CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Oxfordshire County Council
Transport Management, Thursday 10 October 2024 at 10.00am

Bus Services Contracts - March 2025

Approved Committee 1 paper

Transport Management approved this item on Thursday 10 October 2024. Below is the council's own wording, with the papers it was decided on.

Item153/24

Resolved

RESOLVED to: (a) Approve a procurement process to secure new and continued bus service provision following the expiry of 17 existing contracts, 3 of which require a Key Decision; (b) Approve use of surplus ENCTS and LABSG for new contracts as detailed in Exempt Annex A; (c) Approve the business case for the spend set out in this Report and to delegate authority to the Director of Environment & Highways in consultation with the Head of Legal & Deputy Monitoring Officer and the Head of Procurement & Contract Management to: Commence procurement processes to secure the services outlined below; Carry out the selection of the winning tenderers in accordance with the selection criteria set out in any procurement documentation and within the budget envelope for the respective services, and award the contracts to those providers; Negotiate and conclude the terms of any contractual arrangements required to deliver the services including entering into all necessary legal documentation; and Take any further steps necessary to ensure that continuity of services can be achieved should any further commercial routes be withdrawn or reduced.
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Transport Management, 11 pages

Recommendation

The Cabinet Member is RECOMMENDED to:

(a) Approve a procurement process to secure new and continued bus service provision following the expiry of 17 existing contracts, 3 of which require a Key Decision;

(b) Approve use of surplus ENCTS and LABSG for new contracts as detailed in Exempt Annex A;

(c) Approve the business case for the spend set out in this Report and to delegate authority to the Director of Environment & Highways in consultation with the Head of Legal & Deputy Monitoring Officer and the Head of Procurement & Contract Management to:

Commence procurement processes to secure the services outlined below;

Carry out the selection of the winning tenderers in accordance with the selection criteria set out in any procurement documentation and within the budget envelope for the respective services, and award the contracts to those providers;

Negotiate and conclude the terms of any contractual arrangements required to deliver the services including entering into all necessary legal documentation; and

Take any further steps necessary to ensure that continuity of services can be achieved should any further commercial routes be withdrawn or reduced. Executive Summary

2. The Transport Policy team plan and implement regular bus contract tender processes to ensure delivery of the Council’s strategic objectives. There is a requirement to procure 17 contracts for bus routes across Oxfordshire in order to secure the continuity of existing services.

3. Three of these contracts are expected to exceed £500,000 in value, and therefore these require a Key Decision and approval from the Cabinet Member for Transport Management.

4. In 2022, the Council was required to step in and provide funding for a number of services which were no longer commercially viable following a reduction in post-Covid passenger numbers, a reduction in financial support from Government and a significant increase in operating costs.

5. Many of these contracts expired in August 2024. At the time these contracts were due for procurement, it was expected that the traffic filter trial scheme would commence in November 2024 and therefore short-term arrangements were put in place until March 2025 in order to identify what effects the scheme would have on patronage, revenue and commercial viability of these services.

6. However, Network Rail’s continuing closure of Botley Road has necessitated a delay to introduction of the traffic filter trial scheme and therefore a further extension to these contracts is required.

7. At the same time, services funded through the Council’s Bus Service Improvement Plan (BSIP) are also due to end in March 2025 with the conclusion of the Government’s BSIP funding period, and initial trial rural services funded by the Council’s new rural and community transport budget are also due for renewal.

8. Continued approval is sought to use expected surplus from the English National Concessionary Travel Scheme (ENCTS) budget and held grant income from the Local Authority Bus Subsidy Grant (LABSG) to maintain these services, and others at the Council’s discretion.

Introduction

9. The Council has undertaken significant work in recent years to maintain and improve Oxfordshire’s bus network. Unprecedented challenges for the bus industry arising from the Covid-19 pandemic has resulted in the large-scale withdrawal of commercial services and necessitated the use of contracts to keep key services in operation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bus Services Contracts: March 2025Report 11 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 2 attended
AG
Councillor Andrew GantCommittee Member, present
JA
Jack AhierSecretary, expected

On this subject at Oxfordshire

Search all
  1. Bus Services Contracts - March 2025This decision
  2. Bus Services Contracts Autumn 2024Approved
  3. Business Services Transformation Programme Business RefocusApproved
  4. Provision of Services for Adults and children affected by Domestic AbuseAgreed

More from Oxfordshire Transport Management

All decisions
MeetingDecisionOutcome
23 Apr 2026 Copenhagen Drive, Abingdon - Proposed Toucan Crossing and Shared Use PathRESOLVED to: Approve the following measures on Copenhagen Drive in Abingdon, as advertised: a) New Toucan Crossing, t... Approved Open
23 Apr 2026 Proposed Bus Stops - Ladygrove, DidcotRESOLVED to: a) Approve the introduction of two new bus stop clearways (with ‘No stopping except local buses’ restric... Approved Open
23 Apr 2026 Wallingford Area LCWIPRESOLVED to: a) Approve Wallingford Area Local Cycling and Walking Infrastructure Plan (LCWIP). Approved Open
23 Apr 2026 A4130, Steventon Lights - Proposed Traffic Management MeasuresContact: Mohamed Gulamhussein, Project Manager – Infrastructure Delivery ( [email protected] ) ... Approved Open
23 Apr 2026 Proposed Puffin Crossing - A329 Reading Road, CholseyRESOLVED to: a) Approve the introduction of a new Puffin crossing on the A329 Reading Road in Cholsey, as advertised. Approved Open