Oldham Metropolitan Borough Council
Cabinet, Monday 28 February 2022 at 6.00pm

The former WH Shaws office and clock tower building, Diggle - Options Appraisal

Decided Executive 1 paper

Cabinet decided this item on Monday 28 February 2022. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED – That the Cabinet would consider the commercially sensitive information at Item 13 before making a decision.
Word for word from the decision Oldham published for this meeting. Source: committees.oldham.gov.uk

Follow this further

Built from Oldham's papers

What the report saysPro

Report to Cabinet

Reason for decision

Cabinet approval is required to confirm expenditure of the financial allocation made in the capital programme towards works relating to the former WH Shaws office and clock tower building, Diggle. In addition to delegate authority to the Director of Economy and Legal Services to progress appointments for priority works as set out in this report.

Recommendations

It is recommended that Cabinet;

i. Approve Option 2 ‘Envelope Repair’ as set out in this report. ii. Delegates authority to the Director of Economy to develop, consult, procure and arrange for the execution by the Director of Legal Services of any relevant contracts and incidental and ancillary documentation. Cabinet

Clock Tower, Diggle

Background

1.1The former WH Shaws office and clock tower building is a significant heritage asset which forms the gateway to the new Saddleworth School. As part of the Council’s recently approved Creating a Better Place agenda, the Grade II building has been transferred to the Council’s corporate estate.

2 Current Position

2.1Following a structural and a building survey, an options appraisal has now been completed.

2.2The option that is recommended has been formed on the basis that a viable long term use for the building is still to be determined and that the overall condition of the building is poor and will continue to deteriorate without further action beyond holding repairs.

2.3There is currently a capital allocation for works to the Diggle clocktower held as part of the Corporate Landlord Backlog Maintenance Capital Programme.

3 Options/Alternatives

3.1Options 1 Full Build Repair – Without a clear end-use for the building, this is not considered a viable option.

3.2Option 2 Envelope Repair – A programme that would aim to introduce the provision of mains services into the building and refurbish the external fabric of the building to meet modern design standards, providing long term protection to the building interiors – allowing the building to be mothballed whilst an appropriate end use is identified. This will require the appointment of an appropriate design team to develop and manage the works.

3.3Option 3 Holding Repairs - These repairs would be the minimum necessary to stabilise the rate of deterioration of the building and would include the roof and gutters, drying out the building and stabilising environmental conditions within. Holding repairs by their very nature address the most important defects in the building. However, these have a limited longevity as they do not address the core issues of continued deterioration. They are likely to require continued attention in the challenge against a continually degrading building fabric. Unless the building is to be disposed of on the open market, this option is not advisable.

4 Preferred Option

4.1Option 2 is the preferred option. It allows the building to be retained in a presentable condition that prevents further degradation and presents greater opportunities for

2 further development from its “shell and core” state. The financial expenditure required for Option 2 is not considered abortive as it would form part of the works for Option 1 if additional funding should subsequently be identified.

Consultation

5.1N/A.

Financial implications

6.1Capital Implications

6.2Revenue Implications

7 Legal Services Comments

7.1There are no specific legal implications to this decision provided that the Council’s Financial Procedure Rules are complied with.

7.2Any procurements/contracts conducted/entered into must be lawful and compliant with the Council’s Contract Procedure Rules and EU Regulations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The former WH Shaws office and clock tower building, Diggle: Options AppraisalReport 244 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 19 attended
SA
Shoab AkhtarCommittee Member, apologies
AC
Amanda ChaddertonCommittee Member, present
ZC
Zahid Chauhan OBECommittee Member, present
LD
Liz DroganSecretary, expected
PE
Paul EntwistleOfficer, expected
LG
Lewis GreenwoodOfficer, expected
AJ
Abdul Jabbar MBECommittee Member, present
HL
Helen LockwoodOfficer, expected
EM
Eddie MooresCommittee Member, present
SM
Shaid MushtaqCommittee Member, present
HR
Hannah RobertsCommittee Member, present
NR
Nicci RobinsonOfficer, expected

All 19 on the meeting page

More from Oldham Cabinet

All decisions
MeetingDecisionOutcome
23 Mar 2026 MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. Approved Open
23 Mar 2026 Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... Noted Open
23 Mar 2026 Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... Approved Open
23 Mar 2026 Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... Decided Open
23 Mar 2026 Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies