Oldham Metropolitan Borough Council
Cabinet, Monday 19 January 2026 at 6.00pm

Yew Tree Community School - Capital Works

Approved Executive 2 papers

AI summaryOldham Cabinet approves £592,077.50 capital scheme to add SEND places and enhance provision at Yew Tree Primary School via a refurbished modular building.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedModular building for KS1 SEND at Yew Tree
Money£592,077.50Project total including 10% contingency
What happens nextNo next step stated in papers
Who it affectsYew Tree Primary SchoolPupils with additional needs and families

What was decided

Cabinet approved the capital project to provide additional places and enhance provision for pupils with additional needs at Yew Tree Primary School.

Cabinet approved allocation of funding from High Needs Provision Capital Allocations and Basic Need Grant towards the scheme.

Why

The project is needed to offer additional places and enhance provision for pupils with additional needs at the school. Report P1

What happens next

No further steps are set out in the papers supplied beyond Cabinet approval of the funding allocation.

The money

  • £592,077.50 Project total Report P30
  • 541077.50 Modular building subtotal Report P26, P13
  • 31000.00 Mechanical and electrical subtotal Report P22, P27
  • 20000.00 General works subtotal Report P25, P28
  • 59207.75 10% contingency Report P29
  • 195000 Refurbished 23m x 10m modular building Report P3
  • 35304 Delivery, crane hire and installation Report P4
  • 26813 Preliminaries Report P5
  • 17850 Enabling works, gateway and trackway Report P6
  • 33800 Ground investigations, surveys, commissioning, building control, SBEM Report P7
  • 94298 Groundworks Report P8
  • 14513 Two sliding or folding partition walls Report P9
  • 13500 Rental cost for refurbished building, 20 weeks at £1,350 per week, 50% refunded on purchase Report P10
  • 110000 Extra over cost, risk of needing a new unit instead, excluded from subtotal Report P11

Options considered

  • Chosen: Refurbished modular building. Lower cost than new unit, based on Portable Offices quote of 19/5/25 Report P3, P11

Implications

  • Financial: Total scheme cost £592,077.50 to be funded from High Needs Provision Capital Allocations and Basic Need Grant. Report P30
  • Financial: A further £110,000 risk item is flagged for the possibility of having to buy a new unit rather than the refurbished one; this is excluded from the subtotal. Report P11
  • Risk: The rental agreement secures the refurbished unit for 20 weeks, with 50% of the rental refunded on purchase; the EO1 sum covers the risk of missing that unit. Report P10, P11

Who and where

  • Pupils with additional needs at Yew Tree Primary School
  • The wider school community at Yew Tree Primary School Report P1

Timeline

  • 19/5/25: Portable Offices quote referenced for the modular building Report P3
  • 20 weeks rental period: Period to secure the refurbished modular building at £1,350 per week Report P10
  • 27/10/2025: Budget costs report dated Report P1
  • 2026-01-19: Cabinet decision to approve the capital project and funding allocation

Plain English for the jargon

  • KS1: Key Stage 1, the stage of primary education for pupils aged 5 to 7.
  • SEND: Special Educational Needs and Disabilities.
  • PC Sum: Prime Cost Sum, a provisional allowance for an item not yet finally specified.
  • Prelims: Preliminaries, the general site setup and running costs in a building project.
  • SBEM: Simplified Building Energy Model, used to show compliance with energy standards.
  • kVA: Kilovolt-ampere, a unit of electrical power for sizing supply.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That the Cabinet approves the capital project, detailed in the submitted report, that will offer additional places and enhance provision for pupils with additional needs at Yew Tree Primary School. 2. That the Cabinet approves the allocation of funding from High Needs Provision Capital Allocations and Basic Need Grant towards ... view the full minutes text for item 8.
Word for word from the decision Oldham published for this meeting. Source: committees.oldham.gov.uk

Follow this further

Built from Oldham's papers

What the report saysPro

Report to Cabinet

Yew Tree Primary School - Proposed KS1 SEND Modular Building BUDGET COSTS - 27/10/2025

Item Description of works Quantity Sum Cost

Modular Building (to be read inconjunction with Portable Offices quote dated 19/5/25) 1 Provide 23m x 10m refurbished modular building (see proposed plan) Item 195000

2 Delivery, crane hire and installation Item 35304

3 Prelims Item 26813

4 Enabling works (gateway and trackway) Item 17850

5 Ground investigations, surveys, commissioning, building control, SBEM Item 33800

6 Groundworks Item 94298

7 2no sliding/folding partition walls Item 14513

8 Rental cost to secure refurbished building (£1350 per week, 50% back when purchased) 20 weeks 13500

EO1 Extra Over Cost - Risk of missing out on refurbished unit and having to provide new (cost excluded from sub total) PC Sum 110000

`

Modular Building £541,077.50

Mechanical & Electrical

Provide 3 compartment trunking for power and data sockets Item 2000

Supply and install new fire alarm connected to main school Item 5000

Provide fob access to external double doors Item 3000

Heating, ventilation and CO2 monitors Item 11000

Provide CCTV cameras connected to server (4 camera system) Item 5000

Test new and existing electrics and provide certification Item 1000

Electrical main supply upgrade from 75kVA to 112kVA Item 4000

Mechanical & Electrical £31,000.00

General Works

Planning submission Item 5000 IT equipment Item 15000

General Works £20,000.00

Modular Building 541077.50

Mechanical & Electrical 31000.00

Gereral Works 20000.00

10% Contingency 59207.75

Project Total £592,077.50

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Yew Tree: Budget Costs 27-10-25Report 452 KB DownloadRead as text
PDF
Yew Tree Community School: Capital WorksReport 316 KB Download

At this meeting

Whole meeting

Who was there

6 of 31 attended
MA
Mohon AliCommittee Member, present
JB
Jack BaileyOfficer, expected
MB
Mike BarkerOfficer, expected
MB
Mike BarkerOfficer, expected
EB
Emma BartonOfficer, expected
AB
Alex BougatefOfficer, expected
BB
Barbara BrownridgeCommittee Member, present
MB
Matthew BulmerOfficer, expected
NC
Neil ConsterdineOfficer, expected
ND
Nasir DadOfficer, expected
JD
Julie DanielsOfficer, expected
PD
Peter DeanCommittee Member, apologies

All 31 on the meeting page

On this subject at Oldham

Search all
  1. Yew Tree Community School - Capital WorksThis decision
  2. VAR/52279/24 - Yew Tree Community School, Alcester Street, ChaddertonDecided
  3. FUL/350732/23 - Yew Tree Community School, ChaddertonDecided

More from Oldham Cabinet

All decisions
MeetingDecisionOutcome
23 Mar 2026 MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. Approved Open
23 Mar 2026 Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... Noted Open
23 Mar 2026 Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... Approved Open
23 Mar 2026 Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... Decided Open
23 Mar 2026 Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... Approved Open