affected: All Date of consultation with Executive Member: 03/06/2024 Relevant Council Plan Key Outcome: Green, Clean and Connected Communities Keeping Nottingham Working Carbon Neutral by 2028 Safer Nottingham Child-Friendly Nottingham Living Well in our Communities Keeping Nottingham Moving Improve the City Centre Better Housing Serving People Well Summary of issues (including benefits to citizens/service users): The Council are required by regulation to ensure that all its social housing meets the governments Decent Homes standard and prove how it knows that its housing stock meets this requirement. The decent homes standard sets out a minimum standard for social housing and is underpinned by four criteria linked to a statutory minimum standard based on the 29 Hazards detailed in the Housing Health and Safety Rating System (HHSRS), reasonable state of repair, having modern facilities and meeting identified levels for thermal comfort.

We maintain decency through the delivery of repair, maintenance and investment works to homes, blocks, and estates. We do this through a mixed service delivery model of directly employed staff and trade colleagues and external contractors who provide additional capacity and technical expertise.

This paper is to seek approval to appoint a single partner to undertake a new Stock Condition survey of all of the NCC managed stock.

We do not have sufficient internal capacity to deliver the scale and scope of surveys required at this time to ensure we maintain decency across our housing assets.

The HRA Capital/Revenue Investment programme, which this work will be carried out under was reported to executive board on 13 February 2024 as part of the Capital Programme and subsequently signed off on 5 March 2024.

The 2006 Decent Homes standard is currently under review as part of one of the most significant regulatory reviews of social housing in the last decade. Using the consultation that has taken place to date there are likely to be additional measures we will have to take on as a landlord to ensure we are compliant with the decency standard, meaning a new survey of our properties is required to ensure we take them into account.

The Social Housing Regulation Act 2023 (“The Act”) introduced a requirement for landlords to evidence how we ensure compliance with the decency standard through the Consumer standards specifically the Safety and Quality standard. Many of the provisions in the Act are responses to the tragedies of the 2017 Grenfell Tower fire and death of two-year old Awaab Ishak, who died in 2020 from exposure to serious mould.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Stock Condition Surveys: key decisionDecisions 496 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 7 attended
ML
Mark LeavesleyClerk, expected
CB
Councillor Cheryl BarnardCommittee Member, present
LW
Councillor Linda WoodingsChair, present
JH
Councillor Jay HayesVice Chair, present
CJ
Councillor Corall JenkinsCommittee Member, present
ER
Councillor Ethan RadfordCommittee Member, present
PK
Councillor Pavlos KotsonisNon-voting, apologies (council business)

More from Nottingham Commissioning and Procurement Executive Committee

All decisions
MeetingDecisionOutcome
14 Apr 2026 Public Health Funerals and The Nottingham Funeral - key decisionResolved to (1) approve: (a) continuation of the Nottingham Funeral Service in order to address funeral poverty in No... Approved Open
14 Apr 2026 Procurement of digital, AI, automation and telephony platforms - key decisionResolved to (1) approve spend of £1.9m to procure a 5-year contract (2 years, with an option to extend by a further 3... Approved Open
14 Apr 2026 Legal support for expiry of Private Finance Initiatives - key decisionResolved to approve (1) spend of a total £2million (£1.5million on general legal support and £0.5million specifically... Approved Open
14 Apr 2026 Procurement of new railway gantry - key decisionResolved to approve that: (1) the Council procure, via an open market competition, and up to the maximum value as det... Approved Open
10 Mar 2026 Agency Worker contract - key decisionResolved to (1) approve a tender process be undertaken to procure a corporate agency worker contract, with a maximum ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies