CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Nottingham City Council

Final 2024/25 Accounts and Audit Completion Report

Noted Finance 1 paper

AI summaryThe Nottinghamshire and City of Nottingham Fire and Rescue Authority noted KPMG's final 2024/25 audit, which gave a qualified opinion due to insufficient evidence on property valuations, but found no significant value for money weaknesses and recorded a £772k underspend.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedMembers noted the Treasurer's report and KPMG's final audit completion
Money£772k underspend on £52.720m budget1.46% revenue underspend, with £1.286m to capital as VRP
What happens nextAddress audit recommendationsTwo recommendations raised on risk register and committee terms of reference
Who it affectsNot stated

What was decided

Members noted the Treasurer's report and the contents of the External Auditors Final Completion Report attached as Appendix A. Report 10.1

The report confirmed the Authority has been able to meet its statutory obligations in relation to its historic Statement of Accounts. Report P7

Why

KPMG issued a modified opinion on 25th February 2026 because it could not obtain sufficient audit evidence on the Authority's property, plant and equipment valuation at 31 March 2024, or on net assets at 1 April 2023, ahead of the 27 February 2026 backstop date. Report P19, P27

The auditor identified no significant weaknesses in the Authority's arrangements for financial sustainability, governance, or improving economy, efficiency and effectiveness. Report P19, P52

The Authority recorded 2024/25 revenue expenditure of £51.948m against a revised budget of £52.720m, an underspend of £772k (1.46%), with £1.286m transferred to capital as voluntary revenue provision. Report P57, P58

What happens next

The auditor raised two recommendations: include climate change risks in the corporate risk register, and update the Finance and Resources and Performance Committees' Terms of Reference, which still date back to 2015. Report P60

Audit work on the Terms of Reference review recommendation is ongoing. Report P60

Future audits will need to address the underlying property valuation evidence issues that gave rise to the qualified opinion. Report P27

The money

  • £52.688m Original 2024/25 revenue budget approved by the Fire Authority in February 2024 Report P57
  • £52.720m Revised 2024/25 revenue budget after additional use of earmarked reserves Report P57, P58
  • £51.948m Total 2024/25 net cost of services, after £1.286m voluntary revenue provision Report P57, P58
  • £772k In-year revenue underspend (1.46% of revised budget) Report P57
  • £1.286m Voluntary revenue provision charged to fund the capital programme Report P57
  • £219k Planned cashable savings in the previous Efficiency and Productivity Plan for 2024/25 Report P64
  • £149k Achieved savings from the planned £219k target Report P64
  • £381k Total efficiency savings achieved for 2024/25 including additional in-year savings Report P64

Implications

  • Financial: KPMG's qualified opinion arises from insufficient audit evidence on property, plant and equipment balances at 31 March 2024 and on net assets at 1 April 2023, with possible knock-on effects on income and expenditure and reserves. Report P27
  • Legal: The report confirms the Authority has met its statutory obligations in relation to its historic Statement of Accounts under the Local Audit and Accountability Act 2014 framework. Report P7, P20
  • Risk: Two formal recommendations were raised: add climate change risks to the risk register, and update 2015-era committee Terms of Reference; a control deficiency over journal postings was also reported with no recommendation. Report P33, P60
  • Staffing: Staff costs make up around 77% of total expenditure, making workforce culture and skills a key factor in the Authority's delivery of services. Report P54

Who and where

  • Nottinghamshire and City of Nottingham Fire and Rescue Authority (Combined Fire Authority) Report P17, P54
  • Nottingham City Council and Nottinghamshire County Council, which provide councillors to the Combined Fire Authority Report P54
  • Council taxpayers in Nottingham and Nottinghamshire who fund the Authority Report P54

Timeline

  • February 2024: Original 2024/25 revenue budget of £52.688m approved by the Fire Authority Report P57
  • September 2024: HMICFRS inspection report published, rating 10 of 11 areas Good and one Adequate Report P61
  • 25th February 2026: KPMG issued a modified opinion on the Authority's 2024/25 financial statements Report P19, P27
  • 27 February 2026: Statutory backstop date for publishing 2024/25 accounts and audit opinion under the Accounts and Audit (Amendment) Regulations 2024 Report P27
  • 2026-03-27: Finance and Resources Committee noted the Treasurer's report and the External Auditors Final Completion Report

Plain English for the jargon

  • Combined Fire Authority (CFA): The statutory body made up of councillors from Nottingham City Council and Nottinghamshire County Council that runs the Fire and Rescue Service.
  • Modified / qualified opinion: An auditor's opinion that financial statements give a true and fair view except for the possible effects of specific matters where evidence could not be obtained.
  • Backstop Date: The statutory deadline of 27 February 2026 set by the Accounts and Audit (Amendment) Regulations 2024 for publishing 2024/25 accounts and the audit opinion.
  • Medium Term Financial Strategy (MTFS): The Authority's multi-year financial plan setting out forecast income, expenditure, savings and reserves.
  • Voluntary Revenue Provision (VRP): An additional charge against revenue used to fund capital expenditure, giving a medium-term financial benefit.
  • HMICFRS: His Majesty's Inspectorate of Constabulary and Fire and Rescue Services, the national inspection body for the fire service.
  • Community Risk Management Plan (CRMP): The Authority's strategic plan for identifying and reducing fire and rescue related risks.
  • CIPFA Code: The CIPFA/LASAAC Code of Practice on Local Authority Accounting, the framework used to prepare the 2024/25 financial statements.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item33

Resolved

Resolved to note the report of the Treasurer to the Authority, and the contents of the External Auditors Final Completion Report attached as appendix A.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Nottingham Fire and Rescue Authority - Finance and Resources

Financial implications

The financial implications are set out in the body of the report.

4. HUMAN RESOURCES AND LEARNING & DEVELOPMENT IMPLICATIONS

There are no human resources or learning and development implications arising directly from this report. 5. EQUALITIES AND ETHICAL IMPLICATIONS

An equality impact assessment has not been undertaken because this report is not associated with policy, function or service. Its purpose is to provide members with an External Audit update.

6. ENVIRONMENTAL AND SUSTAINABILITY IMPLICATIONS

There are no environmental and sustainability implications arising directly from this report.

This report confirms that the Authority has been able to meet its statutory obligations in relation to its historic Statement of Accounts.

8. RISK MANAGEMENT IMPLICATIONS

The production of the Statement of Accounts is fundamental in demonstrating a sound financial position for any organisation.

9. COLLABORATION IMPLICATIONS

There are no collaboration implications arising directly from this report.

Recommendations

It is recommended that Members:

10.1Consider the contents of the External Auditors Draft Completion Report as attached at Appendix A.

11. BACKGROUND PAPERS FOR INSPECTION (OTHER THAN PUBLISHED DOCUMENTS)

None.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Final 2024/25 Accounts and Audit Completion ReportReport 302 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
JC
Councillor John Clarke MBEChair, present
CZ
Catherine Ziane-PryorClerk, present
LA
Councillor Liaqat AliCommittee Member, present
TC
Councillor Terry CoxCommittee Member, present
JL
Councillor Johno LeeCommittee Member, present
JS
Councillor John SemensCommittee Member, present
JS
Councillor Jody StollCommittee Member, apologies, sent representative
AK
Councillor Anwar KhanCommittee Member, present
WL
Councillor Wendy LukacsSubstitute, present as substitute

On this subject at Nottingham

Search all
  1. Final 2024/25 Accounts and Audit Completion ReportThis decision
  2. Update on Final Audited Statement of Accounts 2021/22 and 2022/23Noted
  3. Unaudited Final Accounts 2022/23Noted
  4. Harvey Hadden and Highfields Financial Outturn 2021/22 and Bridge Estate Final Accounts 2021/22Noted
  5. 2020/21 Audited Final AccountsAgreed
  6. Unaudited Final Accounts 2021/22Noted

More from Nottingham Nottingham Fire and Rescue Authority - Finance and Resources

All decisions
MeetingDecisionOutcome
19 Jun 2026 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... Approved Open
19 Jun 2026 Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... Approved Open
19 Jun 2026 External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... Decided Open
19 Jun 2026 Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d... Noted Open
27 Mar 2026 Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies