RESOLVED – That: 1. Authority be delegated to the Deputy Chief Executive in consultation with the Leader to award the Strategic Partnership Agreement and Reserve Supplier Agreement, in consultation with the Director of Finance and Director of Legal Services. 2. Authority be delegated to the Director of Environmental Management in consultation with the Director of Finance, and the Director of Legal Services to award the individual call off contracts for the separate works packages under the Strategic Partnership Agreement and Reserve Supplier Agreement. 3. Authority be delegated to the Director of Legal Services to affix the Council’s seal to the Strategic Partnership Agreement and Reserve Supplier Agreement any incidental and ancillary documentation and also to the individual call off contracts under the Strategic Partnership Agreement and Reserve Supplier Agreement any incidental and ancillary documentation.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
To delegate authority to Helen Lockwood (Deputy Chief Executive) in consultation with the Leader to award the Accessible Oldham Strategic Partnership Agreement and reserve supplier agreement, and delegate authority to the Director of Environmental Management in consultation with the Director of Finance and the Director of Legal Services to award the individual call off orders for the separate projects, due to the urgency to deliver a programme of works in accordance with the funding timeline constraints.
Executive summary
The Transportation and Planning Team in collaboration with Unity Partnership have successfully bid for several capital funded multi-disciplinary highway improvement programme of work, namely Growth Deal 3 (GD3) and Mayor’s Cycling and Walking Challenge Fund (MCF). The funds (cumulatively amounting to circa £16.5m) are managed by Transport for Greater Manchester (TfGM) under the overarching administration of Department for Transport (DfT).
For Oldham Council to deliver the programme it was considered necessary to seek a mid- term (4 years) Strategic Partner (Partner) to assist the Delivery Team at key stages of the design and construction work. The current method of delivery of the highway construction work is described below which can take upwards of 12 weeks from tender stage to commencement on site. Ultimately, in order to deliver the GD3 and MCF programme within the set timeframe, a more streamlined method of procuring construction work is required. The intention is that individual projects will be procured via a Call Off procedure under the Strategic Partnership Agreement. This will require Director sign off (in liaison with the Directors of Finance and Legal Services) rather than an individual Cabinet report for each element of work.
The Accessible Oldham Strategic Partnership Agreement is scheduled to be advertised by the Commercial Services Team before the end of the year and it is expected to be available for use in March/April 2021. An initial sift will be undertaken with a shortlist of three Contractors being invited to enhance/review their respective bids with one being awarded as the outright winner.
Recommendations It is recommended that delegated authority is given to:
The Deputy Chief Executive in consultation with the Leader to award the Strategic Partnership Agreement and Reserve Supplier Agreement, in consultation with the Director of Finance and Director of Legal Services The Director of Environmental Management in consultation with the Director of Finance, and the Director of Legal Services to award the individual call off contracts for the separate works packages under the Strategic Partnership Agreement and Reserve Supplier Agreement. The Director of Legal Services to affix the Council’s seal to the Strategic Partnership Agreement and Reserve Supplier Agreement any incidental and ancillary documentation and also to the individual call off contracts under the Strategic Partnership Agreement and Reserve Supplier Agreement any incidental and ancillary documentation.
2 Cabinet 22nd February 2021
Accessible Oldham Strategic Partnership Agreement
Background
1.1The key Accessible Oldham scheme objectives are to: Facilitate development and the regeneration of Oldham Town Centre; Improve the attractiveness of the town centre for pedestrians and cyclists; Maintain the integrity of the highway network within and around the town centre.
The objectives align to the Growth Deal 3 priorities and regional initiatives such as the GM 2040 Transport Strategy and Growth and Reform Plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe...
Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.