Resolved
RESOLVED – That the proposals be approved and new vehicles be purchased from 2019/20 onwards.
Cabinet approved this item on Monday 25 February 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the proposals be approved and new vehicles be purchased from 2019/20 onwards.
1.1Oldham Council introduced the Fleet Replacement Programme (FRP) in 2012/13 in accordance with the strategy approved by cabinet on 6th February 2012. The objective was to replace leased and hired vehicles gradually with purchased vehicles that would have a useful economical life ranging from 3 to 7 years. Since then Fleet Management has carried out this policy whenever a vehicle is due to be replaced.
1.2The programme is now in its seventh year of operation and the purpose of acquiring vehicles by purchasing rather than leasing has been fully realized. A requirement for hired vehicles still exists but this is restricted to shorter term vehicle needs i.e. normally of six months duration or less. This gives flexibility to the programme of vehicle usage and allows the service to meet business needs in a dynamic, supportive manner.
1.3A report was submitted to the Capital Investment Programme Board (CIPB) in March 2016 outlining a proposed 5 year vehicle programme and associated funding requirement. The report highlighted the need for increased capital investment from 2019/20 onwards and the CIPB noted the identified funding requirement at that time.
1.4The point has now been reached where a significant number of Fleet vehicles need to be replaced because they have reached the end of their economic useful lives. Replacement is due to begin in 2019/20.
2 Current Position
2.1Since the FRP was introduced (and by the end of the current financial year), the Council will have acquired 121 Fleet assets at a combined cost of £5,541k. The details are summarized in the table below (also see Appendix 1 for a more detailed schedule analysed by asset type).
Total Fleet Spending & Number of Vehicles Acquired 2012/13 to 2018/19
Spend No. Financial Year £’000 Acquired 2012/13 2,573 40 2013/14 1,011 18 2014/15 609 18 2015/16 523 21 2016/17 107 8 2017/18 349 8 2018/19 (forecast for year) 369 8 Total 5,541 121
2.2The unused balance of funding remaining from the original FRP and still available to purchase new vehicles is forecast to be £456K by year end 2018/19.
2 2.3 A review has taken place of the Fleet spending requirement for the next 5 years commencing 2019/20. The cost of purchasing these vehicles is estimated at £5,570K. A summarised annual breakdown of this is shown in the table below and a more detailed analysis by vehicle type is included at Appendix 2.
Projected Spend Summary and Funding Position Financial Years 2019/20 to 2023/24
Projected Available Cumulative Financial Spend Funding Shortfall Year £’000 £’000 £’000
2019/20 4,165 456 (3,709) 2020/21 1,019 - (4,728) 2021/22 42 - (4,770) 2022/23 302 - (5,072) 2023/24 42 - (5,114) Total 5,570 456
The above table shows that planned spending over the next five years exceeds the available capital resource by £5,114k.
2.4The first tranche of spending is the planned replacement of 18 refuse collection vehicles at an estimated cost of £3,186k in Autumn 2019.
2.5The estimated economic life of the assets to be acquired ranges from four to seven years. The required investment analysed by economic life is shown in the following table:
Asset Cost Analysed by Economic Life Expectancy
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Fleet Replacement ProgrammeReport | 454 KB | DownloadRead as text |
Follow Cabinet at Oldham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2026 | MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. | Approved | Open |
| 23 Mar 2026 | Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... | Noted | Open |
| 23 Mar 2026 | Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... | Approved | Open |
| 23 Mar 2026 | Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... | Decided | Open |
| 23 Mar 2026 | Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.