What was decided
The Executive Board approved a single capital investment to undertake identified essential health and safety, statutory compliance and priority condition related works to the Council's community and youth assets.
Authority to approve individual drawdowns from the capital allocation was delegated to the Corporate Director of Growth and City Development, in consultation with the Executive Member for Strategic Regeneration, Property and Communications. Report 2.4
Drawdowns are subject to the agreed prioritisation framework, procurement compliance and confirmation that the proposed works are necessary to support the lease transition.
Why
The investment addresses identified building liabilities that would otherwise prevent or delay sustainable lease or operating arrangements, supporting the Council's financial sustainability objectives, reducing ongoing subsidy and protecting community and youth use where a viable occupier or delivery partner is able to take on future responsibilities. Report P10, 3.2
It delivers the remaining £0.300m of MTFP saving for community centres, addresses long standing maintenance issues caused by historic budget constraints, reduces ongoing financial liabilities and protects community and youth provision where suitable operators can take on future responsibility. Report 2.2, 2.3
Independent condition surveys have identified the works needed, with each centre having an indicative assessment of the repairs required to support sustainable occupation and implementation of the new lease arrangements. Report 1.7, 1.10
What happens next
Capital investment will be applied through a controlled drawdown process, with works prioritised where necessary to address essential health and safety, statutory compliance or essential building condition issues that would otherwise prevent the transition to sustainable lease arrangements. Report 1.10
The programme will not undertake full refurbishment or improvement works beyond the essential scope required to support safe occupation and lease completion, with a phased delivery programme linked to lease milestones. Report 1.10, P30
An Equality Impact Assessment was last reviewed on 16 August 2026 and will continue to be reviewed and updated before final decision implementation to reflect survey findings, the proposed investment approach and any asset specific implications. Report 3.5, 8.1
The money
- £0.300m Remaining Medium Term Financial Plan saving for community centres, to be delivered by the investment Report 2.2, P17
- £0.604m MTFP savings already applied to the 2024/25 and 2025/26 revenue budgets ahead of the new operating lease arrangements Report P48
- £300k Earmarked reserves funded from revenue resources to cover ineligible capital expenditure, subject to Section 151 officer approval Report 5.6
Options considered
- Rejected: Do nothing or defer the capital investment. Would delay FRI lease implementation, prolong repair and maintenance liabilities, put the remaining £0.300m MTFP saving at risk and fail to respond to condition survey evidence Report P17
- Rejected: Building closure and disposal. Could result in loss of community and youth provision, reduce access to neighbourhood based services and create wider demand pressures for the Council and partners Report P17
- Rejected: Maintain the existing subsidy model. Would not deliver the agreed MTFP saving, address long term financial pressure or regularise inconsistent lease, occupation and funding arrangements Report P18
- Rejected: Proceed with Full Repairing and Insuring leases without capital investment. Condition survey evidence has identified existing liabilities that may prevent or delay lease completion and risk lease negotiations failing, association failure and service disruption Report P19
- Rejected: Fund all identified works. Would increase the capital requirement beyond the proposed controlled allocation and would not represent a proportionate use of Council resources Report P20
Implications
- Financial: Investment supports the remaining £0.300m MTFP saving, removes ongoing subsidy and addresses historic maintenance backlogs caused by constrained budgets. Report 2.2, 2.3, 5.3
- Legal: Works should fall within the Council's landlord obligations, with regard to any pre existing agreements or arrangements with occupiers that may place obligations on them to contribute or cover particular costs. Report 6.1
- Equalities: An Equality Impact Assessment was last reviewed on 16 August 2026 and will continue to be reviewed and updated before final decision implementation, particularly where decisions may affect local access, children, families, older people, disabled residents or residents in areas of deprivation. Report 3.5, 8.1
- Risk: Risks include capital cost escalation, delays to lease completion and MTFP saving, associations unwilling to sign FRI leases, future building liabilities returning to the Council, reputational risk, procurement and governance risk, and Local Government Reorganisation uncertainty. Report P25, P28, P29, P30, P31, P32, P33, P34
- Staffing: Capacity and capability risk within Council services is recognised, with a dedicated delivery plan with named leads, milestones and escalation routes to be established and regular reporting to the relevant senior governance group. Report P35
- Other: State subsidy or grant control compliance may need to be confirmed for any repair incentive or works funding structured as support to associations. Report P37
Who and where
- Community associations occupying Council community centres and youth assets citywide Report 1.3, 1.4, 3.4
- Voluntary, community and youth sector delivery partners and future operators identified through the Expression of Interest process for vacant or transitioning assets Report 1.8, 3.3
- Children, young people, families, older people, disabled residents, residents in areas of deprivation and groups relying on accessible neighbourhood provision who use community and youth centres Report 3.5
- Residents across all wards of Nottingham Report P70
Timeline
- 21st January 2025: Previous Executive Board report addressing community and library provision Report 1.2
- 18th March 2025: Executive Board approved the Full Repairing and Insuring lease model for community centres and libraries Report 1.2, 1.6
- August 2026: First Full Repairing and Insuring lease completions Report 1.9
- 16 August 2026: Equality Impact Assessment last reviewed Report 3.5, 8.1
- early autumn 2026: Remaining Full Repairing and Insuring leases expected to be taken up Report 1.9
- 2026-09-22: Executive Board decision approving the single capital investment
Plain English for the jargon
- Full Repairing and Insuring (FRI) lease: A lease where the tenant is responsible for all repairs, maintenance and insurance of the building, rather than the landlord.
- Medium Term Financial Plan (MTFP): The Council's multi year budget and savings plan.
- Corporate Landlord: A model where the Council manages its property assets centrally and consistently across the estate.
- Expression of Interest process: A process used to identify community or voluntary sector organisations capable of operating vacant or transitioning assets for community benefit.