AI summaryOxford City Council Cabinet approves procurement of a new HR and Payroll system to replace the iTrent platform, with £250,000 extra capital approved on top of £75,000 already agreed.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet agreed to start competitive procurement for new HR and Payroll system
Money£325,000 total capital£250,000 new plus £75,000 already approved
What happens nextSupplier Engagement Day 24 March 2026Followed by procurement and future award report
Who it affectsAround 1,500 employeesAcross council and Oxford Direct Services Ltd
What was decided
Cabinet approved starting a competitive procurement for a modern HR and Payroll system to replace the current iTrent platform, with a future report to confirm contract value, duration and supplier.
An additional £250,000 of capital was approved for implementation costs, on top of £75,000 already approved, bringing the total planned allocation to £325,000. Report P16
Authority was delegated to the Chief Executive, in consultation with the Group Finance Director, to set the final procurement terms, decide contract length, and delay or halt the process if Local Government Reorganisation developments require it.
Why
The existing iTrent contract provided by Midland HR cannot lawfully be extended beyond 31 March 2028, and failure to replace it would put payroll, pension contributions and statutory reporting at risk. Report P32, P44
Officers considered six alternative options, including a short-term contract, a custom in-house system, a joint consortium procurement, a PCR2015 extension, skipping the final one-year extension, and deferring until after the LGR decision. All were rejected, mainly due to cost, disruption, complexity or insufficient time before April 2028. Report P1, P2, P3, P4, P5, P6
The new system is intended to support around 1,500 employees, integrate with the Finance system, comply with GDPR, align with the council's Net Zero commitments and prepare for potential Local Government Reorganisation. Report P13, P42, P46
What happens next
A Supplier Engagement Day is scheduled for 24 March 2026 to inform suppliers and align offerings with the council's needs. Report P9, P10
A Recommendation to Award report will come back to Cabinet after the procurement, setting out the chosen supplier, contract length, value and rationale, before any contract is signed.
A go/no-go decision will follow the Local Government Reorganisation outcome expected in summer 2026; if it does not result in three unitary authorities, the procurement will be halted. Capital spend in 2026/27 and 2027/28 (£100,000 and £150,000) is at risk until then. Report P15, P17, P18, P19
The money
£250,000 Additional capital bid approved for implementation costs Report P16
£75,000 Capital previously approved for the project Report P16
£325,000 Total planned capital allocation for implementation Report P16
£100,000 Planned 2026/27 spend on procurement and early implementation Report P17
£150,000 Planned 2027/28 spend on configuration, migration and parallel running Report P18
£715,915 Value of existing HR and Payroll contract over its full 10-year term Report P23
Options considered
Rejected: Short-term transition contract with a different provider for 1 to 2 years. High risk of disruption, extra set-up and migration costs, and diversion from broader transformation. Report P1
Rejected: Custom built in-house system. Large investment in expertise and maintenance, plus risks on scalability, security and resilience. Report P2
Rejected: Consortium procurement with other local authorities. Local Government Reorganisation creates uncertainty over timelines, governance and long-term viability. Report P3
Rejected: Extend the existing contract under PCR2015 allowances. Limited scope and the current supplier is moving to a new platform; kept as a possible contingency only. Report P4
Rejected: Decline the final one-year extension to speed up replacement. Risk of overlap with other corporate system changes and too little procurement and mobilisation time. Report P5
Rejected: Defer procurement until the Local Government Reorganisation decision in July. Would leave insufficient time to complete procurement and implementation by April 2028. Report P6
Implications
Financial: Total capital allocation rises to £325,000, with phased spend of £100,000 in 2026/27 and £150,000 in 2027/28; the current contract costs around £79,000 a year over a 10-year term worth £715,915. Report P16, P17, P18, P23
Risk: Risks include data security during migration, budget uncertainty, limited internal capacity, supplier disengagement, system performance, and disruption from Local Government Reorganisation. The current system cannot be lawfully extended beyond 31 March 2028. Report P31, P32
Legal: Procurement will follow the Procurement Act 2023 and the council's Constitution; a final award at or above £750,000 will be a Key Decision requiring Cabinet approval. Report P27, P28
Equalities: An Equalities Impact Assessment has been completed and will be updated; the system must meet accessibility standards such as WCAG and consider protected groups throughout design and training. Report P37, P38
Climate: A cloud-based delivery model, digital-first processes, remote training and supplier sustainability checks are expected to keep environmental impact low and support Net Zero targets. Report P40, P41, P42
Staffing: Implementation will affect all staff and requires coordinated change management, communication, training and support, with revenue costs for training and ongoing support managed within existing budgets. Report P12, P22
Who and where
Around 1,500 employees across Oxford City Council and Oxford Direct Services Ltd Report P46
The council's People Team and project team Report P21, P48
Current supplier Midland HR, whose iTrent platform is being replaced Report P4
Neighbouring local authorities whose experiences have informed the approach Report P14
Timeline
11 February 2026: Cabinet approves initiation of procurement
24 March 2026: Supplier Engagement Day scheduled Report P9
Summer 2026: Local Government Reorganisation decision expected; triggers a go/no-go on the procurement Report P15, P19
2026/27: Planned capital spend of £100,000 on procurement and early implementation Report P17
2027/28: Planned capital spend of £150,000 on configuration, migration, integration and parallel running Report P18
31 March 2028: Latest lawful end date of the current HR and Payroll contract Report P32
April 2028: Target date for full implementation, with up to eight months of parallel running beforehand Report P18, P23
Plain English for the jargon
PCR2015: Public Contracts Regulations 2015, which govern how public bodies procure contracts in the UK.
Procurement Act 2023: New UK legislation replacing parts of the previous regulations and setting rules for how public bodies award contracts.
Local Government Reorganisation (LGR): Government-led restructuring of local councils, in this case possibly into three unitary authorities, with a decision expected in summer 2026.
Section 151 Officer: The senior council officer legally responsible for the proper administration of the council's financial affairs.
Three unitary authorities (3UA): A possible outcome of Local Government Reorganisation where existing councils would merge into three single-tier councils.
Key Decision: A council decision of significant financial or strategic impact that must follow formal publication and scrutiny procedures.
WCAG: Web Content Accessibility Guidelines, standards for making digital services accessible to people with disabilities.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item149
Resolved
Cabinet resolved to: 1. Approve the initiation of a competitive procurement process for a modern HR and Payroll management system to replace the existing platform, noting that final contract details (including duration and value) will be confirmed in a future report and will take account of Local Government Reorganisation (LGR). 2. Note a further ‘Recommendation to Award’ report will be presented to Cabinet following the conclusion of the procurement process, detailing the proposed supplier, confirmed contract duration, contract value, and award rationale, for approval prior to entering into any contract. 3. Delegate authority to the Chief Executive, in consultation with the Group Finance Director (Section 151 Officer) to: a. Determine the final form and content of the procurement exercise; b. Determine the duration of the contract; and c. Delay or halt the procurement, if necessary, due to developments in respect of Local Government Reorganisation. 4. Note the anticipated financial commitment and resource implications associated with the procurement and implementation of a new HR and Payroll system, as set out in this report and approve the inclusion of an additional £250k to cover implementation costs in addition to the £75k already approved.
Word for word from the decision Oxford published for this meeting.Source: mycouncil.oxford.gov.uk
To: Cabinet Date: 11 February 2026 Report of: Stephanie Nichols – People Operations Manager Title of Report: HR and Payroll system procurement and delegation to award contract Summary and recommendations Decision being To approve the procurement of a new HR and Payroll taken: management system to replace the Council’s current iTrent platform provided by Midland HR. Key decision: Yes http://mycouncilpages.oxford.gov.uk/mgIssueHistoryHome. aspx?IId=41521&PlanId=572&RPID=64928162&$LO$=1 Cabinet Member: Councillor Nigel Chapman, Cabinet Member for Citizen Focused Services and Council Companies Corporate A Well-run Council Priority: Policy Well-run Council Framework:
Recommendation(s): That Cabinet resolves to: 1 Approve the initiation of a competitive procurement process for a modern HR and Payroll management system to replace the existing platform, noting that final contract details (including duration and value) will be confirmed in a future report and will take account of Local Government Reorganisation (LGR).
2 Note a further ‘Recommendation to Award’ report will be presented to Cabinet following the conclusion of the procurement process, detailing the proposed supplier, confirmed contract duration, contract value, and award rationale, for approval prior to entering into any contract.
3 Delegate authority to the Chief Executive, in consultation with the Group Finance Director (Section 151 Officer) to:
▪ Determine the final form and content of the procurement exercise; ▪ Determine the duration of the contract; and
343 ▪ Delay or halt the procurement, if necessary, due to developments in respect of Local Government Reorganisation.
4 Note the anticipated financial commitment and resource implications associated with the procurement and implementation of a new HR and Payroll system, as set out in this report and approve the inclusion of an additional £250k to cover implementation costs in addition to the £75k already approved.
Information Exempt From Publication Not applicable
Appendix No. Appendix Title Exempt from Publication Appendix 1 Risk Register No
Appendix 2 Equalities Impact No Assessment Appendix 3 Data Impact No Assessment
Introduction and background 5. This report seeks approval to initiate the procurement of a new HR and Payroll management system to replace the Council’s existing platform currently provided by Midland HR. The original contract commenced in 2018 for an initial five-year term, with options for extensions of +2 years, +2 years, and +1 year. The Council is currently in the second two-year extension, which runs until March 2027, and has agreed to exercise the final one-year extension, taking the contract to its maximum permitted term of 10 years, expiring in March 2028. This decision was made to ensure continuity and stability during the implementation of other major corporate systems, avoiding unnecessary disruption to critical HR and payroll functions.
6. In line with statutory obligations and to ensure compliance with procurement rules, the Council is required to retender the service. The final 12-month extension to March 2028 has been agreed to provide sufficient time for mobilisation and a phased transition from the current system to the new platform. While implementation of the new system is planned for 1 October 2027, the extension ensures continuity and mitigates risk by allowing a six-month parallel running and contingency period before full decommissioning of the existing system. This approach guarantees uninterrupted HR and payroll services, supports thorough testing and data validation, and retains the current system as a fallback option should unforeseen delays occur, thereby safeguarding business continuity during a critical transition phase to a new system at a time of broader organisational change, as a result of LGR.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement of a GO strategic partnerCabinet resolved to: Note the update as to the progression of the procurement of a strategic partner for the design a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.