Revenue, Capital and Prudential Code Monitoring Report to 30 November 2024
NotedFinance1 paper
Nottingham Fire and Rescue Authority - Finance and Resources noted this item on Friday 17 January 2025. Below is the council's own wording, with the papers it was decided on.
Resolved to: 1) note the contents of the report; 2) approve the slippage and acceleration in the capital programme into/from 2025/26 as detailed in Section 2.27 and Appendix B of the report; 3) approve the forecasted capital programme over / underspends as set out in Section 2.28 of the report.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Nottingham Fire and Rescue Authority - Finance and Resources
Nottinghamshire and City of Nottingham Fire and Rescue Authority Finance and Resources Committee
REVENUE, CAPITAL AND PRUDENTIAL CODE MONITORING REPORT TO 30 NOVEMBER 2024 Report of the Chief Fire Officer Date: 17 January 2025
Purpose of Report: To report to Members on the 2024/25 financial performance of the Service and Prudential Code monitoring to the end of November 2024. Recommendations: It is recommended that Members:
Note the contents of this report. Approve the slippage and acceleration in the capital programme into/from 2025/26 as detailed in Section 2.27 and Appendix B. Approve the forecasted capital programme over / underspends as set out in Section 2.28.
CONTACT OFFICER Bev Bull Name: Head of Finance and Treasurer to the Fire Authority Tel: 0115 8388100
Media Enquiries Corporate Communications Team Contact: 0115 8388100 [email protected] 1. BACKGROUND
1.1Budget monitoring is a key aspect of financial management for the Fire Authority. Regular reporting of spending against the revenue budgets is a check that spending is within available resources and if necessary, allows for financial resources to be re-assigned to meet changing priorities.
1.2This report covers those areas with a higher risk of significant variance. An assessment of this risk has been made in the light of the size of the budgets selected and/or previous experience of variances, as well as the emergence of actual variances. It is vital that an overview of the budgetary position during the year is maintained, so that appropriate action can be taken in respect of significant variances and the budget is managed as a whole.
1.3Monitoring against the revised prudential indicators is also included in this report, as required in the Prudential Code published by the Chartered Institute of Finance and Accountancy (CIPFA).
2. REPORT
2.1The revenue monitoring position is set out in Table 1 below. It shows a forecast outturn position of £51.741m, which is an £1.244m (2.35%) underspend against the revised budget of £52.985m. The revised budget reflects the planned use of £584k of earmarked reserves relating to various projects, and the transfer of £287k of grant funding to earmarked reserves.
Table 1 – Summary Expenditure and Funding Position 2024/25
Budget Area Original Revised Forecast Variance Budget Budget Outturn £’000 £’000 £’000 £’000 Employees 43,434 43,604 42,723 (881) Premises 4,464 4,423 4,055 (368) Transport 2,259 2,240 2,546 306 Supplies & Services 4,639 4,889 5,218 329 Third Party 996 1,018 1,108 90 Support Services 183 143 120 (23) Capital Financing Costs 3,126 3,226 2,740 (486) Fees and Charges (469) (469) (330) 139 Other Income (5,944) (6,089) (6,439) (350) Net Cost 52,688 52,985 51,741 (1,244) Financed by: Revenue Support Grant (8,939) (8,939) (8,939) 0 Non-Domestic Rates (11,880) (11,880) (11,880) 0 Council Tax (30,993) (30,993) (30,993) 0 Core Spending Power (738) (738) (738) 0 Grant Earmarked Reserves 0 (297) (297) 0 General Reserve (138) (138) 1,106 1,244 Funding Total (52,688) (52,985) (51,741) 0 Total 0 0 0 0
2.2At the October meeting of the Finance and Resources Committee, Members approved the principle that the in-year revenue underspend will be used to fund the capital programme. The current forecast underspend of £1.244m means the £138k use of the general reserve to balance the budget will not be required and the remaining £1.106m underspend will be applied to capital funding at year end, to reduce the level of borrowing required and therefore reduce the capital charges in future years.
2.3The anticipated movement in reserves table (Table 3) and the estimated reserve position (Appendix A) and the capital programme funding (Appendix B) have been prepared on the basis the above use of the underspend is actioned. The level of actual underspend used to fund capital will be finalised in the outturn position at year end.
2.4Major variances on specific budgets are shown below.
EMPLOYEE COSTS (£881k underspend)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Nottingham Fire and Rescue Authority - Finance and Resources at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ...
Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.