Resolved
RESOLVED -That the Cabinet would consider the commercially sensitive information contained at Item 11 of the agenda before making a decision.
Cabinet decided this item on Monday 25 January 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED -That the Cabinet would consider the commercially sensitive information contained at Item 11 of the agenda before making a decision.
Prior to the Covid-19 (CV19) lockdown commencing, the Alexandra Park Eco Centre project had progressed to RIBA Stage 3, and subsequently obtained planning approval on 22nd May 2020. An Outline Business Case (OBC) was submitted in June 2020, and following detailed scrutiny of the proposals the project was unfortunately deemed to be financially unviable for delivery as one complete project, as the long-term revenue implications for the proposals needed significant subsidy, which could not be justified given the current financial climate.
However, the ambition for embracing green technologies and sustainable property design solutions remains – and due to the severe dilapidation issues noted with the corporate building and accommodation of staff / teams within Alexandrea Park, urgent works have been declared essential to ensure compliance with workplace safety and to provide an early phase of the masterplan on an accelerated delivery programme.
As a result of this, five options were explored to provide an indication of what could be included as part of the initial phase to help rectify the building dilapidation issues. Part B of the report provides significantly more information on each of the options alongside the project objectives, benefits, issues, risks and revenue implications, however in summary:
Option 1 - Do nothing – only undertaking urgent reactive maintenance to maintain the buildings (not considered to be a feasible option given the current deteriorating condition of the depot building).
Option 2 – Do minimum - undertake urgent backlog maintenance on the existing building to ensure it is compliant and safe for teams / services to use. (This would need significant levels of investment; it would cause considerable disruption to the services and wouldn’t deliver any of the ambitions for green technologies or efficiency / sustainability).
Option 3 – Progress an early phase of the masterplan for the Eco Centre including the green technology power solutions within the new office building.
Option 4 – Build and deliver a new office with conventional/mains gas and electricity supply to help keep construction costs to a minimum (this helps support the building dilapidations, but does not allow opportunities to introduce or accelerate any of the eco / green technologies).
Option 5 – Install emergency portacabins powered by electricity to provide a temporary / efficient solution to ensure staff were working in safe and compliant accommodation. (This option fails to tackle any of the longer term building dilapidation issues and doesn’t introduce any of the green or sustainability ambition).
Original proposal (masterplan) – Deliver a new office, a new glasshouse, a green energy centre and substantial external works – this is the entire project masterplan but it has significant financial viability challenges to deliver as one entire project.
An application has been made to the Decarbonisation Fund for grant towards the cost of an air source heat pump system to support the accelerated delivery of option 3 to kickstart the first phase of the Eco Centre ambitions. If successful, this system will, along with mains electricity, provide heat and hot water for the new office. The remaining structures within the depot that require power will be supplied via the current mains gas and electricity system.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Alexandra Park Eco CentreReport | 260 KB | DownloadRead as text |
Follow Cabinet at Oldham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2026 | MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. | Approved | Open |
| 23 Mar 2026 | Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... | Noted | Open |
| 23 Mar 2026 | Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... | Approved | Open |
| 23 Mar 2026 | Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... | Decided | Open |
| 23 Mar 2026 | Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.