Nottingham City Council
Commissioning and Procurement Executive Committee, Tuesday 10 February 2026 at 9.30am

Supply of capacity and expertise to supplement plans to deliver improvements of services to children, young people, families and communities - key decision

Approved Executive 1 paper

AI summaryNottingham City Council approves tender for up to £1,500,000 one year contract to bring in external expertise to improve Children's and Education Services following an inadequate inspection rating.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedUp to £1,500,000 for service improvement expertise
MoneyUp to £1,500,000 over 12 monthsCovered by grant funding already set aside
What happens nextRun competitive tenderVia CCS Management Consultancy Framework, Lot 7
Who it affectsChildren's and Education ServicesAll wards in Nottingham City

What was decided

The Commissioning and Procurement Executive Committee approved a tender process for a one year contract, with a total maximum value of up to £1,500,000, for a supplier to provide service improvement resources and expertise to the Children's and Education Services Directorate.

Authority to award the contract to the successful bidder was delegated to the Corporate Director of Children's and Education Services.

Procurement will be run through the Crown Commercial Service Management Consultancy Framework, using a mini competition under Lot 7, with a single supplier to be appointed to deliver all required service improvement stages. Report P47

Why

In July 2022, Nottingham's Children's Services received an inadequate judgement following a full Inspection of Local Authority Children's Services, and the council needs additional capacity and expertise to complete its improvement journey at the required pace. Report 1.1

The supplier is expected to engage leaders, practitioners, partners, children, young people and communities in shaping a shared vision, provide sector leading practice frameworks across Children's Integrated Services, Education and SEND, and deliver hands on implementation support to embed best practice. Report 1.2, P3, P4, P5

A competitive tender is needed to identify a supplier with the relevant expertise at a price that offers value for money, using a framework with pre-approved providers to reduce risk and speed mobilisation. Report 2.1, 6.3, P29

What happens next

Procurement will lead the mini competition through the Crown Commercial Service Management Consultancy Framework, Lot 7, and award a contract to a single supplier. Report P47, P48

The contract will set out deliverables and a payment mechanism linked to achievement of those deliverables, with robust contract management and review stages throughout. Report P48

Legal services will continue to support the report author and procurement colleagues in completing the necessary contract documentation and reviewing tender documents. Report 6.7

The money

  • up to £1,500,000 Total maximum value of the one year contract, covered by grant funding already set aside Report 5.1, P30

Options considered

  • Chosen: Run a competitive tender for an external supplier (recommended). Enables the council to secure a supplier with the required expertise, experience and capacity to deliver the improvement journey at the required pace Report 2.1
  • Rejected: Do nothing. Would not enable Nottingham to fully achieve its priorities to improve services for children, families and communities within the optimum time Report 3.1
  • Rejected: Recruit additional staff with the necessary expertise and capacity. The experience required to manage the complexity and scale of the changes, and the time needed for recruitment and coordination, would not be practical, and the services are only needed for a limited period, so this would not deliver value for money Report 3.2

Implications

  • Financial: Total cost of up to £1,500,000 over 12 months is covered by grant funding already set aside and committed for this purpose. Report 5.1, P30
  • Legal: The procurement will follow the Crown Commercial Service Management Consultancy Framework and comply with the Procurement Act 2023 or the Public Contracts Regulations 2015, the council's Constitution and Contracts Procedure Rules. Report 6.5
  • Risk: There is a risk that the tender process will not identify a supplier with the relevant expertise at a price offering value for money; this is mitigated by using a framework with relevant providers in a competitive tender. Report P29
  • Other: An Equality Impact Assessment, Data Protection Impact Assessment and Community Impact Assessment are not currently required, and no social value or public health implications have been identified at this stage. Report 8.1, P52
  • Staffing: The supplier will work alongside existing teams and practitioners to embed revised ways of working, strengthen leadership and capability, and ensure improvements are consistently applied and sustained. Report P13, P15

Who and where

  • Children, young people, families and communities across Nottingham City Report 1.1, P8
  • Children's and Education Services Directorate, including Children's Integrated Services, Education and SEND Report P4, P9
  • Practitioners, leaders and partners within Children's and Education Services Report P3, P13
  • All wards in Nottingham City Report P60

Timeline

  • July 2022: Nottingham's Children's Services received an inadequate judgement following a full Inspection of Local Authority Children's Services Report 1.1
  • 19/01/2026: Legal and procurement comments provided on the report Report P43, P49
  • 21/01/2026: Finance Business Partner comment provided on the report Report P33
  • 10 February 2026: Commissioning and Procurement Executive Committee approved the tender process
  • 12 months (contract period): Supplier will deliver the service improvement work covering vision, overarching improvement plans, service level plans, and embedding support Report 5.1, P7, P9, P11, P13, P46

Plain English for the jargon

  • ILACS: Inspection of Local Authority Children's Services, the framework used to judge how well a council looks after children
  • CES: Children's and Education Services Directorate of Nottingham City Council
  • SEND: Special Educational Needs and Disabilities
  • CCS: Crown Commercial Service, a UK government body that runs procurement frameworks
  • Lot 7: The Health, Social Care and Community lot of the CCS Management Consultancy Framework, which is the lot being used for this procurement
  • Mini competition: A process where buyers run a short competitive tender among suppliers already approved on a framework
  • BAU: Business as usual, meaning the supplier's solutions will be embedded into the council's everyday working after the contract ends
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item57

Resolved

Resolved to approve undertaking a tender process for a 1-year contract, at a total maximum value of up to £1,500,000, for a supplier to provide services for service improvement resources and expertise for the Children’s and Education Services Directorate, and to delegate authority to the Corporate Director of Children’s and Education Services to award the contract to the successful bidder. Reasons for recommendation a) The recommendation will enable the Council to tender for services required from suppliers with the required expertise, experience and capacity by following a competitive procurement process and to award the contract to the most appropriate bidder. Other options considered a) Do nothing - this option will not enable Nottingham to fully achieve its priorities to improve services for Children, Families and Communities within the optimum time, therefore was rejected. b) Recruiting additional staff with the necessary expertise and capacity was considered. However, the level of experience required to manage the complexity and scale of the changes, along with the time needed for recruitment and coordination, means this approach would not be practical. Furthermore, as the required services are only needed for a limited period, this option would not achieve the desired objectives or deliver value for money, therefore, this option was rejected.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Commissioning and Procurement Executive Committee

Background

1.1In July 2022 Nottingham City’s Children’s Services received an inadequate judgement following the full Inspection of Local Authority Children’s Services (ILACS). In its forward planning and improvement journey, the intention is to invite tenders from suitably qualified consultancies with experienced discipline in Children’s Services to provide the additional capacity and expertise necessary to complete our improvement journey at the required pace to improve outcomes for children, young people and communities.

1.2The supplier will need to evidence the ability to:

• actively engage leaders, practitioners, partners, children, young people and communities in shaping and articulating a shared Vision, Values and Purpose for Children’s and Education Services (CES);

• provide the Council with the capacity, expertise and recognised sector‑leading practice frameworks, including improvement plans, methodologies, policies and procedures, across Children’s Integrated Services, Education and SEND, enabling the organisation to drive sustainable practice improvement and transformation;

• deliver hands‑on implementation and delivery support to service teams, working alongside practitioners to embed best‑practice ways of working, strengthen leadership and capability, and ensure improvements are consistently applied, embedded and sustained.

1.3Key objectives and deliverables are as follows:

a) Refresh and articulate a shared vision for CES in Nottingham

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Supply of capacity and expertise to supplement plans to deliver improvements of services to children, young people, families and communities: key decisionDecisions 137 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 5 attended
CB
Councillor Cheryl BarnardCommittee Member, present
JH
Councillor Jay HayesVice Chair, present
CJ
Councillor Corall JenkinsCommittee Member, apologies (personal reasons)
ER
Councillor Ethan RadfordChair, present
HK
Councillor Helen KalsiCommittee Member, present

More from Nottingham Commissioning and Procurement Executive Committee

All decisions
MeetingDecisionOutcome
14 Apr 2026 Public Health Funerals and The Nottingham Funeral - key decisionResolved to (1) approve: (a) continuation of the Nottingham Funeral Service in order to address funeral poverty in No... Approved Open
14 Apr 2026 Procurement of digital, AI, automation and telephony platforms - key decisionResolved to (1) approve spend of £1.9m to procure a 5-year contract (2 years, with an option to extend by a further 3... Approved Open
14 Apr 2026 Legal support for expiry of Private Finance Initiatives - key decisionResolved to approve (1) spend of a total £2million (£1.5million on general legal support and £0.5million specifically... Approved Open
14 Apr 2026 Procurement of new railway gantry - key decisionResolved to approve that: (1) the Council procure, via an open market competition, and up to the maximum value as det... Approved Open
10 Mar 2026 Agency Worker contract - key decisionResolved to (1) approve a tender process be undertaken to procure a corporate agency worker contract, with a maximum ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies