Cherwell Bus Service Improvement Scheme

Approved Committee 7 papers

Transport Management approved this item on Thursday 10 October 2024. Below is the council's own wording, with the papers it was decided on.

Item144/24

Resolved

RESOLVED to: a) Approve in principle the preferred scheme to take forward into the preliminary and detailed design stage for the Cherwell Street Bus Service Improvement Scheme.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Transport Management, 8 pages

Recommendation

The Cabinet Member is RECOMMENDED to:

a) Approve in principle the preferred scheme to take forward into the preliminary and detailed design stage for the Cherwell Street Bus Service Improvement Scheme.

Executive summary

1. The Cherwell Street bus service improvement scheme in Banbury is a DfT- funded project under Oxfordshire's Bus Service Improvement Plan (BSIP), developed by Oxfordshire County Council in collaboration with local bus operators. The first version of the Bus Service Improvement Plan was approved by Cabinet on 19 October 2021 and has recently been updated and approved on 18 June 2024. This Banbury scheme constitutes measures to improve bus journey times from the current George Street bus lane into the town centre. The preferred scheme also proposes related pedestrian improvements (see scheme diagram in Annex 1).

2. Following a comprehensive options’ assessment, Oxfordshire County Council officers carried out an informal public consultation on the proposed scheme option in March 2024. The consultation document is provided in Annex 2. Whilst consultation feedback towards the proposals was generally positive, including from the key bus operator, there are elements that would require the removal of highway lanes and/or reduced highway capacity which has raised concern. Officers have addressed the issues in this report, but the next stage of design work will provide more evidence and detail, ahead of a formal consultation in December 2024. 3. Approval is therefore sought for the principles of the scheme to be taken forward into the next design stage.

Options and Feasibility

4. There are delays for buses travelling between George Street and the bus hub in Banbury town centre, with significant congestion at the Bridge Street/ Cherwell Street junction during peak periods. The scheme aims to improve and prioritise bus movement in this area.

5. The Oxfordshire BSIP recognised the lack of journey time reliability for buses through Banbury and aimed to improve their access into the town centre by introducing a northbound bus lane on Cherwell Street to reduce delay at peak times.

6. An appraisal was undertaken of a wide range of interventions (including the northbound bus lane), with five scheme options shortlisted for design and assessment using a VISSIM microsimulation model. The work demonstrated that the bus lane was not operating well because of its interaction with the petrol filling station on Cherwell Street, and reconfiguration of the signals with an extended left turn lane into the town centre (for buses and left turning vehicles) worked more effectively. Given the low number of left turning vehicles, modelling showed that this lane worked as a ‘virtual bus lane’ that still prioritised bus movements. Further detail is provided in the Options Assessment Report (Annex 3).

7. As well as the virtual bus lane, the proposed scheme includes wider improvements:

 George Street / Cherwell Street junction - the scheme includes the widening of the existing George Street bus lane to current standards where the buses turn left; the introduction of a pedestrian crossing on George Street and on the northern arm, and improvements to the traffic lanes approaching the junction from the south. These improvements would require general traffic lanes on George Street to be reduced from two lanes to one lane, close to the junction.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CMDTMT10102024: 6a: Annex 1 /24Appendix 1 pages Download
PDF
CMDTMT10102024: 6b: Annex 2 /24Appendix 8 pages Download
PDF
CMDTMT10102024: 6c: Annex 3 /24Appendix 55 pages Download
PDF
CMDTMT10102024: 6d: Annex 4 /24Appendix 16 pages Download
PDF
CMDTMT10102024: 6e: Annex 5 /24Appendix 4 pages Download
PDF
CMDTMT10102024: 6f: Annex 6 /24Appendix 53 pages Download
PDF
Cherwell Bus Service Improvement SchemeReport 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 2 attended
AG
Councillor Andrew GantCommittee Member, present
JA
Jack AhierSecretary, expected

On this subject at Oxfordshire

Search all
  1. Cherwell Bus Service Improvement SchemeThis decision
  2. Cherwell Street Bus Service improvement Scheme - Detailed DesignApproved
  3. Cherwell Street Bus Service improvement Scheme - ConstructionDecided

More from Oxfordshire Transport Management

All decisions
MeetingDecisionOutcome
23 Apr 2026 Copenhagen Drive, Abingdon - Proposed Toucan Crossing and Shared Use PathRESOLVED to: Approve the following measures on Copenhagen Drive in Abingdon, as advertised: a) New Toucan Crossing, t... Approved Open
23 Apr 2026 Proposed Bus Stops - Ladygrove, DidcotRESOLVED to: a) Approve the introduction of two new bus stop clearways (with ‘No stopping except local buses’ restric... Approved Open
23 Apr 2026 Wallingford Area LCWIPRESOLVED to: a) Approve Wallingford Area Local Cycling and Walking Infrastructure Plan (LCWIP). Approved Open
23 Apr 2026 A4130, Steventon Lights - Proposed Traffic Management MeasuresContact: Mohamed Gulamhussein, Project Manager – Infrastructure Delivery ( [email protected] ) ... Approved Open
23 Apr 2026 Proposed Puffin Crossing - A329 Reading Road, CholseyRESOLVED to: a) Approve the introduction of a new Puffin crossing on the A329 Reading Road in Cholsey, as advertised. Approved Open