Cabinet, Tuesday 17 March 2026 at 2.00pm

Capital Programme Update and Monitoring Report

Noted Key decision Executive 2 papers

AI summaryCabinet approved an updated ten year capital programme and the inclusion of Milton Heights Bridge with an £8.608m budget, noting forecast 2025/26 spending of £267.5m excluding earmarked reserves [D][P19][P114].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted 2025/26 monitoring and approved changes [D][P5][P19]
Money£8.608m [P114][D]Milton Heights Bridge capital budget [P114][D]
What happens nextFormalise bridge funding before construction [P114]Enterprise Zone 2 allocation approval must come first [P114]
Who it affectsMilton Heights and Didcot connections [P113]Housing, enterprise zones and sustainable travel links [P113]

What was decided

Cabinet noted the 2025/26 capital monitoring position. Forecast expenditure is £267.5m, excluding earmarked reserves, which is £10.6m below the latest programme approved in February 2026 [D][P19]. Report P19

Cabinet approved the updated capital programme at Annex 2, incorporating the changes set out in the report [D][P5]. Report P5

Cabinet approved Milton Heights Bridge with a budget of £8.608m, funded from a variety of sources [D][P114]. Report P114

Why

The capital programme supports the Strategic Plan, the council's nine priorities and statutory functions, including school placements and urgent health and safety maintenance [P2]. Report P2

The update reflects delivery timeframes, current cost projections, new grants and the latest funding position [P3][P5][P6]. Report P3, P5, P6

The bridge would provide a key active travel link. It would offer a more attractive alternative to the congested route via Milton Interchange [P113]. Report P113

What happens next

Formalise approval of the Enterprise Zone 2 Retained Business Rates allocation before construction work begins [P114]. Report P114

Continue quarterly updates and full annual refreshes of the capital programme [P3]. Report P3

Where permanent funding is needed, address it through reprioritisation or permanent prudential borrowing. No further borrowing additions are planned for the 2026/27 budget process [P136]. Report P136

The money

  • £8.608m Milton Heights Bridge capital budget Report P114
  • £0.238m Growth Deal funds for the bridge Report P114
  • £2.604m Section 106 developer contributions for the bridge Report P114
  • £1.766m Council resources for the bridge Report P114
  • £4.000m Conditional Enterprise Zone 2 allocation Report P114
  • £267.5m Forecast 2025/26 expenditure, excluding earmarked reserves Report P19
  • £1,350.3m Updated ten year strategy programmes, excluding earmarked reserves Report P115, P116
  • £184.7m Earmarked reserves after £4m bridge funding Report P121

Options considered

  • Chosen: Include Milton Heights Bridge in the capital programme. The project will provide a key active travel link and a more attractive alternative to the congested route via Milton Interchange. Report P113

Implications

  • Legal: In year changes to the capital programme must be approved by Cabinet under the council's Financial Regulations. Schemes with total estimated resource allocations above £2,000,000 can enter through the periodic capital report, following Strategic Capital Board and Section 151 Officer recommendations [P141]. Report P141
  • Financial: Earmarked reserves are £184.7m, down £3.9m because £4m is included for Milton Heights Bridge. The overall capital programme is over programmed by £10.4m [P121][P123]. Report P121, P123
  • Financial: The ten year programme includes £210.6m of prudential borrowing, with £57.1m expected in 2025/26. Overall capital reserves are expected to fall to only £8m by the end of 2029/30 [P118][P124]. Report P118, P124
  • Risk: Grant slippage can affect funding availability, and inflation can erode the value of grants by construction. The HIF1 forecast is sensitive to change as projects move from detailed design into early enabling works [P126][P51]. Report P126, P51
  • Climate: Milton Heights Bridge is intended to encourage local active travel trips and provide a more attractive alternative to the congested route via Milton Interchange [P113]. Report P113
  • Equalities: There are no equality and inclusion implications arising directly from the report [P140]. Report P140
  • Staffing: There are no staffing implications arising directly from the report [P139]. Report P139

Who and where

  • Strategic housing site at Milton Heights Report P113
  • Enterprise zones 1 & 2, including Milton Park Report P113
  • Didcot Report P113
  • People making local trips by sustainable modes Report P113
  • People in low income properties with poor energy performance Report P89
  • Adults who may currently be in hospital or secure units Report P94
  • Pupils with Special Educational Needs and Disabilities Report P27
  • Maintained schools Report P91

Timeline

  • February 2025: Council agreed £1.766m of council resources for Milton Heights Bridge. Report P114
  • October 2025: Cabinet conditionally approved an allocation of up to £4.000m from Enterprise Zone 2 Retained Business Rates towards Infrastructure. Report P114
  • end of January 2026: Actual capital expenditure was £154.4m. Report P22
  • February 2026: Council approved the latest capital programme. Report P21
  • Ahead of any construction work taking place: Approval of the Enterprise Zone 2 allocation's use for the bridge will be formalised. Report P114
  • May 2026: Main construction of Didcot Science Bridge is planned to start. Report P54
  • 2026/27: Four remaining decarbonisation sites are expected to complete, and planned office spending is reprofiled into the year. Report P79, P85
  • end of 2029/30: Overall capital reserves are expected to reduce to only £8m. Report P124

Plain English for the jargon

  • Capital expenditure: Spending that creates a council asset or meets regulations under the Local Government Act 2003 [P9].
  • Capital programme: The ten year programme for using capital expenditure to deliver the council's priorities [P3].
  • Earmarked reserves: Capital reserves held for identified purposes, including the capital programme contingency and other provisions [P121].
  • Prudential borrowing: Borrowing that increases the Capital Financing Requirement. It creates a Minimum Revenue Provision cost and is generally paid over 25 years [P119].
  • Section 106: An agreement used to secure developer contributions towards community and social infrastructure [P26][P114].
  • HAMP: The Highways Asset Management Plan for maintaining the council's 4,656km network [P65].
  • HIF1: The Housing Infrastructure Fund 1 major infrastructure programme [P46][P50].
  • Enterprise Zone 2 Retained Business Rates: A funding source for infrastructure that directly enhances access to Enterprise Zone 2 [P114].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item43/26

Resolved

RESOLVED to:- a. Note the capital monitoring position for 2025/26 set out in this report and summarised in Annex 1. b. Approve the updated Capital Programme at Annex 2 incorporating the changes set out in this report. Additions to the Capital Programme c. Approve the inclusion of Milton Heights Bridge into the capital programme, with a budget of £8.608m, to be funded from a variety of funding sources. (see paragraph 65-66)
Word for word from the decision Oxfordshire published for this meeting. Source: mycouncil.oxfordshire.gov.uk

Follow this further

Built from Oxfordshire's papers

What the report saysPro

Report to Cabinet, 17 pages

Executive summary

2. The Strategic Plan sets out how the council will lead positive change by working in partnership to make Oxfordshire a greener, fairer, and healthier county.

3. The Capital and Investment Strategy agreed by Council in February 2026 articulates how capital investment will help achieve this vision and the council’s nine priorities. In addition, the capital programme also supports statutory functions such as school placements and urgent health and safety capital maintenance works.

4. The ten-year Capital Programme sets out how the council will use capital expenditure to deliver these priorities. The Capital Programme is updated quarterly and fully refreshed annually as part of the Budget and Business Planning Process to ensure that it remains aligned to the latest priorities, reflects the latest cost projections and profile for delivery, and incorporates the current funding position.

5. This is the fourth capital programme update and monitoring report for 2025/26 and sets out the monitoring position based on activity to the end of January 2026.

6. The report also updates the Capital Programme approved by Council in February 2026 taking into account additional funding, new budget priorities and new schemes. The updated programme also incorporates changes agreed through the Capital Programme Approval Reports to Cabinet during the year as well as new funding.

7. The forecast programme expenditure for 2025/26 is £267.5m (excluding earmarked reserves). This has decreased by £10.6m compared to the previous capital programme for 2025/26 approved by Council in February 2025. The updated programme reflects the spend profile from the latest delivery timeframes as well as the inclusion of new grants received by the Council.

8. The total ten-year capital programme (2025/26 to 2035/36) is £1,534.9m. The updated capital programme summary is set out in Annex 2. The main changes since the report to Council in February 2026 are set out in this report.

Introduction

9. Capital expenditure is defined as spending that creates an asset for the council (e.g. buildings, vehicles, and equipment) as well as spending which meets the definition in regulations specified under the Local Government Act 2003. This includes spend on non-current assets that are not owned by the council such as academies and the award of capital grants and funding agreements.

10. The capital programme supports the delivery of the council’s vision and priorities as set out in the Strategic Plan. The programme is updated quarterly and fully refreshed annually as part of the Budget and Business Planning Process to ensure that it remains aligned with the latest priorities, reflects the latest cost projections and profile for delivery, and incorporates the current funding position.

11. The programme comprises the following strategy areas:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
& 2: Capital Programme Summary (Cabinet Mar 26) /26Appendix 1 3 pages Download
PDF
Capital Programme Update and Monitoring ReportReport 17 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Oxfordshire

Search all
  1. Capital Programme Update and Monitoring ReportThis decision
  2. Capital Programme Monitoring ReportNoted
  3. Capital Programme Approvals - January 2026Approved
  4. Capital Programme Update and Monitoring ReportNoted
  5. Capital Programme Approvals - November 2025Approved
  6. Capital Programme Update and Monitoring ReportNoted

More from Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Response to Motion by Councillor Evans on Motor Neurone DiseaseContact: Izzie Rockingham, Commissioning Manager (Improve Enable) [email protected] Report by the ... Approved Open
15 Sep 2026 DfT Local Transport Delivery PlanContact: Hannah Battye, Head of Place Shaping [email protected] Report by the Director of Environment ... Approved Open
15 Sep 2026 Treasury Management Quarter 1 Report 2026/27RESOLVED to note the council’s treasury management activity at the end of the first quarter of 2026/27. Noted Open
15 Sep 2026 Forward Plan and Future BusinessRESOLVED to note the items currently identified for forthcoming meetings. Noted Open
28 Jul 2026 Proposed Changes to Adult Social Care Contributions PolicyRESOLVED to:- Note the contents of this report and confirm its agreement for a) Reducing the initial Disability Relat... Noted Open