Resolved
RESOLVED -That the grant funding be accepted and the Council commence the works.
Cabinet decided this item on Monday 23 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED -That the grant funding be accepted and the Council commence the works.
That Cabinet accept the grant and the Council commence works. Under this option, the Council will enter into a partnership agreement with GMCA for disbursal of the grant, and the works will be carried out by the Spindles project team already appointed for the wider renovation programme at the site. Cabinet 23 January 2023
Public Sector Decarbonisation Scheme Phase 3a Grant Acceptance – Spindles
1.1The Public Sector Decarbonisation Scheme is a UK Government funded programme, administered by Salix.
1.2The Council has previously benefited from PSDS grant funding for two projects – LED lighting at Oldham Leisure Centre (circa £100K) and Air Source Heat Pumps at Alexandra Park Eco-Centre (circa £290K)
1.3In October 2021, the Council applied (via a GMCA consortium) to the PSDS3a funding round, for decarbonisation works at the Spindles, including the installation of roof and wall insulation, glazing, solar PV and heat pumps. The grant funding was not awarded at that time, due to the overall funding envelope being exceeded by the time Salix received Oldham’s application (via GMCA)
1.4However, in September 2022 Salix approached GMCA asking whether Oldham would still be looking for the funding, as the PSDS3a programme was underspent after the first 12 months of operation.
1.5The PSDS3a application form for Spindles has been updated to take into account changes to the proposed project over the past 12 months, and has now been approved by Salix, who have signed a Grant Agreement with GMCA for the grant funding. The actual grant amount received by GMCA from Salix will be £2,291,822. However, the GMCA will ‘top-slice’ this grant amount as a management fee (£138,468 or 6%) and the actual grant amount to be received from GMCA by Oldham will be £2,153,354.
1.6The decarbonisation works at the Spindles will contribute to the carbon neutrality targets set out in the Oldham Green New Deal Strategy and will also support the “A Clean and Green Future” priority set out in the Corporate Plan. They are also forecast to save around £45K annually in energy costs at the complex.
2 Current Position
2.1The Spindles project has been offered £2,153,354 in grant funding against a total project value of £3,956,223, requiring a match funding element from the Council of £1,802,869.
2.2The grant funding must be spent by 31st March 2025.
2.3Key to successful delivery of the project will be accurate and timely reporting to GMCA on progress and effective draw-down of the grant funding. This will in turn depend on a detailed understanding by the contractors delivering the scheme as to which items are grant eligible, itemised invoices as evidence, how the Council’s match funding for the scheme is accounted for, and robust assurance in terms of meeting the conditions of the grant. The Council will therefore need to ensure that appropriate governance is in place to support successful delivery of the grant-funded scheme.
2 3 Options/Alternatives
3.1Option 1: do not accept the grant. Under this option, the grant funding will not be accepted and the additional energy works proposed at the Spindles complex will not be implemented.
1.7Option 2: accept the grant and commence works. Under this option, the Council will enter into a partnership agreement with GMCA for disbursal of the grant, and the works will be carried out by the Spindles project team already appointed for the wider renovation programme at the site.
4 Preferred Option
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Public Sector Decarbonisation Scheme Phase 3a Grant Acceptance: SpindlesReport | 258 KB | DownloadRead as text |
Follow Cabinet at Oldham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2026 | MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. | Approved | Open |
| 23 Mar 2026 | Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... | Noted | Open |
| 23 Mar 2026 | Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... | Approved | Open |
| 23 Mar 2026 | Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... | Decided | Open |
| 23 Mar 2026 | Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.