That Cabinet approval is given to – 1. Cabinet approves a modification to extend those current CHWS Framework Agreements, detailed at Appendix A, for a term of 12-months, to allow sufficient time to robustly procure and mobilise a new CHWS framework arrangements from 3rd October 2024 and to apply an inflationary uplift to the charges payable under the Framework Agreements, as detailed in the submitted report. 2. The Cabinet delegates approval to the Deputy Chief Executive (Place), Director of Environment and the Director of Economy, as appropriate, to award call-off contracts under the Framework Agreement entered into under the CHWS framework arrangements, subject ... view the full minutes text for item 10.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
Current Framework Agreements for CHWS expired on 2nd October 2023 and there is insufficient time to develop and complete a tender process for a replacement framework arrangement that meets service delivery requirements and wider corporate objectives (e.g. social value) prior to the expiry of the agreements. There is also insufficient time to conduct the extensive market engagement required to ensure an appropriate procurement model is deployed to attract the most economically advantageous suppliers. If the current CHWS Framework Agreements were to expire without new arrangements being in place, this would leave officers without access to procurement compliant framework arrangements which facilitate the efficient weekly procurement of statutory compliance works and services, maintenance and minor works without the need to commission on a case by case basis in accordance with Contract Procedure Rules. It is, therefore, proposed that current Framework Agreements are modified to extend their expiry date to 2 nd October 2024, but also to apply an inflationary increase to the Charges payable to suppliers.
Appendix A to this report details the current suppliers appointed to the CHWS Framework Agreements.
Recommendations
That Cabinet approval is given to –
approve a modification to extend those current CHWS Framework Agreements detailed in Appendix A for a term of 12-months to allow sufficient time to robustly procure and mobilise a new CHWS framework arrangements from 3rd October 2024 and to apply an inflationary uplift to the charges payable under the Framework Agreements, as detailed in this report.
delegate approval to the Deputy Chief Executive (Place), Director of Environment and the Director of Economy, as relevant, to award call-off contracts under the Framework Agreement entered into under the CHWS framework arrangements, subject to compliance with the prescribed call-off procedures and the formalisation of call-offs using the prescribed forms of contract.
2 Delegate authority to the Director of Legal Services or nominee to carry out all legal formalities.
Cabinet 13 November 2023
Construction and Highways Works & Services Framework Agreement (CHWSFA) - Existing Framework
Background
1.1The current Construction and Highways Works & Services Frameworks were procured during 2019 and became contractually effective from 3rd October 2019. The contract term for each of the 23 lots was 2 years with the option to extend by an additional two years in one-year increments (2+1+1). The frameworks are now in the final year and will end on 2nd October 2023. The Council did not extend the term for Lot 8 Legionella Risk Assessments & Remediation for the period 3rd October 2022 to 2nd October 2023.
1.2On 3 January 2023 approval was granted to apply an inflationary increase to the charges payable by the Council under the following Lots –
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe...
Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.