AI summaryCabinet approved an updated ten year capital programme and the inclusion of Milton Heights Bridge with an £8.608m budget, noting forecast 2025/26 spending of £267.5m excluding earmarked reserves [D][P19][P114].
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted 2025/26 monitoring and approved changes [D][P5][P19]
Money£8.608m [P114][D]Milton Heights Bridge capital budget [P114][D]
What happens nextFormalise bridge funding before construction [P114]Enterprise Zone 2 allocation approval must come first [P114]
Who it affectsMilton Heights and Didcot connections [P113]Housing, enterprise zones and sustainable travel links [P113]
What was decided
Cabinet noted the 2025/26 capital monitoring position. Forecast expenditure is £267.5m, excluding earmarked reserves, which is £10.6m below the latest programme approved in February 2026 [D][P19]. Report P19
Cabinet approved the updated capital programme at Annex 2, incorporating the changes set out in the report [D][P5]. Report P5
Cabinet approved Milton Heights Bridge with a budget of £8.608m, funded from a variety of sources [D][P114]. Report P114
Why
The capital programme supports the Strategic Plan, the council's nine priorities and statutory functions, including school placements and urgent health and safety maintenance [P2]. Report P2
The update reflects delivery timeframes, current cost projections, new grants and the latest funding position [P3][P5][P6]. Report P3, P5, P6
The bridge would provide a key active travel link. It would offer a more attractive alternative to the congested route via Milton Interchange [P113]. Report P113
What happens next
Formalise approval of the Enterprise Zone 2 Retained Business Rates allocation before construction work begins [P114]. Report P114
Continue quarterly updates and full annual refreshes of the capital programme [P3]. Report P3
Where permanent funding is needed, address it through reprioritisation or permanent prudential borrowing. No further borrowing additions are planned for the 2026/27 budget process [P136]. Report P136
The money
£8.608m Milton Heights Bridge capital budget Report P114
£0.238m Growth Deal funds for the bridge Report P114
£2.604m Section 106 developer contributions for the bridge Report P114
£1.766m Council resources for the bridge Report P114
£4.000m Conditional Enterprise Zone 2 allocation Report P114
£1,350.3m Updated ten year strategy programmes, excluding earmarked reserves Report P115, P116
£184.7m Earmarked reserves after £4m bridge funding Report P121
Options considered
Chosen: Include Milton Heights Bridge in the capital programme. The project will provide a key active travel link and a more attractive alternative to the congested route via Milton Interchange. Report P113
Implications
Legal: In year changes to the capital programme must be approved by Cabinet under the council's Financial Regulations. Schemes with total estimated resource allocations above £2,000,000 can enter through the periodic capital report, following Strategic Capital Board and Section 151 Officer recommendations [P141]. Report P141
Financial: Earmarked reserves are £184.7m, down £3.9m because £4m is included for Milton Heights Bridge. The overall capital programme is over programmed by £10.4m [P121][P123]. Report P121, P123
Financial: The ten year programme includes £210.6m of prudential borrowing, with £57.1m expected in 2025/26. Overall capital reserves are expected to fall to only £8m by the end of 2029/30 [P118][P124]. Report P118, P124
Risk: Grant slippage can affect funding availability, and inflation can erode the value of grants by construction. The HIF1 forecast is sensitive to change as projects move from detailed design into early enabling works [P126][P51]. Report P126, P51
Climate: Milton Heights Bridge is intended to encourage local active travel trips and provide a more attractive alternative to the congested route via Milton Interchange [P113]. Report P113
Equalities: There are no equality and inclusion implications arising directly from the report [P140]. Report P140
Staffing: There are no staffing implications arising directly from the report [P139]. Report P139
Who and where
Strategic housing site at Milton Heights Report P113
Enterprise zones 1 & 2, including Milton Park Report P113
Didcot Report P113
People making local trips by sustainable modes Report P113
People in low income properties with poor energy performance Report P89
Adults who may currently be in hospital or secure units Report P94
Pupils with Special Educational Needs and Disabilities Report P27
Maintained schools Report P91
Timeline
February 2025: Council agreed £1.766m of council resources for Milton Heights Bridge. Report P114
October 2025: Cabinet conditionally approved an allocation of up to £4.000m from Enterprise Zone 2 Retained Business Rates towards Infrastructure. Report P114
end of January 2026: Actual capital expenditure was £154.4m. Report P22
February 2026: Council approved the latest capital programme. Report P21
Ahead of any construction work taking place: Approval of the Enterprise Zone 2 allocation's use for the bridge will be formalised. Report P114
May 2026: Main construction of Didcot Science Bridge is planned to start. Report P54
2026/27: Four remaining decarbonisation sites are expected to complete, and planned office spending is reprofiled into the year. Report P79, P85
end of 2029/30: Overall capital reserves are expected to reduce to only £8m. Report P124
Plain English for the jargon
Capital expenditure: Spending that creates a council asset or meets regulations under the Local Government Act 2003 [P9].
Capital programme: The ten year programme for using capital expenditure to deliver the council's priorities [P3].
Earmarked reserves: Capital reserves held for identified purposes, including the capital programme contingency and other provisions [P121].
Prudential borrowing: Borrowing that increases the Capital Financing Requirement. It creates a Minimum Revenue Provision cost and is generally paid over 25 years [P119].
Section 106: An agreement used to secure developer contributions towards community and social infrastructure [P26][P114].
HAMP: The Highways Asset Management Plan for maintaining the council's 4,656km network [P65].
HIF1: The Housing Infrastructure Fund 1 major infrastructure programme [P46][P50].
Enterprise Zone 2 Retained Business Rates: A funding source for infrastructure that directly enhances access to Enterprise Zone 2 [P114].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item43/26
Resolved
RESOLVED to:- a. Note the capital monitoring position for 2025/26 set out in this report and summarised in Annex 1. b. Approve the updated Capital Programme at Annex 2 incorporating the changes set out in this report. Additions to the Capital Programme c. Approve the inclusion of Milton Heights Bridge into the capital programme, with a budget of £8.608m, to be funded from a variety of funding sources. (see paragraph 65-66)
Word for word from the decision Oxfordshire published for this meeting.Source: mycouncil.oxfordshire.gov.uk
2. The Strategic Plan sets out how the council will lead positive change by working in partnership to make Oxfordshire a greener, fairer, and healthier county.
3. The Capital and Investment Strategy agreed by Council in February 2026 articulates how capital investment will help achieve this vision and the council’s nine priorities. In addition, the capital programme also supports statutory functions such as school placements and urgent health and safety capital maintenance works.
4. The ten-year Capital Programme sets out how the council will use capital expenditure to deliver these priorities. The Capital Programme is updated quarterly and fully refreshed annually as part of the Budget and Business Planning Process to ensure that it remains aligned to the latest priorities, reflects the latest cost projections and profile for delivery, and incorporates the current funding position.
5. This is the fourth capital programme update and monitoring report for 2025/26 and sets out the monitoring position based on activity to the end of January 2026.
6. The report also updates the Capital Programme approved by Council in February 2026 taking into account additional funding, new budget priorities and new schemes. The updated programme also incorporates changes agreed through the Capital Programme Approval Reports to Cabinet during the year as well as new funding.
7. The forecast programme expenditure for 2025/26 is £267.5m (excluding earmarked reserves). This has decreased by £10.6m compared to the previous capital programme for 2025/26 approved by Council in February 2025. The updated programme reflects the spend profile from the latest delivery timeframes as well as the inclusion of new grants received by the Council.
8. The total ten-year capital programme (2025/26 to 2035/36) is £1,534.9m. The updated capital programme summary is set out in Annex 2. The main changes since the report to Council in February 2026 are set out in this report.
Introduction
9. Capital expenditure is defined as spending that creates an asset for the council (e.g. buildings, vehicles, and equipment) as well as spending which meets the definition in regulations specified under the Local Government Act 2003. This includes spend on non-current assets that are not owned by the council such as academies and the award of capital grants and funding agreements.
10. The capital programme supports the delivery of the council’s vision and priorities as set out in the Strategic Plan. The programme is updated quarterly and fully refreshed annually as part of the Budget and Business Planning Process to ensure that it remains aligned with the latest priorities, reflects the latest cost projections and profile for delivery, and incorporates the current funding position.
11. The programme comprises the following strategy areas:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.