Demolition and redevelopment of HRA shops at Robin Hood Chase for social housing

Agreed Executive 2 papers

Executive Board agreed this item on Tuesday 20 May 2025. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Resolved to (1) agree full decommission and demolition of Robin Hood Chase Shops; (2) approve £3.507m of RTB RF/HRA direct revenue funding for the scheme; (3) appropriate the library unit from the General Fund to the HRA; (4) agree delegation of approval for any change in unit number or unit cost to the Corporate Director of Growth & City Development in consultation with the Corporate Director of Finance and Resources/s.151 Officer and Executive Member for Housing & Planning Reasons for decisions: · NCC currently has over 10,000 households on its housing register, and also faces significant general fund pressures from homelessness regarding the use of nightly paid temporary and emergency accommodation. Increasing the housing stock will allow for the allocation of secure tenancies creating throughput in established temporary accommodation and therefore reducing use on nightly paid accommodation from the private sector (e.g. Hotels). · Increasing the HRA housing stock will help secure the necessary rental income over the medium to long term which is vital for replenishment of resources to operate the housing stock. · Changes to the RTB RF retention agreement allowing schemes to now be 100% funded by these receipts are in place until 31st March 2026 until review, therefore maximum benefit is gained from assigning and spending in this period. · The shops are a not viable for investment owing to their location and inability to attract sufficient commercial interest from occupants paying commercial rents. · The shops are a maintenance liability with no prospect of income to support these undertakings. Other options considered: · Retain – The shops are commercially unviable because of location and regardless of condition. This option was rejected. · Sell on open market – The cleared site could be marketed for sale to a third party; however, it would be unlikely to attract a large capital receipt, would not see the delivery of social housing and would be complicated by the Asset of Community value that affects three of the six units. This option was rejected.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Executive Board – 20th May 2025

Subject: Decommission, demolition and redevelopment of HRA shops at Robin Hood Chase for social housing

Corporate Nicki Jenkins, Corporate Director Growth & City Development Director(s)/Director(s): Geoff Wharton, Consultant Strategic Director of Housing

Executive Member(s): Councillor Jay Hayes, Executive Member for Housing & Planning Report author and Ceri Davies, Regeneration Team Leader, x.63530 contact details: [email protected]

Other colleagues who Daniel Derry – Estates Surveyor have provided input: James Christian – Solicitor, Conveyance David Worthington – Senior Accountant Mick Suggett – Team Leader, Conveyance Jonathan Whitmarsh – Lead Procurement Officer Paul Stanley – Head of Development Subject to call-in: Yes No Key Decision: Yes No Criteria for Key Decision: (a) Expenditure Income Savings of £750,000 or more taking account of the overall impact of the decision and/or (b) Significant impact on communities living or working in two or more wards in the City Yes No Type of expenditure: Revenue Capital If Capital, provide the date considered by Capital Board Date: 29 April 2025 Total value of the decision: £3.507m Section 151 Officer expenditure approval Has the spend been approved by the Section 151 Officer? Yes No N/a Spend Control Board approval reference number: n/a Commissioner Consideration Has this report been shared with the Commissioners’ Office? Yes No Any comments the Commissioners wish to provide are listed below. Wards affected: St Ann’s Date of consultation with Executive Member(s): 23/09/24. Ward Councillors: 16/01/25 Relevant Council Plan Key Outcome: 1. A Renewed Council  Fostering governance transparency and innovation  Financial stewardship  Adopting a ‘One Council’ approach

2. Delivering for local people  Empowering safe communities  Providing safe, affordable housing  Healthy and safe residents  Enhancing education and skills

3. Leading Nottingham forward  Revitalising the economy  Celebrating cultural heritage  Improving infrastructure and connectivity  Championing sustainability

Summary of issues (including benefits to citizens/service users):

The remaining parade of HRA shops at Robin Hood Chase is mainly vacant and owing to its location would not be able to attract the commercial rents required to justify its improvement.

The parade is the remainder of the “shopping centre” at Robin Hood Chase, that was earmarked for redevelopment, but was shelved following the completion of the first two phases of regeneration, which saw the development of a Registered Provider independent living scheme.

There is an opportunity now, given the availability of funding for the delivery of new social housing (Right to Buy replacement funds, which since June 2024 can be used to fund 100% of new social housing development) to add this site to the council’s pipeline for new delivery.

The site would require vacant possession, demolition and clearance, costs that can be accommodated by the funding described above.

The scheme would deliver around 15 new council houses assisting in address of NCC’s 10,000 plus waiting list and homelessness pressures to the General Fund.

Does this report contain any information that is exempt from publication? Exempt Appendix 1 Finance is exempt from publication under paragraph 3 of Schedule 12A to the Local Government Act 1972 because it contains information relating to forecast finances of the project, and, having regard to all the circumstances, the public interest in maintaining the exemption outweighs the public interest in disclosing the information. It is not in the public interest to disclose this information because it could influence value for money in future procurement processes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Carbon Impact AssessmentAppendix 5 501 KB Download
PDF
Demolition and redevelopment of HRA shops at Robin Hood Chase for social housingReport 360 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 20 attended
NK
Councillor Neghat KhanChair, apologies (work commitments)
ER
Councillor Ethan RadfordVice Chair, present
CB
Councillor Cheryl BarnardCommittee Member, present
KC
Councillor Kevin ClarkeNon-voting, apologies (work commitments)
JH
Councillor Jay HayesCommittee Member, present
CJ
Councillor Corall JenkinsCommittee Member, apologies (personal reasons)
HK
Councillor Helen KalsiCommittee Member, absent
SL
Councillor Sam LuxCommittee Member, present
LW
Councillor Linda WoodingsCommittee Member, present
BB
Beth BrownOfficer, in attendance
SF
Stuart FairOfficer, in attendance
BG
Beverley GouveiaOfficer, in attendance

All 20 on the meeting page

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies