AI summaryCabinet approved a £1,087,163.22 programme to replace access control units across Oxford City Council's HRA housing portfolio and delegated authority to the Director of Housing to award the contract.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedProgramme approved; contract award delegated to Director of Housing
Money£1,087,163.22Total tender sum, exclusive of VAT
What happens nextAward contractDirector of Housing to award, in consultation with named officers
Who it affectsHRA residents and propertiesAccess control systems across the HRA portfolio
What was decided
Cabinet approved the planned programme to replace access control units across the HRA portfolio.
Cabinet delegated authority to the Director of Housing, in consultation with the Director of Group Finance, Director of Law and Governance, and the Cabinet Member for Housing and Communities, to award the contract and agree the contracting mechanism, subject to the Procurement Act 2023 and the Council's Contract Procedure Rules.
Why
Existing fob management systems are reaching capacity as blocks reach end of life, and ad-hoc site-by-site replacement would be more time and resource intensive. Report P1
Doing nothing would compromise building security, leave officers unable to issue fobs to new tenants, and require unplanned staffing for tenancy engagement. Report P2
The contract only covers City Council properties and the works are budgeted within the Medium Term Financial Plan, with delivery expected to conclude before Local Government Reorganisation. Report P3
What happens next
The Director of Housing will award the contract and agree the contracting mechanism, including any variation or ancillary agreement, in consultation with the named officers and Cabinet Member.
Legal services may be required to support Section 20 consultation, and the Council must follow landlord requirements if seeking to recover costs through service charges. Report P5
Any underspend in 2025/26 will need to be carried forward to ensure sufficient budget for the scheme. Report P4
The money
£1,087,163.22 Total tender sum for the contract, exclusive of VAT Report P4
£1,752,640 Latest approved HRA MTFP budget for the project, spread across 2025/26 to 2027/28 Report P4
£134,560 Provisional budget for Contract Administration, Project Management, Legal and Officer time Report P4
Options considered
Rejected: Ad-hoc site-by-site replacement. Individually tendering works on a site-by-site basis is time and resource intensive and creates added pressure on existing staffing for tenancy engagement. Report P1
Rejected: Do nothing. Blocks' fob management system would reach capacity, building security would be compromised, and officers would be unable to issue fobs to new tenants. Report P2
Chosen: Planned programme replacement
Implications
Financial: The £1,087,163.22 tender sum sits within the £1,752,640 approved MTFP budget across 2025/26 to 2027/28, with a further £134,560 provisionally allocated for administration, project management, legal and officer time. Report P4
Legal: Cabinet approval is required because the project and contract value exceed £750,000 under the Constitution; the Procurement Act 2023 and the Council's Contract Procedure Rules apply, and Section 20 consultation may be needed. Report P5
Equalities: An Equalities Impact Assessment has been prepared and is at Appendix 2. Report P7
Risk: A risk register has been prepared and is at Appendix 1. Report P6
Other: The works are timed to conclude before Local Government Reorganisation and the contract only covers City Council properties. Report P3
Climate: Carbon and environmental considerations are stated as not applicable. Report P8
Who and where
Tenants and residents of Oxford City Council HRA properties receiving new access control units Report P2
Oxford City Council as landlord and asset owner of the HRA portfolio Report P3, P5
Officers responsible for fob management and tenancy engagement Report P1, P2
Timeline
2025/26 to 2027/28: Budget period over which the £1,752,640 MTFP allocation is spread Report P4
Before Local Government Reorganisation: All works under this contract are scheduled to conclude Report P3
2025/26: Any underspend is to be carried forward to support the scheme Report P4
Plain English for the jargon
HRA: Housing Revenue Account: the ring-fenced account that funds council housing in England
MTFP: Medium Term Financial Plan: the council's multi-year budget planning document
LGR: Local Government Reorganisation: restructuring of local authorities
Section 20: Consultation process landlords must follow under the Landlord and Tenant Act 1985 before carrying out qualifying works
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item186
Resolved
Cabinet resolved to: 1. Approve the planned programme to replace the access control units across the HRA portfolio. 2. Delegate authority to the Director of Housing, in consultation with the Director of Group Finance, Director of Law & Governance, and the Cabinet Member for Housing and Communities, to award the contract and to agree the contracting mechanism (incl. any variation/ancillary agreement) and enter necessary documentation, subject to the Procurement Act 2023 and the Council’s Contract Procedure Rules.
Word for word from the decision Oxford published for this meeting.Source: mycouncil.oxford.gov.uk
To: Cabinet Date: 15th April 2026 Report of: Director of Housing Title of Report: Controlled Entry Systems Replacement (HRA)
Summary and recommendations Decision being To approve a contract for the programme replacement of taken: the access control units across the HRA portfolio. Key decision: Yes Cabinet Member: Councillor Linda Smith, Cabinet Member for Housing and Communities Corporate Priority: Good Affordable Homes Policy Framework: Housing, Homelessness and Rough Sleeping Strategy, Asset Management Strategy
Recommendation(s): That Cabinet resolves to: 1. Approve the planned programme to replace the access control units across the HRA portfolio. 2. Delegate authority to the Director of Housing, in consultation with the Director of Group Finance, Director of Law & Governance, and the Cabinet Member for Housing and Communities, to award the contract and to agree the contracting mechanism (incl. any variation/ancillary agreement) and enter necessary documentation, subject to the Procurement Act 2023 and the Council’s Contract Procedure Rules.
Information Exempt From Publication Tender Process The winning bid will be awarded a contract once Cabinet and Financial approves delegated authority to proceed. Implications
239 Appendix No. Appendix Title Exempt from Publication Appendix 1 Risk Register No Appendix 2 Equalities Impact No Assessment (EIA)
Introduction and background 1. The Council owns and manages multiple occupancy buildings across the HRA portfolio. Each building contains a fob management system (access control), providing residents with secure access into the building and to their respective residence. 2. There are multiple fob management providers currently in operation across the portfolio with some containing unsecure architecture. Many of these systems are now obsolete. Continued resident turnover means that these systems are now reaching storage capacity, with no ability to delete off the system. This impacts the ability to allocate new tenants with fobs, consequently delaying access to their new homes. This also potentially compromises the building security when fobs from former tenants are not returned and still used. 3. The council seeks to standardise fob management across the HRA portfolio, implementing a cloud-based fob management system using 4G technology. This will manage individual fobs remotely through a software platform. This will allow lost, stolen, or misplaced fobs to be remotely deactivated and set controls on the number of fobs allocated per residence, which will be in line with a newly implemented fob management protocol. 4. This system has been trialled; in the last 12 months a limited number of properties reached fob storage capacity. Properties were fitted with a cloud-based access control management system, which has proved very successful. 5. The project now seeks to implement a full programme rollout to provide a standardised approach. This will benefit both staff and residents going forward.
Overview of works 6. The new system will be on a secure cloud-based system that can be managed by staff through a website or a mobile application. The system technology uses GSM/4G networks, enabling remote management. The aim of these inclusions is to create a secure, manageable service for tenants, and for the council to improve building security. 7. Installation shall be carried out in accordance with the following legislation: • Construction (Design and Management) Regulations 2015 (CDM) • BS 7671 (IET Wiring Regulations) • BS EN 50133 (Access Control Systems for Security Applications) • Consideration of the Building Regulations Part M (Access to and use of buildings) • Equality Act 2010
240 • Data Protection Act 2018
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement of a GO strategic partnerCabinet resolved to: Note the update as to the progression of the procurement of a strategic partner for the design a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.