It was agreed at CIPB that confirmation of the additional requirement for Basic Need Funds would be reported to Cabinet on completion. Subject to Cabinet approval of the recommendations in this report, Kier would be issued a contract award. This would be based on the final price which would be reviewed and verified by the Council’s consultant cost estimator. There continued to be a pressing need for additional places in secondary schools within the borough. North Chadderton is one of the boroughs highest performing and over-subscribed schools. North Chadderton agreed a temporary increase in the school PAN from 240- 270 at the request of the LA in order to secure sufficient school places in the borough. Options/alternatives considered Option 1 - Approve the cost for a 1 FE expansion to North Chadderton School. Option 2 - Do not approve the cost of expansion by 1 FE for North Chadderton School. This would not fulfill the Local Authority’s a statutory obligation to provide the necessary additional places in East Oldham by 2020. RESOLVED – That the Cabinet would give consideration to the commercially sensitive recommendations as contained at Item ****of the agenda.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
Cabinet approval is required to allocate Basic Needs Funding previously identified to facilitate a one form entry (1FE) expansion at North Chadderton School. This will enable a new - 3 storey, six classroom science block, sports changing and teaching pavilion, library classroom, parking and hard play extension- all of which are necessary to the scheme.
Recommendations
That Cabinet approves the recommendations set out in Part B of the report. North Chadderton School 1 FE Expansion
Background
1.1North Chadderton School is located in the North Chadderton ward of Oldham and is part of the Oak Trust. As part of the Basic Needs Programme of Work, Cabinet gave its approval in April 2018 for the 1 FE expansion through the basic needs fund, based on a £3.4m cost estimate.
1.2It has previously been reported to CIPB July 2020 that the previous design and build ITT exercise concluded without an appointment as the submissions did not meet with the Council’s procurement requirements. CIPB was also informed that the tender bid was significantly above the original cost estimate previously approved and the current pandemic has exacerbated the delay and potential costs of the proposed scheme. Furthermore, the Council’s cost advisors have confirmed that the cost of building materials are running well above inflation and this trend is expected to continue over the next 18 months.
1.3The proposed works has since been retendered in accordance with the Council’s procurement rules through a 2 Stage Design and Build procurement strategy. A professional team was appointed to complete the new tender package and Kier were also appointed under a Pre-Construction Services Agreement. It was agreed at CIPB that confirmation of the additional requirement for Basic Need Funds would be reported to Cabinet on completion.
2 Current Position
2.2Subject to Cabinet approval of the recommendations in this report, Kier will be issued a contract award. This will be based on the final price which is due to be submitted on the 7th September. The final price will be reviewed and verified by the Council’s consultant cost estimator.
2.3There continues to be a pressing need for additional places in secondary schools within the borough. North Chadderton is one of the boroughs highest performing and over-subscribed schools. North Chadderton agreed a temporary increase in the school PAN from 240- 270 at the request of the LA in order to secure sufficient school places in the borough.
2.4These are school places required by the Council under their statutory duty. The Oak Trust are a local independent academy who do not have the capacity for direct delivery of capital works of this scale and nature. The Oak Trust have written to the Council, confirming agreement to the works, access and acceptance of the proposed building works at practical completion.
2.5It is intended that in managing the risk associated with this project, the Council will enter into a minor works contract with Kier to complete essential enabling works (site set up, early site works and playground replacement) at October half term 2021, having the benefit of previous funding approval and delegated authority to contract
2 at Cabinet (April 2018). The main contract award is due to be issued early November 2021.
3 Options/Alternatives
3.1Option One: Approve the cost for a 1 FE expansion to North Chadderton School.
3.2Option two: Do not approve the cost of expansion by 1 FE for North Chadderton School. This would not fulfill the Local Authority’s a statutory obligation to provide the necessary additional places in East Oldham by 2020.
The cost of this expansion is set out in Part B of this report
4 Preferred Option
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe...
Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.