Resolved
that the Cabinet will consider the confidential recommendations, in the report, at agenda item 16.
Cabinet decided this item on Monday 20 January 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
that the Cabinet will consider the confidential recommendations, in the report, at agenda item 16.
To appoint Rowland Homes to develop land at South Chadderton following the completion of a competitive land sale process. Rowland’s will deliver 149 homes, including 60 affordable homes with 15 for Social Rent. All homes constructed to the low carbon ‘Future Homes Standard’.
To select Rowland Homes for the purchase for the former South Chadderton School Site, Butterworth Lane. Cabinet 20 January 2025
Selection of Preferred Developer for Southlink
1.1Following the closure of the former South Chadeerton School in July 2012, Collective Spirit opened in September 2013. In May 2016, the school had its first Ofsted inspection and was deemed to be ‘inadequate’. In June 2017, the school announced that it would close – leaving 210 pupils without a school from September 2017.
1.2In 2020 the Council agreed to acquire the Freehold Interest in the former School for the Department for Education and the building was demolished leaving a cleared secured site.
1.3A Housing Delivery Strategy was approved by Cabinet in March 2022 that set out a series of recommendations for the Council to drive forward a programme of housing development activity and the former south Chadderton school site was identified as suitable to help meet these ambitions.
1.4In March 2024 Cabinet Approved ‘A local response to the national housing crises’ Report to accelerate the development and delivery of truly affordable homes and set out ambitions towards low/zero carbon.
2 Current Position
2.1The disposal was managed by CBRE via a competitive land sale utilising a two-stage formal tender process. First round bids were invited for the 25th September 2024 on a “Subject-to-Planning” basis. To support the disposal a series of technical reports which detailed site-specific constraints and shaped an indicative masterplan. This provided bidders with a degree of certainty on site capacity to reduce the likelihood of caveats being attached to offers.
2.2Sales particulars, which included details of the property, planning and development brief and disposal process were provided. The particulars were circulated amongst CBRE’s database of active developers and investors in the Northwest and Nationwide. 10 bids were submitted.
2.3Given the low variance in the financial offers between the top seven bidders, CBRE invited those parties to provide responses to clarifications.
2.4A further bid comparison was undertaken between the top two bids was undertaken to access the risks with each offer:
2.5This demonstrated that Rowland’s offer was not only the strongest from a financial standpoint but also provides for a significantly reduced risk of non-delivery or re- negotiation. content that a competitive level of 2.6 All homes will be built to the Government’s Future Homes Standard that will ensure:
Carbon emissions are reduced by 75-80% compared to current standards, contributing significantly to reaching net-zero goals. Low-carbon heating systems like heat pumps, ensuring homes are both energy-efficient and environmentally friendly are utilised. Focusing on fabric efficiency by improving insulation, minimising heat loss, and creating well-sealed structures.
2 Rowland’s proposal provides 149 homes (Scheme Outline can be found at Appendix 1) in the following tenure split:
Open Market Sale – 89 units Social Rent – 15 units Affordable Rent – 15 units Shared Ownership – 15 units First Homes – 15 units
3 Options/Alternatives
Option 1 – Select Rowland Homes This bid provides the most economically advantageous offer to the Council as well as achieving other objectives around the provision of truly affordable homes and low carbon credentials.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Selection of Preferred DeveloperReport | 241 KB | DownloadRead as text |
Follow Cabinet at Oldham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2026 | MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. | Approved | Open |
| 23 Mar 2026 | Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... | Noted | Open |
| 23 Mar 2026 | Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... | Approved | Open |
| 23 Mar 2026 | Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... | Decided | Open |
| 23 Mar 2026 | Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.