Property Decarbonisation Programme

Approved Finance 1 paper

Finance approved this item on Friday 8 March 2024. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED to: (a) approve the receipt of £3.1m grant funding from the Public Sector Decarbonisation Fund. (b) note, subject to approval (a), that the total Decarbonisation Programme budget included in the capital programme for 2024/25 will be £8.2m for works to 26 sites. (c) approve the commencement of the procurement of decarbonisation works with a value above £1m for Kidlington Fire Station HQ. (d) approve the commencement of the procurement of decarbonisation works with a value above £1m for Oxford Resource Centre. (e) approve the commencement of the procurement of decarbonisation works for the other sites in the programme of works, noting that where sites may be batched together into a single procurement exercise these will have a combined value in excess of £1m. (f) Delegate authority to the Executive Director of Resources & Section 151 Officer to agree the procurement strategy and award of contracts associated with the 2024/25 .
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Finance, 6 pages

Recommendation

1. The Cabinet Member for Finance is RECOMMENDED:

(a) To approve the receipt of £3.1m grant funding from the Public Sector Decarbonisation Fund.

(b) To note, subject to approval (a), that the total Decarbonisation Programme budget included in the capital programme for 2024/25 will be £8.2m for works to 26 sites.

(c) To approve the commencement of the procurement of decarbonisation works with a value above £1m for Kidlington Fire Station HQ.

(d) To approve the commencement of the procurement of decarbonisation works with a value above £1m for Oxford Resource Centre.

(e) To approve the commencement of the procurement of decarbonisation works for the other sites in the programme of works, noting that where sites may be batched together into a single procurement exercise these will have a combined value in excess of £1m.

(f) Delegate authority to the Executive Director of Resources & Section 151 Officer to agree the procurement strategy and award of contracts associated with the 2024/25 Property Decarbonisation Programme.

Executive summary

2. The Council has secured central government grant funding of £3.1m, requiring £5.1m match funding, to conduct full scale property decarbonisation of 26 buildings, putting these buildings on the pathway to net zero. This includes the electrification of heating, building fabric improvements, electrical efficiency improvements and deployment of renewable electricity generation technology.

3. This funding is time limited and need to be spent by 31 March 2025. A complex programme of works to replace aged equipment in a poor state of repair will generate potential carbon savings of 425 Tonnes of CO2e.

4. A range of options are presented within the report, with the recommendation to approve the full set of works to achieve the maximum decarbonisation benefits.

Background

5. The Council declared a climate emergency in 2019 with a target of 2030 to bring the Council’s operations and activities to net zero. This target is reflected in the Council’s Climate Action Framework and Property Strategy.

6. In 2022/23 the Council’s property accounted for approximately 33% (3,467 T CO2e) of the emissions that need to be reduced to meet the net zero target by 2030. In addition, a reactive only maintenance approach has left much of the Council’s estate in very poor-quality condition, with many components past their expected working life and in need of replacement irrespective of the net zero target.

7. To reduce emissions the aim is to stop fossil fuelled activities within the Council’s properties, which is predominantly heating, via the electrification of these components. Although there will be a carbon component remaining by 2030 from the use of electricity, this will be much reduced and will be on the pathway to fully net zero in line with the decarbonisation of the electricity grid. This should enable an ever-reducing need for carbon offsetting by 2030 and beyond which is outside of this scope of works but is recognised by the industry to be a significant unknown given the, currently, few recognised and accepted methods of carbon offsetting.

8. The transition to electric heating will predominantly be via heat pumps and infrared heating. Due to the lower operating temperatures of the heat pumps improvements are required in thermal building fabric (e.g. single glazing to double or triple glazing, insulation installations, etc.) to decrease the potential running costs. Nonetheless even with these improvements because of the, currently, low cost of gas compared to electricity the running costs would be increased. As part of the strategic approach the Council would seek to install renewable electricity measures (solar PV) and upgrade electrical components (particularly lighting to LED), to ensure the overall running costs do not increase.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Property Decarbonisation ProgrammeReport 6 pages DownloadRead as text

At this meeting

Whole meeting
4Property Decarbonisation ProgrammeThis decision
5Sale of Glebe House and The Moors, KidlingtonApproved

On this subject at Oxfordshire

Search all
  1. Property Decarbonisation ProgrammeThis decision
  2. Outline business case for Property decarbonisation programme 2025/26Approved

More from Oxfordshire Finance

All decisions
MeetingDecisionOutcome
16 May 2025 Tender for Insurance coverage and associated service (not brokering services)RESOLVED to: a) approve, as a key decision, the commencement of the procurement of insurance cover for the Council; a... Approved Open
11 Apr 2025 Fire Remedial Project Phase 2&3RESOLVED to: approve the entering into contract with Hughes & Associates to deliver the £3.7m capital funded Fire Com... Approved Open
11 Apr 2025 Outline business case for Property decarbonisation programme 2025/26RESOLVED to: a) Note that the total Property Decarbonisation Programme Budget included in the capital programme for 2... Approved Open
14 Feb 2025 Wood Green School, WitneyRESOLVED to Approve the completion of the Funding Agreement with Acer Trust which will release funding greater than £... Approved Open
10 Jan 2025 Marlborough School, WoodstockRESOLVED to: approve the sealing of a funding agreement to enable the Council to release funding greater than £1 mill... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies