Executive Board, Tuesday 22 September 2026 at 2.00pm

Newstead Abbey Programme of Repairs Phase 2

Approved Executive 1 paper

AI summaryNottingham Executive Board accepts over £1.7m in grants and approves procurement for Phase 2 repairs at Newstead Abbey, with a further £990,000 application planned for Phase 6.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPhase 2 repairs and Phase 6 application authorised
Money£2,706,861 totalGrants and fundraising, no Council capital cost
What happens nextProcurement and HE HARCF bidContracts to be tendered; HE outcome spring 2027
Who it affectsNewstead Abbey and museum serviceGrade 1 listed site in Gedling borough

What was decided

The Board accepted the Arts Council England MEND Round 5 grant and the Historic Houses Foundation grant and agreed to enter into the funding agreements. Report 2.1

The Board authorised procurement of Phase 2 contracts and delegated award and spending to the Strategic Director of Communities, using NCM reserves, Raise the Roof donations, and the secured grants. Report 2.3

The Board approved a further grant application to Historic England Heritage at Risk Capital Fund for up to £990,000 and delegated authority to procure Phase 6 if the award is secured. Report 2.4, 2.5

Why

Newstead Abbey is Grade 1 listed, a Scheduled Monument, and on the Heritage at Risk Register. Internal propping is now needed because ceilings risk collapse after a decade of water ingress. Report 1.4

Owners have a duty of care and Gedling Borough Council could serve a repairs notice under the Planning (Listed Buildings and Conservation Areas) Act 1990, with the cost recharged or compulsory purchase possible. Current estimated full repair cost is £9 Million. Report 2.2, P15

Grants, ringfenced NCM reserves, and Raise the Roof Appeal donations mean the project can be delivered with no impact on the Council Capital Programme. Report 2.1, 2.3, P26

What happens next

Procure professional team and main contractor for Phase 2 using the full NCC ITT procedure, with main contractor estimated at £1.5 million and professional fees about 9% of project value. Report 2.3

Submit an Expression of Interest to HE HARCF round 2 this autumn, with outcome expected in spring 2027. Report 2.4

If HE HARCF is awarded, tender Phase 6 alongside Phase 2 to share scaffolding and preliminaries, with Phase 2 still proceeding regardless. Report 2.5, P14

The money

  • £2,706,861 Total value of the decision, comprising grants, fundraising and potential HE award Report 5.1
  • £1,550,747 Arts Council England MEND Round 5 grant (per Finance section) Report 5.1
  • £1,550,774 Arts Council England MEND Round 5 grant (per funding table) Report P23
  • £66,114 Historic Houses Foundation grant Report 5.1, P23
  • £100,000 Raise the Roof Fundraising campaign Report 5.1, P23
  • £990,000 Maximum potential Historic England Heritage at Risk Capital Fund award for Phase 6 Report 2.4, 5.1
  • £1.5 million Estimated Phase 2 main contractor contract value Report 2.3
  • £4,657,571 Total capital programme if HE HARCF is awarded in full Report 5.7
  • £9 Million Current estimate of full repair cost if not addressed Report P15

Options considered

  • Chosen: Approve grants, Phase 2 procurement, and HE HARCF application. Avoids enforcement risk and delivers works without capital programme impact Report 2.1, 2.4
  • Rejected: Do nothing. Grants would be returned, the Abbey would continue to deteriorate, and the Council would remain statutorily liable under the Planning (Listed Buildings and Conservation Areas) Act 1990, with major capital programme impact Report P11

Implications

  • Legal: Acceptance binds the Council to keep Newstead Abbey operating as an accredited museum for 20 years and to comply with grant procurement rules; breach could trigger clawback. Gedling Borough Council could otherwise serve a repairs notice under the 1990 Act. Report 6.1, 6.2, 2.2
  • Risk: Failure to proceed could leave the Council facing the full £9 Million repair bill. Local government reorganisation may place the site in a new Nottinghamshire Council unitary authority, and the 20-year grant obligations extend beyond that point. Report P15, P18, 6.4
  • Climate: Works are phased across five stages to allow roof removals only during permitted months, to protect roosting bats, with periodic ecology surveys and protected species licences required. Report 1.5
  • Staffing: Continued operation supports the Museums Service Future Delivery Plan 2025-2030, with subsidy expected to fall from £1.9 M to about £0.5 M over five years. Report P17
  • Other: Heritage at Risk status: Abbey is on the Heritage at Risk Register and is Grade 1 listed and a Scheduled Monument.

Who and where

  • Visitors and school groups using Newstead Abbey as a museum and parkland Report 1.1
  • Nottingham City Museums service, including costume, textile and designated lace collections stored on site Report 1.1
  • Roosting bats in the Abbey roofs, with phased works and ecology surveys planned Report 1.5
  • Gedling Borough Council as potential enforcement authority under the 1990 Act Report 2.2
  • Future Nottinghamshire Council unitary authority under local government reorganisation proposals Report P18
  • Donors to the Raise the Roof Appeal and the Museums service volunteers Report 2.1, P17

Timeline

  • 1931: Abbey and park gifted to Nottingham City Museums Report 1.1
  • 2014: Purcell condition survey identifies urgent roof repairs
  • October 2025: Executive Board approved Phase 1 grant works Report P16
  • April 2026: MEND Round 5 grant agreement signed, conditional on operating as a museum for 20 years Report P16
  • 2026: Updated Peter Rogan Architects condition survey with appendix on stable block canopy and kitchen roof Report 1.4
  • Autumn 2026: Expression of Interest to be submitted to HE HARCF round 2 Report 2.4
  • Spring 2027: Outcome of HE HARCF round 2 expected Report 2.4
  • Within 2 years: Urgent priority repairs to stable block canopy and collapsed kitchen area roof Report 1.4
  • Next 5 years: Window for delivery of priority repairs identified by Peter Rogan Report 1.3
  • 3-year window: Funders' terms and conditions allow for full delivery of Phase 2 Report P14

Plain English for the jargon

  • ACE MEND Round 5: Arts Council England Museums and Exhibitions Development fund, round 5
  • HHF: Historic Houses Foundation, a heritage funder
  • HE HARCF: Historic England Heritage at Risk Capital Fund
  • NCM: Nottingham City Museums
  • LGR: Local Government Reorganisation
  • ITT: Invitation to Tender, a procurement procedure
  • ITQ: Invitation to Quote, a procurement procedure
  • MTFP: Medium Term Financial Plan
  • NLHF: National Lottery Heritage Fund
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item75

Resolved

Resolved to: (1) approve acceptance of the ACE MEND Round 5 grant and the Historic Houses Foundation grant awards which includes entering into the grant terms and conditions of each funding agreement; (2) authorise procurement of contracts for the Phase 2 work programme, and delegate authority to the Strategic Director of Communities to award the contracts and to spend the ringfenced NCM reserves, funds raised through the Raise the Roof Appeal and the secured grant funding awarded by ACE MEND Round 5 and HHF; (3) approve an additional grant application to Historic England Heritage at Risk Capital Fund (HE HARCF) to enable the programme to commence Phase 6 in conjunction with Phase 2 works; (4) if an HE HARCF grant award of up to £990,000 is secured, authorise procurement of contracts for the Phase 6 work programme, and delegate authority to the Strategic Director of Communities to award the contracts and to spend the grant fund. Reason for decisions: maintaining the Grade I listed site is important to meet the Council’s responsibilities as owner and avoid potential enforcement action if the buildings fall into disrepair; accepting grant funding from Arts Council England’s MEND Round 5 programme and the Historic Houses Foundation will enable Phase 2 repair works at Newstead Abbey to proceed. The funding, combined with existing museum reserves and donations raised through the Raise the Roof Appeal, means the project can be delivered without any impact on the Council’s Capital Programme; if successful, applying for up to £990,000 from Historic England’s Heritage at Risk Capital Fund would support urgent Phase 6 repairs. These works would be delivered alongside Phase 2 to achieve greater efficiency and reduced costs. Other options considered: do nothing. This would result in the grant awards being returned to the funders, Newstead Abbey would continue to deteriorate, and the repairs would remain the statutory responsibility of the Council under the Planning (Listed Buildings and Conservation Areas) Act, 1990, resulting in a major impact on the Council Capital Programme.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Executive Board – 22 September 2026

Subject: Newstead Abbey Programme of Repairs Phase 2 – Key Decision

Executive Member(s): Councillor David Mellen, Executive Member for Leisure, Culture and Tourism

Corporate Colin J Parr, Corporate Director of Communities, Environment & Director(s)/Director(s): Resident Services Summary of issues: Following the approval of the Executive Board (October 2025) to accept the Arts Council England’s Museum Estate and Development Fund (ACE MEND) Round 4 grant award of £1,482,882 and the National Lottery Fund grant of £249,828 Phase 1 repair works have commenced on site at Newstead Abbey which includes replacing the life expired lead and copper roofs.

Since then, Nottingham City Museums (NCM) have been successful in securing two further grant awards totalling £1,616,861. Along with match funding from ringfenced reserves and a fundraising campaign, this achieves the capital to deliver Phase 2 works which includes replacing the life expired slate roofs.

The income breakdown for Phase 2 works is as follows: • Secured grant award from ACE MEND Round 5 - £ 1,550,747 • Secured grant from Historic Houses Foundation - £66,114 • Ringfenced NCM reserves – £218,000 (previously approved and in the capital programme) • Raise the Roof Fundraising Campaign - £100,000 • Phase 2 works total cost as outlined in external grant funding approvals - £1,934,861

There are 6 phases of work that urgently need delivering at Newstead which include:

• Phases 1-3: Urgent repairs to the fabric of the building, including re-roofing, to make it wind and watertight. • Phase 4: Replacement of life expired M&E (fire and security alarms, heating and electrics) to make the building safe and environmentally sustainable. • Phase 5: Alterations and improvements to current facilities to make them accessible for all (toilets, café, visitor route etc) • Phase 6: Urgent repairs to a collapsing parapet in the stable block courtyard and the reinstatement of a collapsed roof in the café courtyard area. This last phase is a recent addition due to the severity of the safety concerns with both areas. An additional grant for a maximum of £990,000 is being applied for to cover the cost of this additional phase which will need to be delivered as soon as possible and can be delivered in conjunction with Phase 2 works. No match funding is required. If terms of grant award change to this approval, a further report and approval will be necessary.

Recommendation(s): 1 To approve acceptance of the ACE MEND Round 5 grant and the Historic Houses Foundation grant awards which includes entering into the grant terms and conditions of each funding agreement.

2 To authorise procurement of contracts for the Phase 2 work programme, and delegate authority to the Strategic Director of Communities to award the contracts and to spend the ringfenced NCM reserves, funds raised through the Raise the Roof Appeal and the secured grant funding awarded by ACE MEND Round 5 and HHF.

3 To approve an additional grant application to Historic England Heritage at Risk Capital Fund (HE HARCF) to enable the programme to commence Phase 6 in conjunction with Phase 2 works.

4 If an HE HARCF grant award of up to £990,000 is secured, to authorise procurement of contracts for the Phase 6 work programme, and delegate authority to the Strategic Director of Communities to award the contracts and to spend the grant fund.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Newstead Abbey Programme of Repairs Phase 2Report 149 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 20 attended
BB
Beth BrownOfficer, expected
MC
Michael CareyClerk, expected
SF
Stuart FairOfficer, expected
JH
Councillor Jay HayesCommittee Member, expected
PU
Councillor Patience Uloma IfedioraCommittee Member, expected
NJ
Nicki JenkinsOfficer, expected
HK
Councillor Helen KalsiCommittee Member, expected
NK
Councillor Neghat KhanChair, expected
LL
Lucy LeeOfficer, expected
SL
Councillor Sam LuxCommittee Member, expected
SM
Councillor Sulcan MahmoodCommittee Member, expected
NM
Neil McArthurOfficer, expected

All 20 on the meeting page

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies