Oxford City Council
Cabinet, Wednesday 13 August 2025 at 6.00pm

Oxpens River Bridge Update on Delivery and Funding

Agreed Executive 2 papers

Cabinet agreed this item on Wednesday 13 August 2025. Below is the council's own wording, with the papers it was decided on.

Item39

Resolved

Cabinet resolved to: Delegate authority to the Deputy Chief Executive - Place, in consultation with the Council’s Group Finance Director (Section 151 Officer), the Director of Law Governance and Strategy (Monitoring Officer) and the Cabinet Member for Planning and Culture to enter into legal agreements, or amend legal agreements, to secure the additional external funds required to meet the £3.7 m needed to deliver the Oxpens River Bridge and to enter an amended agreement with Oxfordshire County Council to enable the Growth Deal funding to be spent in 26/27 To approve the increase in the budget for the project within in the capital programme for the Oxpens River Bridge project by £3.7 m from £10.3m to £14.00m through the virement of underspend within the capital programme 2025/26. Delegate authority to the Deputy Chief Executive - Place, in consultation with the Council’s Group Finance Director (Section 151 Officer), the Director of Law Governance and Strategy (Monitoring Officer) and the Cabinet Member for Planning and Culture to enter into a construction contract and any necessary ancillary contracts for the delivery of the bridge, subject to the necessary funds being in place. Delegate authority to the Deputy Chief Executive - Place, in consultation with the Council’s Group Finance Director (Section 151 Officer), the Director of Law Governance and Strategy (Monitoring Officer) and the Cabinet Member for Planning and Culture, to approve the transfer of the bridge to Oxfordshire County Council on completion.
Word for word from the decision Oxford published for this meeting. Source: mycouncil.oxford.gov.uk

Follow this further

Built from Oxford's papers

What the report saysPro

Report to Cabinet

Agenda Item 9

To: Cabinet Date: 13 August 2025 Report of: Deputy Chief Executive - Place Title of Report: Oxpens River Bridge Update on Delivery and Funding

Summary and recommendations Decision being To agree to the virement of underspend in the current taken: capital programme to increase the project budget in the capital programme for the Oxpens bridge; to accept additional funding for the construction of the bridge from external bodies, and to agree to amending and entering legal agreements as necessary for the funding, construction and transfer of the bridge. Key decision: Yes Cabinet Member: Councillor Alex Hollingsworth Cabinet Member for Planning and Culture Corporate Priority: Enable an inclusive economy; Support thriving communities; and Pursue a zero carbon Oxford. Policy Framework: Adopted Local Plan policy AOC1 and SP2 and West End SPD

Recommendation(s): That Cabinet resolves to: 1 Delegate authority to the Deputy Chief Executive - Place, in consultation with the Council’s Group Finance Director (Section 151 Officer), the Director of Law Governance and Strategy (Monitoring Officer) and the Cabinet Member for Planning and Culture to enter into legal agreements, or amend legal agreements, to secure the additional external funds required to meet the £3.7 m needed to deliver the Oxpens River Bridge and to enter an amended agreement with Oxfordshire County Council to enable the Growth Deal funding to be spent in 26/27

2. To approve the increase in the budget for the project within in the capital programme for the Oxpens River Bridge project by £3.7 m from £10.3m to £14.00m through the virement of underspend within the capital programme 2025/26.

21 3. Delegate authority to the Deputy Chief Executive - Place, in consultation with the Council’s Group Finance Director (Section 151 Officer), the Director of Law Governance and Strategy (Monitoring Officer) and the Cabinet Member for Planning and Culture to enter into a construction contract and any necessary ancillary contracts for the delivery of the bridge, subject to the necessary funds being in place. 4. Delegate authority to the Deputy Chief Executive - Place, in consultation with the Council’s Group Finance Director (Section 151 Officer), the Director of Law Governance and Strategy (Monitoring Officer) and the Cabinet Member for Planning and Culture, to approve the transfer of the bridge to Oxfordshire County Council on completion.

Information Exempt From Publication Cost Information This information is exempted from publication under contained in the Schedule 12A to the Local Government Act 1972: report Information about someone’s finances or business This appendix includes cost information that is commercially sensitive

Appendix No. Appendix Title Exempt from Publication Appendix 1 Risk Register No

Appendix 2 Confidential Appendix Yes

Introduction and background

1. The Cabinet considered the Oxpens Bridge project at its meeting on 16 November 2022. The Cabinet report and resolutions can be viewed at: https://mycouncil.oxford.gov.uk/ieListDocuments.aspx?CId=527&MId=7378 2. In November 2022 the Cabinet approved the delegation of the acceptance of £2.8m from the Oxfordshire Growth Deal and the additional budget, entering into the pre- construction services agreement and delivery agreement and to enter into agreements with OXWED to allow the bridge to be constructed on their land. 3. Following that meeting, Balfour Beatty was appointed to provide early contractor support and deliver the detailed design via Stantec, the designers. The architectural concept for the bridge was developed and planning permission granted in July 2024. The detailed design was further developed and was accepted by Oxfordshire County Council, acting as the Technical Approval Authority for the scheme in early 2025. In June 2025 the Secretary of State for Transport granted permission for the bridge over the river under S106(3) of the Highways Act 1980 (as amended). The

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25 07 24 Risk Register_Appendix 1 356 KB Download
PDF
Oxpens River Bridge Update on Delivery and FundingReport 575 KB DownloadRead as text

At this meeting

Whole meeting

More from Oxford Cabinet

All decisions
MeetingDecisionOutcome
19 Aug 2026 Procurement of a GO strategic partnerCabinet resolved to: Note the update as to the progression of the procurement of a strategic partner for the design a... Noted Open
19 Aug 2026 Controlled Parking Zones (CPZ) Review of existing zones and CIL spendCabinet resolved to: Approve the request to add the West Oxford Controlled Parking Zone (CPZ) to the approved list of... Approved Open
19 Aug 2026 Oxfordshire Infrastructure Strategy (OxIS)Cabinet resolved to: Endorse the Oxfordshire Infrastructure Strategy (OxIS) which has already been endorsed by the Ox... Decided Open
19 Aug 2026 Use of CIL funding to support infrastructure and public realm related to the Cowley Branch LineCabinet resolved to: Ringfence 30% of future CIL income arising from development within 1.5 km of either of the two C... Agreed Open
8 Jul 2026 Thames Valley Strategic Authority Proposal: Update and Implications for Oxford CityCabinet resolved to: 1. Note Oxfordshire County Council’s decision to veto the Thames Valley Foundation Strategic Aut... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies