Extend the contract term for the Delivery of Accommodation Based Services

Decided Executive 2 papers

AI summaryOldham Cabinet defers decision on one year extension of three accommodation support contracts to part B agenda item 15.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredDecision deferred to confidential agenda item 15 at same meeting
Money£1,061,696.90Total estimated 2026/27 cost of three contracts
What happens nextConsider at part BAgenda item 15, same Cabinet meeting on 20 October 2025
Who it affectsHomeless service usersVulnerable adults, young people and women in short term supported housing

What was decided

Cabinet will consider the confidential recommendations detailed in the report at agenda item 15 (part B).

Why

The report contains commercially sensitive information and is not for publication under paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972. Report P3

The contracts are due to end on 31 March 2026, and a one year extension is proposed to allow time for a review once the outcome of the Supported Housing (Regulatory Oversight) Act 2023 consultation is known. Report 1.7, P2

What happens next

Cabinet to consider and decide the recommendations at the part B (confidential) agenda item 15 on 20 October 2025. Report P3

If approved, written notice of extension to be given to providers by 3 November 2025, six months before expiry, with a further 12 months running from 1 April 2026 to 31 March 2027. Report 1.6, 1.7, P28

The money

  • £1,061,696.90 Total estimated 2026/27 cost for the three Accommodation Based Service contracts Report 6.1, P24
  • £1,048,432.90 Total 2025/26 value of the three contracts Report 2.2, P24
  • 395,422 Lot 1 Generic Service, Regenda Limited, 2026/27 value (no pound sign in source) Report P23, P24
  • 350,067 Lot 2 Young Peoples Service, Depaul UK, 2026/27 value (no pound sign in source) Report P23, P24
  • 316,207.90 Lot 3 Womens Service, Regenda Limited, 2026/27 value (no pound sign in source) Report P23, P24
  • 388,405 Lot 1 Generic Service, Regenda Limited, 2025/26 value (no pound sign in source) Report P23, P24
  • 343,820 Lot 2 Young Peoples Service, Depaul UK, 2025/26 value (no pound sign in source) Report P23, P24

Options considered

  • Rejected: Option 1: De-commission the services with Regenda and DePaul and cease delivery of Accommodation Based Services. Would leave vulnerable service users without support and likely increase homelessness in the borough Report P34, P35
  • Chosen: Option 2: Extend current contract arrangements for the three Accommodation Based Services to 31 March 2027 and transfer delegated authority to the Deputy Chief Executive (Place). Allows services to continue and gives time for a holistic review of supported accommodation provision Report P36, P37, P38, P39, 4.1, P42

Implications

  • Legal: The proposed one year extension is in line with clause 4.3 of each contract and was part of the original advertised offer, so no formal contract modification is required; regulation 72(1)(a) of the Public Contracts Regulations 2015 applies if needed. Report 7.1, 7.3, P28, P51
  • Financial: There is sufficient budget within the 2026 base budget for Homelessness (cost centre 50500) to fund the estimated contract costs. Report 6.2, P47
  • Risk: If the six months written notice cannot be given before 3 November 2025, an extension is only possible if the provider agrees to accept shorter notice; without agreement, the affected contract cannot be extended. Report 7.2, 7.4, P28
  • Other: Delegated authority for the contracts is to transfer from the Director of Adult Social Services (in consultation with the Lead Member for Adult Health and Social Care) to the Deputy Chief Executive (Place), in consultation with the Cabinet Member for Neighbourhoods, reflecting the earlier move of the budget and responsibility from Adult Social Care to Housing Needs. Report P3, P37, P42, 1.5

Who and where

  • Vulnerable adults, young people and women who are homeless or in housing related crisis and use the service Report 1.2, 1.3, P35
  • Provider Regenda Limited, which holds Lots 1 and 3 and subcontracts to Petrus and Safenet Report 1.1, P6, P8, P12, P14, 2.1
  • Provider Depaul UK, which holds Lot 2 (Young Peoples Service) Report 1.1, P7, P13
  • Oldham Councils Housing Needs service, which holds the budget and responsibility for these contracts Report 1.5, 6.2
  • Councillor Elaine Taylor, portfolio holder consulted on the proposal Report 5.1

Timeline

  • 1 April 2022: Original 3 year contract term for the three lots begins Report 1.6
  • March 2025: Cabinet agreed an initial 12 month extension to 31 March 2026 and transferred budget and responsibility from Adult Social Care to Housing Needs Report 1.5, P2
  • 31 March 2025: Original 3 year contract term ended Report P2
  • 20 October 2025: Cabinet meeting: part A decision to defer recommendations to part B agenda item 15 Report 9.1
  • 3 November 2025: Latest date by which 6 months written notice of extension must be given to providers Report P28
  • 1 April 2026: Proposed start of the further 12 month extension period Report 1.7, P1, P4, P33
  • 31 March 2027: Proposed end of the further 12 month extension period Report 1.7, P1, P4, P33

Plain English for the jargon

  • Accommodation Based Services: Short term supported housing for vulnerable and socially excluded people who are homeless or have experienced a housing related crisis, intended to stabilise service users and help them move to independent living.
  • Lot: A separate contract package within the overall tender; the three lots cover a generic service, a young peoples service, and a womens service.
  • DDR: Due Diligence Review carried out during the original procurement process via the Chest portal (reference DN558663).
  • PCR 2015 regulation 72(1)(a): Public Contracts Regulations 2015 provision allowing a contract modification where the change was set out in the original advertised offer and built into the contract terms.
  • Supported Housing (Regulatory Oversight) Act 2023: Act whose implementing consultation closed earlier in 2025; outcome is awaited and may affect future commissioning of these services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That the Cabinet will consider the confidential recommendations, detailed in the report, at agenda item 15.
Word for word from the decision Oldham published for this meeting. Source: committees.oldham.gov.uk

Follow this further

Built from Oldham's papers

What the report saysPro

Report to Cabinet

Reason for decision

To extend the contract term of each of the 3 contracts referenced in this report, in accordance with the terms and conditions of each contract for the period 1 st April 2026 to 31st March 2027

Executive Summary The Council is party to three separate contracts for the delivery of Accommodation Based Services. The initial term of each contract ended on 31st March 2025, and was extended to 31st March 2026, at the same time as responsibility and budget for these contracts passed from Adult Social Care to Housing needs. There is provision within each contract to extend the term for a further 12 months. This report proposes enacting that extension.

Recommendations  Approve a one year extension to the contract term in respect of those contracts referenced in this report, each of which relates to the delivery of Accommodation Based Services, noting that this is within the delegated authority of the Director of Adult Social Services in consultation with the Lead Member for Adult Health and Social Care  Approve the transfer of delegated authority relating to these contracts from the Director of Adult Social Services (in consultation with the Lead Member for Adult Health and Social Care) to the Deputy Chief Executive (Place), in consultation with the Cabinet Member for Neighbourhoods. This is in recognition of the previous transfer of these contracts from Adult Social Care to Housing Needs. NOT FOR PUBLICATION by virtue of Paragraph(s) 3 of Part 1 of Schedule 12A of the Local Government Act 1972 and it is not in the public interest to disclose the information because of the commercially sensitive nature of the information enclosed in the report.

PART B - Extend the contract term for delivery of Accommodation Based Services for 12 months until 31st March 2027

Background

1.1Oldham Council currently commissions two external providers to deliver three accommodation-based services, detailed below:

Lot 1, Generic Service Regenda Limited (subcontracted to Petrus)

Lot 2, Young Peoples Service Depaul UK

Lot 3, Women’s Service Regenda Limited (subcontracted to Safenet)

1.2Accommodation based services provide short term supported housing for vulnerable and socially excluded people who are homeless/have experienced a housing related crisis. Historically, the services were funded through the Supporting People grant but were mainstreamed to Adult Social Care when this ended.

1.3The aim of each commissioned service is to provide service users with a period of stabilisation, enabling them to successfully move on and establish and sustain independent living. Each commissioned service must therefore meet the short-term housing and support needs of service users whilst also maximizing sustained planned moves and throughput from the Service.

1.4Following a tender process in 2021, Oldham Council awarded a contract for the Provision of Housing Related Support: Short-Term Accommodation-Based Service for three (3) years with an option to extend up to a further two (2) years, to the suppliers named below.

Lots 1, Generic Service Regenda Limited (sub contracted to Petrus)

Lot 2, Young Peoples Service Depaul UK

Lot 3, Women’s Service Regenda Limited (sub contracted to Safenet)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Extend the contract term for delivery of Accommodation Based Services PART BReport 355 KB DownloadRead as text
PDF
Extend the contract term for the Delivery of Accommodation Based ServicesReport 245 KB Download

At this meeting

Whole meeting

Who was there

6 of 32 attended
MA
Mohon AliCommittee Member, apologies
JB
Jack BaileyOfficer, expected
MB
Mike BarkerOfficer, expected
MB
Mike BarkerOfficer, expected
EB
Emma BartonOfficer, expected
AB
Alex BougatefOfficer, expected
BB
Barbara BrownridgeCommittee Member, present
MB
Matthew BulmerOfficer, expected
HC
Harry CatherallOfficer, expected
LC
Laila ChowdhurySecretary, expected
NC
Neil ConsterdineOfficer, expected
ND
Nasir DadOfficer, expected

All 32 on the meeting page

On this subject at Oldham

Search all
  1. Extend the contract term for the Delivery of Accommodation Based ServicesThis decision
  2. Extend the contract term for delivery of Accommodation Based Services for 12 months until 31st March 2028Decided
  3. Approval to extend the Parking Contract with NSLDecided
  4. To Extend the Contract for the Delivery of the Young People's Sexual Health and Substance Misuse ServiceDecided
  5. Request to extend and vary the contract for the provision of Oldham and Rochdale collaborative substance misuse treatment and recovery serviceApproved
  6. Request to extend the contract for the provision of Oldham and Rochdale collaborative substance misuse treatment and recovery serviceDecided

More from Oldham Cabinet

All decisions
MeetingDecisionOutcome
23 Mar 2026 MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. Approved Open
23 Mar 2026 Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... Noted Open
23 Mar 2026 Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... Approved Open
23 Mar 2026 Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... Decided Open
23 Mar 2026 Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies