Spring Brook Capital Works

Approved Executive 2 papers

AI summaryCabinet approves £1,739,319 capital project at Spring Brook Upper School to create 36 new places for pupils with SEMH needs.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCapital investment for Spring Brook Upper School
Money£1,739,319Including 10% contingency, from Basic Need and HNPCA Grant
What happens nextGrant agreement and worksSchool commissions works, drawdown in interim periods
Who it affectsPupils with SEMH needs36 new places at Spring Brook Upper School

What was decided

Cabinet approved the capital project at Spring Brook Upper School to deliver additional and enhanced provision for pupils with additional needs within the New Bridge Academy Trust. Report P1, 5.1, 6.1

Funding is to be allocated from the Basic Need and High Needs Capital Allocation (HNPCA) Grant, charged to the educational capital programme for 2025/26. Report P2, 8.1

Why

The project will create 36 new places for children with Social, Emotional and Mental Health (SEMH) difficulties and bring the lower and upper school pupils together on one site. Report P3, P8

The council has a statutory duty to provide suitable school places, including for those with SEN and EHCPs, and rising out-of-borough placements are putting pressure on the High Needs Budget. Report 4.1

The scheme supports the SEND and Inclusion Strategy 2023-2027 and the council's aim to reduce reliance on costly independent provision outside the borough. Report 1.1, 4.1

What happens next

A grant agreement will be drawn up with the school setting out the funding amount and drawdown arrangements, with legal and procurement input. Report P26, P34

The council will require confirmation that appropriate insurance is in place before releasing funds for the works. Report 3.1

The money

  • £1,581,199 Estimated total project cost after RIBA stage 2 report Report P9
  • £1,739,319 Total project cost including 10% contingency, charged to 2025/26 educational capital programme Report P9, 8.1
  • £2.8 M Basic Need funding currently held by the Local Authority Report P4
  • £9.6 M High Needs Capital Allocation (HNPCA) funding currently held Report P4
  • £911k Additional annual funding required from the High Needs Block if PAN rises by 36 places Report P31

Options considered

  • Chosen: Option 1: Approve the capital investment to deliver the SEND and Inclusion Strategy 2023-2027. Meets statutory duty, increases SEMH places, reduces reliance on out-of-borough provision, supports strategy Report 5.1, 6.1
  • Rejected: Option 2: Do not approve the project. Risk of not fulfilling the SEND and Inclusion Strategy and continuing costly out-of-borough placements Report 5.2

Implications

  • Financial: Capital cost of £1,739,319 charged to 2025/26 educational capital programme from Basic Need and HNPCA Grant; any unspent budget returns to provision. Repayments to the academy will be net of VAT, as the trust reclaims its own VAT. Report 8.1, P26
  • Financial: Increasing the Published Admission Number by 36 places would require an additional £911k per annum from the High Needs Block of the Dedicated Schools Grant, split between base and high needs top-up funding. Report P30, P31
  • Legal: A grant agreement must be put in place covering funding amount and drawdown; legal and procurement services should confirm the document is appropriate. Report P26, P34
  • Equalities: No negative implications for vulnerable groups or children and young people; the project will benefit children with SEMH needs and the most vulnerable children in the borough. Report 10.1, P33
  • Staffing: No HR implications arising from the report; the project is overseen by New Bridge Academy Trust. Report P11
  • Risk: Risk to the council of inadequate insurance is mitigated by requiring confirmation of appropriate insurance before releasing funds. Report 3.1

Who and where

  • Children with Social, Emotional and Mental Health (SEMH) difficulties across Oldham Report P3, P7
  • New Bridge Multi Academy Trust, which runs Spring Brook Upper and Lower Schools Report P7, P11
  • Existing Spring Brook pupils, who would be brought together on one site with separate teaching areas Report P8
  • Children currently placed in out-of-borough or independent provision, who may in future be placed locally Report 4.1

Timeline

  • 2025/26: Capital programme year to which the £1,739,319 cost is to be charged Report 8.1
  • RIBA Stage 2 completed: Design stage completed, providing the cost estimate for the project Report P9, 14.1
  • SEND and Inclusion Strategy 2023-2027: Strategy period that the project supports Report 13.1

Plain English for the jargon

  • SEMH: Social, Emotional and Mental Health difficulties
  • HNPCA: High Needs Capital Allocation, a grant for SEND capital projects
  • EHCP: Education, Health and Care Plan
  • RIBA Stage 2: Concept design stage in the Royal Institute of British Architects' plan of work
  • PAN: Published Admission Number, the school's admission limit
  • KS1, KS2, KS3: Key Stages 1, 2 and 3, covering ages roughly 5-7, 7-11 and 11-14
  • MAT: Multi Academy Trust
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That the Cabinet approves the Capital Project, detailed in the submitted ... view the full minutes text for item 9.
Word for word from the decision Oldham published for this meeting. Source: committees.oldham.gov.uk

Follow this further

Built from Oldham's papers

What the report saysPro

Report to Cabinet

Reason for decision

This report seeks cabinet approval for a capital project that will offer additional places and enhance provision for pupils with additional needs who are based within the Newbridge Trust.

It also seeks approval for the allocation of funding from HNPCA and Basic Need Grant towards the scheme.

Executive summary

This report relates to a project at Spring Brook Upper School that will enhance existing provision and provide additional provision for pupils with additional needs. These proposals are now developed sufficiently for costs and proposals to be placed before the Cabinet for a final decision. This project will create a total of 36 new places in the school for children with additional needs.

Currently the Local Authority has around £2.8 M of Basic Need funding and £9.6 M of High Needs Capital Allocation Funding. It is proposed that where projects will generate additional places these projects are funded from the HNPCA Grant provision

Project Outlines and Recommendation

Spring Brook Upper School

Spring Brook Upper School is a special school that serves all areas Oldham for children with SEMH and is run by New Bridge Multi Academy Trust. This project will increase access to places for 36 children Spring Brook Academy is a special school in Oldham that is based across two sites and currently caters for 114 pupils aged between 4-16 years old with a range of Social, Emotional and Mental Health (SEMH) difficulties. Spring Brook lower school, which accommodates KS1 & KS2 pupils, shares its site with Lyndhurst Primary School, a mainstream primary academy. The Spring Brook upper school site, which accommodates KS3 pupils, is based in the Failsworth area of Oldham. Spring Brook lower school is approximately a 10-minute drive from the upper school site.

The central project objective for the Trust is how best to bring Spring Brook's lower and upper school pupils together on one site. The lower school and upper school pupils are to be predominantly based and taught in separate areas. The lower school pupils are to be accommodated within a new teaching block with the upper school pupils continuing to be taught within the existing main school building. KS1 pupils will be taught on the ground floor of the new teaching block with KS2 pupils taught on the first floor. Classrooms are to be designed to accommodate a maximum group size of between 8-10 pupils

The total cost of this project is estimated to be in the region of £1,581,199 (a total of £1,739,319 when including 10% contingency) following completion of a RIBA stage 2 report by Spring Brook Academy. It is proposed that this project is funded by the LA Basic Need and/or HNPCA Grant.

Background

1.1Demand for provision in special schools has risen substantially in recent years. The option recommended in this report provides an opportunity for the Council to provide funding to enhance SEMH provision in line with its Corporate Priorities, to provide a great start and skills for life.

This project will be overseen by New Bridge Academy Trust, there is no HR, Health and Safety, environmental health, property, IT or community cohesion implications arising from the report

2 Procurement Implications

2.1There are no procurement implications arising from the report.

3 Risk Assessments

3.1The Council will require confirmation that academies have appropriate insurance in place before releasing funds for the works.

4 Current Position

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Spring Brook Capital Works: AppendixAppendix 684 KB Download
PDF
Spring Brook Capital WorksReport 240 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 33 attended
MA
Mohon AliCommittee Member, present
JB
Jack BaileyOfficer, expected
MB
Mike BarkerOfficer, expected
MB
Mike BarkerOfficer, expected
EB
Emma BartonOfficer, expected
AB
Alex BougatefOfficer, expected
BB
Barbara BrownridgeCommittee Member, present
MB
Matthew BulmerOfficer, expected
HC
Harry CatherallOfficer, expected
LC
Laila ChowdhurySecretary, expected
NC
Neil ConsterdineOfficer, expected
ND
Nasir DadOfficer, expected

All 33 on the meeting page

More from Oldham Cabinet

All decisions
MeetingDecisionOutcome
23 Mar 2026 MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. Approved Open
23 Mar 2026 Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... Noted Open
23 Mar 2026 Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... Approved Open
23 Mar 2026 Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... Decided Open
23 Mar 2026 Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... Approved Open