Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026
ApprovedExecutive1 paper
AI summaryOldham Cabinet approves extension of the Adult Social Care Service Level Agreement with Miocare Group CIC to 31 March 2028, with flexibility to vary as the Target Operating Model develops.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedExtend Miocare SLA and endorse buy-back SLAs
MoneyNo figures stated in report
What happens next1 April 2026 to 31 March 2028Agreement effective then, with possible earlier end
Who it affectsAdults receiving social care in OldhamAnd Miocare Group CIC, a council-owned company
What was decided
Cabinet approved the refreshed Service Level Agreement with Miocare Group CIC, which updates the provisions governing the relationship and service delivery between the Council and Miocare, and allows for variation as the future focus of Miocare becomes clearer through the Adult Social Care Target Operating Model. Report P4, 3.3
Cabinet endorsed wider Council corporate services working with Miocare to develop Service Level Agreements and specifications for services Miocare buys back from the Council. Report P2, P4, 2.5
Why
The Council originally entered the SLA in 2013 with Oldham Care and Support Ltd, later restructured into Miocare Group CIC in 2016, and has retained ownership due to instability in the care sector, workforce challenges, the pandemic, and uncertainty over national funding and charging reforms. Report 1.1, 1.2
The 2023 SLA included an option to extend for up to two further years, and the preferred option provides a clear, compliant agreement with flexibility to develop in line with the Adult Social Care Target Operating Model, with the least risk to the Council. Report 1.4, 3.3, 12.1
What happens next
Put in place further Service Level Agreements and specifications between Miocare and Council departments that provide support services Miocare buys back. Report 2.5, P2, 3.3
A strategic review of Miocare's local authority owned company status is due to conclude in 2026/27, with recommendations taken to an options appraisal. Report 2.6
The Extra Care Housing service is going through moderation and evaluation under a separate tender, with current services due to expire Summer 2026. Report 2.1
Options considered
Rejected: Option 1: Do not extend the SLA and do not develop buy-back SLAs.. Would leave the Council and Miocare without a compliant, up to date agreement, causing lack of clarity. Report 3.1, P17
Rejected: Option 2: Delay extending the SLA until Miocare's future focus is clarified.. Carries the same risks as Option 1 and would leave uncertainty during a long implementation period for the Target Operating Model. Report 3.2, P19
Chosen: Option 3: Extend the SLA and develop buy-back SLAs.. Preferred option: updates provisions, allows variation as the Target Operating Model is implemented, and poses the least risk. Report 3.3, P21, 12.1
Implications
Legal: The direct award to Miocare is permitted under the Teckal exemption in the Public Contract Regulations 2015 and the Procurement Act 2023, as the Council exercises control similar to its own departments and more than 80% of Miocare's activities are for the Council, with no direct private capital participation. Report 5.1, 5.2, 5.4, 10.1
Financial: The redrafted agreement runs from 1 April 2026, with provision to extend for a further two years (2026/27 and 2027/28). Charges are set out in Schedule 2 and reviewed periodically. Report 4.2
Staffing: Option 3 provides clarity for Miocare management and their workforce; no other specific workforce issues identified. Report 6.1
Risk: The preferred option is judged the least risk to the Council, providing a clear agreement, consistency, continuity, and flexibility to develop with the Target Operating Model. Report 12.1
Other: Miocare is a tenant of several Council-owned buildings under longstanding Tenancy at Will documents; facilities and property services are recharged through the Corporate Landlord model, with no specific implications at present. Report 11.1
Equalities: No Equality Impact Assessment or Oldham Impact Assessment completed. Report 16.1, 17.1
Who and where
Adults in Oldham receiving social care services delivered through Oldham Care and Support Ltd (the teckal company), including bed-based reablement, community enablement, complex needs, helpline and response, managed services, and continuity of care provision.
Miocare Group CIC, its management and workforce. Report 6.1, 1.1
Council departments that provide support services bought back by Miocare, who will work on new SLAs and specifications. Report 2.5, P2
Timeline
1 April 2026: Redrafted SLA becomes effective.
2026/27: Strategic review of Miocare's local authority owned company status due to conclude, with options appraisal to follow. Report 2.6
Summer 2026: Current Extra Care Housing services due to expire, pending the outcome of a separate tender. Report 2.1
31st March 2028: Extended SLA expires, or sooner if alternative developments are progressed. Report 1.4
Plain English for the jargon
Miocare Group CIC: The Council-owned adult social care company, originally Oldham Care and Support Ltd (2013), restructured and renamed in 2016, delivering services through Oldham Care and Support Ltd (teckal company) and Miocare Services Ltd (trading arm).
Teckal company / Teckal exemption: An in-house entity controlled by a public authority such that contracts can be awarded directly without competitive tender, named after the Teckal case; set out in the Public Contract Regulations 2015 and Schedule 2, paragraph 2 of the Procurement Act 2023.
Service Level Agreement (SLA): An agreement setting out the services to be delivered, standards, and charges between the Council and Miocare.
Target Operating Model: The Council's emerging model for Adult Social Care, aligned to national reforms, under which Miocare's future focus is to be developed.
Buy-back services: Corporate or support services that Miocare purchases from the Council.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service Level Agreement updates the provisions governing the relationship and service delivery between the Council and Miocare Group CIC. The provisions allow for variation as the future focus of the Miocare Group becomes clearer through the implementation of the Adult Social Care Target Operating Model. 3. Endorses wider corporate services work with Miocare to develop Service Level Agreements and specifications of requirements for services Miocare buys back from the Council.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
The report seeks approval to extend the Service Level Agreement with Adult Social Care and Miocare Group CIC, for a range of services provided.
The report also seeks a commitment for wider Council colleagues to work with Miocare Group CIC to develop Service Level Agreements and specifications of requirements for those corporate services that Miocare Group CIC “buys back” from the Council.
Recommendations
Cabinet members are asked to:
Approve the Service Level Agreement with Miocare Group CIC. The refreshed SLA updates the provisions governing the relationship and service delivery between the Council and Miocare Group CIC. The provisions allow for variation as the future focus of the Miocare Group becomes clearer through the implementation of the Adult Social Care Target Operating Model. Endorse wider corporate services work with Miocare to develop Service Level Agreements and specifications of requirements for services Miocare buys back from the Council. Cabinet 23 March 2026
Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026
Background
1.1On 1st October 2013, the Council entered into a Service Level Agreement with Oldham Care and Support Ltd, following the creation of the company as a local authority trading company, from what had previously been “in-house” adult social care services. This agreement was superseded in 2015 following a restructuring of the company, with the parent company Oldham Care Services Ltd, and two subsidiaries, Oldham Care and Support Ltd (the “teckal company) and Oldham Care and Support at Home (the trading arm). In April 2016, the company name changed to Miocare Group Community Interest Company, and services were delivered via sub-contract arrangements through Oldham Care and Support Ltd (the teckal company) and Miocare Services Ltd (the trading arm).
1.2It was originally envisaged that during the initial term of the agreement, decisions about company ownership would be made, which may lead to the company ultimately operating as a completely independent organisation, no longer in council ownership. However, since then there has been unprecedented levels of instability in the care sector, exacerbated in more recent times by significant workforce challenges, the covid- 19 pandemic, and the national developments of significant transformation plans in respect of health and social care provision, and certain levels of uncertainty surrounding funding and charging reforms. As a result, it has felt prudent to retain Council ownership of the company.
1.3Towards the end of 2021, as part of a wider review of Council resources and taking into consideration the prevailing market conditions and future vision with a focus on prevention and strength-based approaches, initial consideration was given to the potential options with regard to the future of MioCare and the services delivered by the company. The outcome of these considerations was to retain the current position in respect of MioCare, but to refresh the Service Level Agreement and specifications, to support a clearer view of future opportunities for and development of the MioCare delivered services, aligned to the emerging Target Operating Model for Adult Social Care and the widespread national reforms.
1.4In 2023 the refreshed Service Level Agreement alongside a contract were put in situ, for a period of three years with the option to extend for up to two further years. This report recommends utilising the original provision to extend the SLAs, expiring 31st March 2028, or sooner should alternative developments be progressed.
2. Current Position
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe...
Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.