That the grant offer from the City Region Sustainable Transport Settlement (CRSTS), for delivery of an outline/full business case (OBC/FBC) for the schemes at Oldham Edge and Higginshaw Active Travel Link and Oldham Town Centre Sustainable Connectivity Link, be accepted. 2. That approval is granted to enter into a Funding Delivery Agreement with TfGM in relation to the proposed schemes. 3. That the intention to bring the additional resource into the transport capital programme in 2025/26 and complete development of the scheme in the appropriate timescales be noted. 4. That approval is granted to procure and make tender awards relating to the necessary external support required to develop the outline/full business case (OBC/FBC) and design development, and that this is ... view the full minutes text for item 11.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
To formally accept capital grant funding of £7.3m from CRSTS1 towards the delivery of two Oldham projects:
Oldham Edge and Higginshaw Active Travel Link
Oldham Town Centre Sustainable Connectivity Links
Executive summary
The Greater Manchester Combined Authority (GMCA) has agreed to reprioritise £190 million of CRSTS1 capital funding to address underspend and delivery challenges. This strategic adjustment supports the Bee Network, active travel and integrated transport goals across the region. As part of this process, 35 local authority-led schemes have been identified across GMCA, totaling £89.5 million in reprioritised funding. For Oldham, funding has been awarded for the development of Outline and Full Business Cases (OBC/FBC) for:
Oldham Edge and Higginshaw Active Travel Link
Oldham Town Centre Sustainable Connectivity Link
These schemes align with Oldham’s strategic transport objectives and growth, and support wider GMCA ambitions for sustainable mobility and inclusive growth.
The allocation of funding will enable detailed design work and the commissioning of professional services to meet funding conditions and ensure readiness for future delivery stages. Cabinet approval is sought to integrate this additional resource into the transport capital programme and proceed with procurement and scheme development.
Furthermore, they complement our current CRSTS1 schemes, which have already received funding:
St Mary’s Way Mumps Broadway to Rochdale Canal Link Park Road / Kings Road
Recommendations
1) That the grant offer from the City Region Sustainable Transport Settlement (CRSTS), for delivery of an outline/full business case (OBC/FBC) for the schemes at Oldham Edge and Higginshaw Active Travel Link and Oldham Town Centre Sustainable Connectivity Link, be accepted;
2) That approval is granted to enter into a Funding Delivery Agreement with TfGM in relation to the proposed schemes;
3) That the intention to bring the additional resource into the transport capital programme in 2025/26 and complete development of the scheme in the appropriate timescales be noted;
4) That approval is granted to procure and make tender awards relating to the necessary external support required to develop the outline/full business case (OBC/FBC) and design development, and that this is delegated to the Deputy Chief Executive (Place);
5) That approval is granted to use part of this resource to support Council teams, as required, to progress design options, stakeholder engagement and production of the full business case to secure further capital funding for Oldham; and
6) That approval to the Director of Legal Services or his nominated representatives be granted to execute and complete any contractual documents.
2 Cabinet 22 September 2025
Grant Acceptance: City Region Sustainable Transport Settlement (CRSTS) – Reprioritisation of CRSTS1 funding
Background
1.1In April 2022, the Greater Manchester Combined Authority (GMCA) was awarded £1.07 billion through the City Region Sustainable Transport Settlement (CRSTS1) to support the delivery of its long-term transport ambitions, including the development of the Bee Network – an integrated system for buses, trams, walking, wheeling, and rail.
1.2By 2025, due to national inflationary pressures and delivery challenges, GMCA undertook a re-baselining and reprioritisation of its CRSTS1 programme. This process was approved by Government in March 2024 and aimed to ensure realistic delivery within the funding period ending March 2027.
1.3As part of this strategic adjustment, GMCA identified £190 million in capital funding available for reprioritisation.
2 Current Position
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe...
Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.