Extension of the Current Commissioning Arrangements for Care at Home
ApprovedExecutive1 paper
AI summaryOldham Cabinet approves three month extension of Care at Home, Extra Care and Night Provision contracts from 1 April to 30 June 2026, with new contracts to start 1 July 2026, at an estimated cost of £5.47m.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedContracts now run to 30 June 2026
Money£5.47mEstimated cost of three month extension
What happens next1 July 2026New contracts to commence
Who it affectsAdult social care usersAround 950 adults and 159 Extra Care residents
What was decided
Cabinet approved a three month extension of the current Care at Home, Extra Care and Night Provision contracts from 1 April 2026 to 30 June 2026 at an estimated cost of £5.47m. Report P12
Cabinet authorised the new contracts to commence on 1 July 2026. Report P13
Why
The current contracts expire on 31 March 2026 and a full tender process for new arrangements is already underway but cannot be completed in time for a safe transition. Report P1, P2, P3
Procurement timelines shifted because the tender submission deadline was extended to 19 December 2025, and evaluation, moderation and a safe mobilisation period are still needed. Report P5, 2.1, 2.2, 2.3
Officers say an extension is required to meet Care Act 2014 duties, protect around 950 Care at Home users, 159 Extra Care residents and night care users, and avoid service disruption. Report P3, 3.2, P50
What happens next
Tender evaluation runs from 5 January to 27 February 2026, with the Contract Award Notice due on 6 March 2026 and formal contract award on 19 March 2026. Report 2.2, P28, P29, P30
A mobilisation period is scheduled from 23 March to 30 June 2026, covering TUPE processes, operational planning and care plan reviews. Report 2.3, P31
New Care at Home, Extra Care and Night Provision contracts will go live on 1 July 2026. Report P32
The money
£5.47m Total estimated cost of the three month extension (per decision and Table 1) Report P8
£5.48m Total estimated cost of the three month extension (per Financial implications section) Report 6.1
£4.90m Care at Home share of three month extension Report P44
£0.55m Extra Care Housing share of three month extension Report P44
£0.03m Night Care share of three month extension (financial section) Report P44
£122,207.84 Night Care annual cost (executive summary) Report P4
£122,507.84 Night Care annual cost (background section) Report 1.2
£153m~ Total contract life spend across the three services Report P8
Options considered
Rejected: Option 1: Allow the existing Care at Home, Extra Care and Night Provision contracts to expire on 31 March 2026 without extension. Would leave the Council without a lawful mechanism to deliver essential adult social care, breach Care Act 2014 duties, and put vulnerable residents at risk Report 3.1, 3.2
Chosen: Option 2: Proceed with the full procurement exercise and approve a three month extension from 1 April 2026 to 30 June 2026, with new contracts starting 1 July 2026. Allows lawful and uninterrupted service delivery and provides time for safe mobilisation, TUPE processes and quality checks Report 3.3, 3.4, P38, 4.1, 4.2
Implications
Legal: The modification is permitted under PCR 2015 Regulation 72(1)(b) and the £5.47m value is well below the 10% threshold, with no change to the overall nature of the services. Report P9, 7.1, P54, P57
Financial: The £5.47m extension will be funded from the Adult Social Care allocated budget for 2026/27, with no anticipated impact on the Medium Term Financial Strategy beyond planned 2026/27 expenditure. Report P45, P46
Legal: Subject to Finance confirming budget availability, there are no legal objections to approving the extension and issuing the required modification documentation. Report P51
Equalities: An equality impact assessment applies as per the previous Cabinet report, with no changes. Report 10.1
Risk: Failing to approve the extension would risk service disruption, potential breaches of statutory duties under the Care Act 2014, and could lead to higher costs from emergency provision. Report P47
Staffing: TUPE processes are underway as part of the procurement exercise; no other HR implications identified for the extension itself. Report 9.1, P64
Other: All existing providers of Care at Home, Extra Care and Night Care have confirmed agreement to the three month extension, and the wider provider market has been informed of the new 1 July 2026 start date. Report 5.1
Who and where
Around 950 adults receiving Care at Home, with approximately 10,850 hours of care delivered each week Report P4, 1.2
159 individuals receiving Extra Care Housing support, with 7,866 hours delivered each week Report P4, 1.2
Service users of Night Care provision Report P4, 3.2
Existing Care at Home, Extra Care and Night Care providers Report 5.1, 1.1
Prospective providers who submitted 117 formal tenders from 572 expressions of interest Report 2.2
Workforce affected by TUPE transfer arrangements during mobilisation Report 2.3, 9.1, P64
Timeline
1 April 2019: Current Care at Home, Extra Care and Night Provision contracts commenced Report P1, 1.1
5 November 2025: Invitation to Tender published for new contracts Report 2.1, P25
19 December 2025, 12:00: Extended deadline for ITT submissions, tender closed Report 2.1, 2.2, P27
5 January to 27 February 2026: Tender evaluation period Report 2.2, P28
6 March 2026: Contract Award Notice to be published Report 2.2, P29
8 working days from 6 March 2026: Standstill period, concluding mid March 2026 Report 2.2, P30
19 March 2026: Formal contract award expected Report 2.2, P30
23 March 2026: Mobilisation period for new contracts begins Report 2.3, P31
23 March 2026 to 30 June 2026: Mobilisation period for new contracts, running alongside extension Report 2.3, P31
31 March 2026: Original expiry date of current contracts, now extended Report P1, 2.4
1 April 2026 to 30 June 2026: Three month extension of current contracts Report P12, P32
1 July 2026: New Care at Home, Extra Care and Night Provision contracts go live Report P13, P32
Plain English for the jargon
Care at Home (CAH): Council funded care delivered in people's own homes to support independence and daily living.
Extra Care Housing: Supported housing with on site care services, currently delivered by a single provider across six schemes in Oldham.
Night Provision: Overnight care support, currently delivered through a legacy block contract with one provider.
Flexible Purchasing System (FPS): An older procurement route used to commission these services since 2019, no longer available for new awards below threshold under the Procurement Act 2023.
Dynamic Purchasing System (DPS): An electronic procurement route similar in concept to the previous FPS.
TUPE: Transfer of Undertakings (Protection of Employment) regulations, governing the transfer of staff when a service changes provider.
PCR 2015: Public Contracts Regulations 2015, the procurement rules that continue to apply to the existing contracts.
Procurement Act 2023: New procurement legislation under which the Council is required to run an Open or Competitive Flexible Procedure for new awards.
ITT: Invitation to Tender, the formal document seeking competitive bids from providers.
PCR 2015 Regulation 72: Provision allowing modification of an existing contract without a new procurement procedure in defined circumstances, subject to value thresholds.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
That the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Provision from 1 st April 2026 to 30 th June 2026 , at an estimated cost of £5.47m . 2. That the Cabinet authorises the new contracts to commence on 1 st July 2026 .
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
The Council's current contractual arrangements for the delivery of Care at Home, Extra Care and Night Provision support services commenced on 1 April 2019 and, following the approved two-year extension option, are due to expire on 31 March 2026.
Approval to undertake a full open tender process for new Care at Home, Extra Care and Night provision support services was granted by Cabinet on 22nd September 2025, as set out in the Cabinet report titled, “Future commissioning Arrangements for Care at Home, Extra Care support and Night Provision support services.” (Original Key Decision Reference: HSC-13-25) The tender process for Care at Home, Extra Care and Night Provision services is underway. However, due to necessary changes in procurement timelines including extended tender submission deadlines which enables full engagement from prospective providers, evaluation and moderation requirements, and the need to ensure a safe mobilisation period for any new providers the recommissioning timetable has needed to be revised.
To ensure continuity of care for vulnerable residents, compliance with our statutory duties under the Care Act 2014, and a safe and well-managed transition to new contractual arrangements, approval is sought to extend the current contracts for a further three months until 30 June 2026, with the new contracts commencing 1 July 2026.
Executive summary
Care at Home (CAH) services provide essential care and support to approximately 950 adults across Oldham, with around 10,850 hours of care delivered each week. The annual expenditure on CAH services is approximately £19.6 million. In addition, Extra Care supports around 159 individuals weekly, delivering approximately 7866 hours weekly at an annual cost of £2.2 million. Night Care provision, currently delivered through a legacy block contract an annual cost of £122,207.84 These services underpin Oldham’s Adult Social Care vision of supporting people to be independent healthy save and well within their own homes.
The invitation to tender is now closed, however, procurement timescales have shifted due to; Provider-requested extension of tender submission deadline Increased volume and complexity of clarification questions Unknown volume of tender submissions Need for extensive evaluation and moderation Need for a safe mobilisation period to prevent disruption
Given these factors, a three month extension is required to ensure continuity, protect residents and enable safe and orderly transition.
Table 1 shows the estimated spend for a 3-Month extension (April–June 2026);
Contract Life Annual Spend Service 3-Month Cost Spend (7 years) Care at Home £137.2m £19.6m £4.9m Extra Care Housing £15.4m £2.2m £0.55m Night Care £854k £122k £28k Total £153m~ £21.9m £5.47m Table 1
The variation is in line with regulation 72 of PCR2015 and the modification is below the 10% of the contract value.
This expenditure is essential to maintain statutory provision.
Recommendations
Option 2 is the Preferred Option
1. Approve a three-month extension of the current contracts for Care at Home, Extra Care and Night Provision from 1 April 2026 to 30 June 2026, at an estimated cost of £5.47m.
2. Approve that the new contracts commence on 1 July 2026.
2 1 Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe...
Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.