Resolved
RESOLVED – That: The actual 2019/20 prudential and treasury indicators presented in this report be approved. The annual treasury management report for 2019/20 be approved. The report be commended to Council.
Cabinet approved this item on Monday 24 August 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That: The actual 2019/20 prudential and treasury indicators presented in this report be approved. The annual treasury management report for 2019/20 be approved. The report be commended to Council.
The Council is required by regulations issued under the Local Government Act 2003 to produce an annual treasury management review of activities and the actual prudential and treasury indicators for 2019/20. This report meets the requirements of both the CIPFA Code of Practice on Treasury Management (the Code) and the CIPFA Prudential Code for Capital Finance in Local Authorities (the Prudential Code).
During 2019/20 the minimum reporting requirements were that the full Council should receive the following reports: • an annual treasury strategy in advance of the year (approved 27 February 2019) • a mid-year (minimum) treasury update report (approved 8 January 2020) • an annual review following the end of the year describing the activity compared to the strategy (this report)
The regulatory environment places responsibility on Members for the review and scrutiny of treasury management policy and activities. This report is therefore important in that respect, as it provides details of the outturn position for treasury activities and highlights compliance with the Council’s policies previously approved by members.
The Council confirms that it has complied with the requirements under the Code to give prior scrutiny to the treasury strategy and the mid-year update. The Audit Committee is charged with the scrutiny of treasury management activities in Oldham and reviewed the content of this annual report at its meeting of 21 July 2020 prior to its consideration by Cabinet. The Committee was content to commend the report to Cabinet (to ensure full compliance with the Code for 2019/20). Executive Summary
During 2019/20, the Council complied with its legislative and regulatory requirements. The key actual prudential and treasury indicators detailing the impact of capital expenditure activities during the year, with comparators, are as follows:
2018/19 2019/20 2019/20 Actual prudential and treasury Actual Revised Actual indicators £'000 £'000 £'000 Actual capital expenditure 48,564 63,945 54,383
Total Capital Financing Requirement: 493,880 491,011 472,377
Gross borrowing 147,846 167,843 167,843 External debt 394,456 403,338 403,709
Investments · Longer than 1 year 15,000 15,000 15,000 · Under 1 year 69,900 52,000 103,120 · Total 84,900 67,000 118,120
Net Borrowing (Gross borrowing less investments) 62,946 100,843 49,723
As can be seen in the table above, actual capital expenditure was less than the revised budget estimate for 2019/20 presented within the 2020/21 Treasury Management Strategy report considered at the Council meeting of 26 February 2020. The outturn position was significantly less than the £84.332m original capital budget for 2019/20 as approved at Budget Council on 27 February 2019.
During the course of the year the Capital Programme saw substantial rephasing. A number of major schemes including a number of schools’ schemes in the Children’s Service Directorate were rephased. The Asset Management (Education) Essential Condition Works provision was realigned into future years to align with other works being undertaken at schools. Housing Revenue Account (HRA) schemes were re-phased into 2020/21 to align with the latest HRA Strategy. In addition, the ‘Creating a Better Place’ Strategy required a number of existing regeneration projects to be reviewed and rephased to align to the long-term vision of the strategy. Also, during the year, the Information Technology (IT) Capital Strategy, the Strategic Roadmap was reviewed. The outcome was a rephasing of resources to ensure that the Council’s future IT offer takes account of new innovations in IT and creates efficiencies that will complement future ways of working.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Treasury Management Review 2019/20Report | 1.6 MB | DownloadRead as text |
Follow Cabinet at Oldham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2026 | MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. | Approved | Open |
| 23 Mar 2026 | Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... | Noted | Open |
| 23 Mar 2026 | Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... | Approved | Open |
| 23 Mar 2026 | Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... | Decided | Open |
| 23 Mar 2026 | Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.