Improvement Plan Progress Update

Noted Executive 1 paper

AI summaryNottingham City Council Executive Board noted progress on the Commissioner-led Improvement Plan, with a new Continuous Service Improvement Plan to be agreed in April 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedEndorsed Improvement Plan progress update
Money£33.7m capital receipts, £137m pipeline2024/25 receipts exceeded target; three-year disposal pipeline
What happens nextCSIP to be agreed April 2026Continuous Service Improvement Plan goes to Executive Board 21 April 2026
Who it affectsAll wards in NottinghamCitywide council improvement programme

What was decided

The Executive Board noted the Council's progress against the activities within the Improvement Plan.

Why

The Council received Directions from the Secretary of State for Levelling Up, Housing and Communities on 22 February 2024, which required the Council to develop an Improvement Plan and report on its delivery. Report 2.1, 2.2, 6.1

Reporting progress to the Executive Board is required to provide assurance on the improvement journey. Report 1.3

What happens next

A Continuous Service Improvement Plan will be developed, with pre-decision scrutiny at Corporate Scrutiny Committee on 25 March 2026 and agreement at Executive Board on 21 April 2026. Report 2.26

A Continuous Improvement Committee is to be established, including the Leader as Chair, opposition councillors, and two independent external members, alongside two Ministerial Envoys. Report 2.25

A MHCLG letter dated 4 February 2026 confirmed the Secretary of State is minded to provide a further but reduced package of statutory support for eighteen months, to be reviewed after twelve. Report 2.21

The money

  • £33.7m Capital receipts for 2024/25, exceeding target Report 2.11
  • £137m Risk-adjusted asset disposal pipeline over three years for 2025/26 onwards Report 2.11

Options considered

  • Rejected: Not to provide an update to Executive Board. Reporting on the Improvement Plan to Executive Board is vital to provide assurance on progress

Implications

  • Legal: The Council continues to act under Directions made under section 15(5) of the Local Government Act 1999 following the Commissioner-led intervention of February 2024. Report 1.1, 6.1
  • Governance: A new Continuous Improvement Committee and two Ministerial Envoys are to be appointed as part of the next phase of statutory support. Report 2.25
  • Risk: Risks and mitigations on the Improvement Plan are reported to the monthly Improvement Board. Report P49
  • Financial: The report has no direct financial implications; any investment required will be approved through the governance process. Report 5.2

Who and where

  • All wards in Nottingham Report P75
  • Council companies and traded services Report 2.12
  • Council workforce, through workforce planning and engagement activity Report 2.14, 2.15

Timeline

  • 22 February 2024: Secretary of State Directions received and Commissioners appointed Report 2.1, 6.1
  • 8th July 2024: Improvement Plan agreed with Commissioners Report 2.3
  • 16th July 2024: Executive Board gave political support and approval to the Plan Report 2.3
  • 5th August 2024: Extraordinary City Council formally approved the Plan Report 2.3, 6.4
  • 28th October 2025: Stakeholder event held to share the Council's position with key partners Report 2.5
  • 2 December 2025: Budget consultation closed; over 500 people engaged Report 2.6
  • 4th February 2026: MHCLG letter confirming minded-to reduced statutory support package for eighteen months Report 2.21, 2.25
  • 24 February 2026: This Executive Board progress update considered Report P75
  • 25th March 2026: CSIP to undergo pre-decision Scrutiny at Corporate Scrutiny Committee Report 2.26
  • 21st April 2026: CSIP to be agreed at Executive Board Report 2.26

Plain English for the jargon

  • CSIP: Continuous Service Improvement Plan, the proposed overarching framework replacing the current Improvement Plan
  • MHCLG: Ministry of Housing, Communities and Local Government
  • NCC: Nottingham City Council
  • EFS: Exceptional Finance Support
  • MTFP: Medium-Term Financial Plan
  • SAMP: Strategic Asset Management Plan
  • DMA: Delivery Model Assessment, used in workforce change reviews
  • ISO31000: International risk management standard
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item89

Resolved

Resolved to: (1) note the Council’s progress against the activities within the Improvement Plan. Reason for decisions: the Council received Directions from the Secretary of State for Levelling Up, Housing and Communities on 22 February 2024. These Directions included the appointment of Commissioners to oversee the next phase of its improvement journey; the Directions included a requirement for the Council to develop and agree an Improvement Plan to the satisfaction of the Commissioners, and to report on the delivery of the Plan at six monthly intervals or at such intervals the Commissioners may direct; the Improvement Plan was developed in close liaison with the Commissioners and agreed with them on 8 th July 2024. The Plan also received political support and approval at the Council’s Executive Board on 16 th July 2024. At an Extraordinary Meeting of City Council on 5 th August 2024, Councillors formally approved the Plan as the Council’s overarching improvement plan in response to the Commissioner-led intervention. Other options considered: not to provide an update to Executive Board. This option was rejected because reporting on the Improvement Plan to Executive Board is vital to provide assurance on the progress being made. Councillor Corall Jenkins left the meeting at the conclusion of this item.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Background

1.1This document provides a Progress Update on Nottingham City Council’s (NCC) Improvement Plan, developed in response to the Commissioner-led intervention initiated in February 2024 under Section 15(5) of the Local Government Act 1999. The Improvement Plan was created to address the issues and challenges identified by the Commissioners and to fulfil the actions required by the Secretary of State.

1.2The Progress Update below sets out how NCC is delivering against the priorities and commitments outlined in the original Improvement Plan and the next steps of the Council’s improvement journey. It highlights the progress made in strengthening governance, improving financial sustainability and enhancing the effectiveness of people, processes, and systems across the Council. The Improvement Plan will be replaced by the Continuous Service Improvement Plan (CSIP) which, in future, will serve as the overarching framework for all improvement and transformation activities, ensuring that immediate challenges are addressed while laying the foundation for long-term, sustainable change.

1.3This progress report is presented for the Executive Board’s endorsement and is intended to provide assurance to the Board that NCC is on track with its improvement journey and is committed to delivering positive outcomes for the city and its residents.

Reasons for recommendations

2.1The Council received Directions from the Secretary of State for Levelling Up, Housing and Communities on 22 February 2024. These Directions included the appointment of Commissioners to oversee the next phase of its improvement journey.

2.2The Directions included a requirement for the Council to develop and agree an Improvement Plan to the satisfaction of the Commissioners, and to report on the delivery of the Plan at six monthly intervals or at such intervals the Commissioners may direct.

2.3The Improvement Plan was developed in close liaison with Commissioners and agreed with them on 8th July 2024. The Plan also received political support and approval at the Council’s Executive Board on 16th July 2024. At an Extraordinary Meeting of City Council on 5th August 2024, Councillors formally approved the Plan as the Council’s overarching improvement plan in response to the Commissioner-led intervention.

Improvement Plan Delivery Progress Update

2.4The update is set out under the three aims of the plan and by thematic area.

Aim 1: “A council that delivers for Nottingham with clear direction and purpose” – significant steps are being taken to strengthen strategic planning, transformation, and continuous improvement.

Theme 1a) Delivery and Performance Planning (note: Themes 1 and 3 were combined due to delivery overlap)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Improvement Plan Progress UpdateReport 151 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 21 attended
CB
Councillor Cheryl BarnardCommittee Member, present
BB
Beth BrownOfficer, apologies
MC
Michael CareyClerk, in attendance
SF
Stuart FairOfficer, in attendance
JH
Councillor Jay HayesCommittee Member, present
CJ
Councillor Corall JenkinsCommittee Member, present
NJ
Nicki JenkinsOfficer, in attendance
HK
Councillor Helen KalsiCommittee Member, present
NK
Councillor Neghat KhanChair, present
LL
Lucy LeeOfficer, expected
SL
Councillor Sam LuxCommittee Member, present
NM
Neil McArthurOfficer, in attendance

All 21 on the meeting page

On this subject at Nottingham

Search all
  1. Improvement Plan Progress UpdateThis decision
  2. Draft Nottingham City Council Continuous Service Improvement PlanDecided
  3. Supply of capacity and expertise to supplement plans to deliver improvements of services to children, young people, families and communities - key decisionApproved
  4. Nottingham City Council Improvement Plan - UpdateNoted
  5. Nottingham City Council Improvement Plan - UpdateNoted
  6. Nottingham City Council Improvement Plan UpdateDecided

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies