Peterborough City Council
Cabinet, Tuesday 20 January 2026 at 4.00pm

Allocation of Funding and Award of contract for RIBA stages 3 & 4 for Pool/Leisure Development

Noted Executive 1 paper

AI summaryPeterborough Cabinet recommends £2,195,000 capital addition and, subject to Full Council approval, awards a £1.8m contract to Alliance Leisure Services for the next design stages of a new pool and leisure complex.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedTo Alliance Leisure Services for RIBA stages 3 and 4
Money£2,195,000 capital addition proposedPlus £1,800,432.91 contract and 7.5% contingency
What happens nextFull Council decides capital additionBusiness case February 2026; grant decision April or May 2026
Who it affectsPeterborough residents and swimmersReplacement for closed Regional Pool

What was decided

Cabinet recommended that Full Council approve adding £2,195,000 to the 2025/26 capital programme for RIBA stages 3 and 4 of the pool and leisure development, and noted that full project funding (including the £20m government grant) is to be considered in 2026/27 budget setting. Report P4

Cabinet agreed, subject to Full Council approving that budget, to authorise award of a contract to Alliance Leisure Services Limited for an initial value of £1,800,432.91, with a 7.5% contingency and any further planning and highways consultancy fees if required. Report P4

Cabinet authorised the Executive Director for Place and Economy, in consultation with the Director of Legal and Governance, to enter into the legal documentation, and delegated authority to approve contract variations subject to sign off from legal, finance and procurement. Report P6

Why

The Regional Pool in Bishops Road closed in 2024 due to structural problems, leaving the city with significant under provision of swimming facilities and unmet peak demand, worsened by population growth. Report 2.1, P13

Cabinet had previously agreed a preferred facility mix in October 2025, and the Government has announced £20m from the Growth Mission Fund subject to a full business case. Report 2.3, 2.7, P1

Alliance Leisure Services is the sole provider on the UK Leisure Framework, and the council judged the delivery partner route necessary to keep the project moving at the pace the Government has indicated. Report 2.5

What happens next

Full Council is asked to approve the £2,195,000 capital addition in 2025/26; the business case is expected to be submitted in February 2026, with an indicative Growth Mission Fund decision in April or May 2026. Report P4, 2.4, 2.7, 2.10

RIBA stages 3 and 4 are expected to run from February 2026 to around December 2026, after which a further Cabinet decision will be sought on the construction contract. Report 2.9, 2.10

A project board, reporting into the Economy and Inclusive Growth Portfolio Board, will oversee progress and risks, and a dedicated project manager is being recruited. Report 2.11

The money

  • £2,195,000 Total addition to 2025/26 capital programme for RIBA stages 3 and 4 Report 5.4, P43
  • £1,800,432.91 Initial contract value to Alliance Leisure Services Limited Report P4
  • 7.5% Contingency on the initial contract value Report 5.3
  • £750,000 RIBA Stage 3 budget Report 5.4, P43
  • £1,055,000 RIBA Stage 4 budget Report 5.4, P43
  • £135,375 RIBA Stage 3 and 4 contingency at 7.5% Report 5.4, P43
  • £100,000 Client side technical support, ad hoc budget if required Report 5.4, P43
  • £100,000 Planning costs (pre application, planning application and performance agreement) Report 5.4, 5.5, P43
  • £54,625 Highways consultancy indicative allowance Report 5.4, P43
  • £20m Government grant through the Growth Mission Fund, subject to business case Report 2.7, P2
  • £36m Estimated cost of new pool and leisure facility, as set out in the October 2025 facility mix Report 2.3, P15
  • £36.5m Overall estimated build cost, within which the RIBA stage fees sit Report 5.1

Options considered

  • Rejected: Do not commission RIBA stages 3 and 4 and abandon further development of a new pool and leisure facility. Strong public demand for new swimming facilities in the city Report 9.1
  • Rejected: Appoint a multidisciplinary design team and contractor through mini competition on a framework, traditional tender, or a two stage design and build contract. Would lengthen the project and place the Growth Mission Fund grant at higher risk; Government wants the project to proceed at pace Report P31
  • Chosen: Continue with Alliance Leisure Services as delivery partner under the UK Leisure Framework. Integrated approach, strong delivery history, fast mobilisation through a compliant framework, and a single point of accountability for managing the multidisciplinary team and risk Report P30, P32

Implications

  • Financial: Capital programme addition of £2,195,000 recommended for 2025/26; full project funding to be considered in 2026/27 budget setting. Report 5.1
  • Financial: The £20m Growth Mission Fund grant is subject to approval of a full business case, with an indicative decision in April or May 2026. Report 2.7, 2.10
  • Financial: Overall build cost and delivery timetable may change as design and market conditions are refined through stages 3 and 4. Report 5.2
  • Legal: Contract procured in compliance with the Public Contracts Regulations 2015, using the UK Leisure Framework; council relies on the discretionary power in section 19 of the Local Government (Miscellaneous) Act 1976. Report 7.1, 7.2, 2.5
  • Legal: An Exempt Annex is withheld under paragraph 3 of Schedule 12A of the Local Government Act 1972 on financial and business affairs grounds. Report 2.12
  • Equalities: No equality impacts are anticipated as part of the RIBA stage 3 and 4 development. Report 8.1
  • Climate: No decision at this stage affects carbon emissions; a carbon assessment will be carried out within the full business case. Report 3.2
  • Staffing: A dedicated project manager is being recruited to oversee the next phases of delivery. Report 2.11
  • Risk: A 7.5% contingency is included to manage pre construction risk, and a project board reporting into the Economy and Inclusive Growth Portfolio Board will monitor risks. Report 5.3, 2.11

Who and where

  • Peterborough residents and swimmers facing current swimming pool under provision Report P13, 2.1
  • Stakeholders consulted, including Friends of the Lido, City of Peterborough Swimming Club, Living Sport, Peterborough MPs, ARU and council services Report 4.1
  • Members of Full Council, who will decide on the capital programme addition Report P4
  • Alliance Leisure Services Limited, as the appointed contractor Report 2.5

Timeline

  • 11 March 2024: Cabinet agreed to decommission the Regional Pool and Fitness Centre in Bishops Road Report 2.1
  • 14 October 2025: Cabinet approved the preferred facility mix (per executive summary) Report P1
  • 16 October 2025: Cabinet agreed the new pool and leisure development in principle, subject to funding Report 2.3
  • 16 December 2025: Corporate Leadership Team consulted Report 4.2
  • 6 January 2026: Cabinet Policy Forum consulted Report 4.2
  • 20 January 2026: Cabinet decision on RIBA stages 3 and 4 funding and contract
  • February 2026: Full business case expected to be submitted Report 2.4, 2.7, P18
  • February 2026 to approximately December 2026: RIBA stages 3 and 4 pre construction phases Report 2.9
  • April/May 2026: Indicative decision on Growth Mission Fund grant Report 2.10

Plain English for the jargon

  • RIBA Stages 3 and 4: Stages 3 (Spatial Coordination) and 4 (Technical Design) of the Royal Institute of British Architects Plan of Work, covering pre construction design development.
  • UK Leisure Framework: A leisure specific procurement framework for public sector bodies, with Alliance Leisure as the sole provider.
  • Growth Mission Fund: Government grant programme under which Peterborough has been provisionally awarded £20m, subject to a full business case.
  • Capital Programme: The council's approved plan for capital spending, to which this report asks Full Council to add £2,195,000.
  • Delivery partner model: Arrangement where a single partner (here Alliance Leisure) acts as client advisor and takes on CDM and Principal Designer duties, assembling and managing the multidisciplinary team and procuring the contractor.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item93

Resolved

RESOLVED to: 1. Note the financial implications of this report and the planned inclusion of Full Funding for this Project as part of the 2026/27 budget setting process (including the Government Grant of £20m). 2. Recommend to Full Council to approve the addition of £2,195,000 to the Capital Programme in 2025/26 for the purposes of RIBA Stage 3 & 4 as set out in section 5.2 of this report. 3. Note that Alliance Leisure Services have been procured through the “UK Leisure Framework”. 4. Subject to Full Council approving that budget, authorise the award of a contract to Alliance Leisure Services Limited (ALS) for an initial contract value of £1,800,432.91 and a further a 7.5% contingency of this amount, and any additional planning and highway consultancy fees as set out within section 5.4, should this be required.
Word for word from the decision Peterborough published for this meeting. Source: democracy.peterborough.gov.uk

Follow this further

Built from Peterborough's papers

What the report saysPro

Report to Cabinet

Executive summary

Following the closure of the Regional Pool, the council has been actively exploring opportunities to develop a replacement facility. Cabinet considered and approved a preferred facility mix at its meeting of 14 October 2025, subject to funding becoming available.

The Government has now announced £20m of grant funding towards the cost of the development, subject to approval of a full business case. This report requests approval to enter the next stages of pre-construction development by allocating the budget and awarding a contract to Alliance Leisure for RIBA Stages 3 & 4.

Recommendations

Cabinet is requested to:

1. Note the financial implications of this report and the planned inclusion of Full Funding for this Project as part of the 2026/27 budget setting process (including the Government Grant of £20m). 2. Recommend to Full Council to approve the addition of £2,195,000 to the Capital Programme in 2025/26 for the purposes of RIBA Stage 3 & 4 as set out in section 5.2 of this report. 3. Note that Alliance Leisure Services have been procured through the “UK Leisure Framework”. 4. Subject to Full Council approving that budget, authorise the award of a contract to Alliance Leisure Services Limited (ALS) for an initial contract value of £1,800,432.91 and a further a 7.5% contingency of this amount, and any additional planning and highway consultancy fees as set out within section 5.4, should this be required.

103 20 January 2026 Cabinet Agenda Item 7

5. Authorise the Executive Director for Place and Economy in consultation with the Director of Legal and Governance to enter into any legal documentation relating to the recommendations set out in this report. 6. Delegate authority to the Executive Director of Place and Economy to approve any variations required to the contract with Alliance Leisure Services Limited, subject to approval from legal, finance and procurement services.

104 20 January 2026 Cabinet Agenda Item 7

1. Purpose

1.1Cabinet is asked to note the significant progress now being made on developing a new pool and leisure complex. Members are requested to agree to award a contract to ALS for the next stages of development, subject to Full Council agreeing the necessary budget being added to the capital programme, for this purpose.

2. Background and key issues

2.1At the meeting on 11 March 2024, Cabinet agreed to decommission the Regional Pool and Fitness Centre in Bishops Road due to several structural and repair issues which meant the centre had reached the end of its natural life.

2.2The Council has commissioned the development of a feasibility study to set out options for a replacement pool and fitness centre. The report identified several key findings:

• Swimming pool capacity in the city at 10.44sqm per 1,000 residents is low and this is reflected in the levels of unmet demand in the peak period. The report also found that the level of under provision in Peterborough is significant. The closure of the Regional Pool has only increased the level of swimming pool deficiency in the city. • The existing public swimming stock is at capacity and highly unlikely to cope with increased usage either as a consequence of more people swimming or through the demand created by increases in population growth. • A Sport England report also identified a lack of swimming provision both in Peterborough and neighbouring local authority areas.

2.3At its meeting of 16 October 2025, Cabinet agreed to a new pool/leisure development subject to funding becoming available. The new pool/leisure facility features will include:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Allocation of Funding and Award of contract for RIBA stages 3 & 4 for Pool/Leisure DevelopmentReport 917 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
SQ
Councillor Shabina Qayyum Leader of the CouncilChair, present
MF
Councillor Mohammed Farooq Deputy Leader & Cabinet Member for Growth and RegenerationVice Chair, present
ZA
Councillor Zameer Ali Cabinet Member for Communities, Poverty & Public HealthCommittee Member, present
NB
Councillor Neil Boyce Cabinet Member for Adults Social CareCommittee Member, present
KC
Councillor Katy Cole Cabinet Member for Children's ServicesCommittee Member, present
AE
Councillor Angus Ellis Cabinet Member for Environment & TransportCommittee Member, present
CH
Councillor Christian Hogg Cabinet Member for Housing and Regulatory ServicesCommittee Member, present
MJ
Councillor Mohammed Jamil Cabinet Member for Finance & Corporate GovernanceCommittee Member, present

More from Peterborough Cabinet

All decisions
MeetingDecisionOutcome
25 Aug 2026 Peterborough Local Plan Proposed Submission Version - Key/06APR26/01Cabinet unanimously RESOLVED to: 1. Approve the Proposed Submission (‘Publication Draft’) Local Plan as attached at A... Approved Open
25 Aug 2026 Youth Guarantee TrailblazerCabinet unanimously RESOLVED to: 1. Approve acceptance of £600,000 grant funding from the Cambridgeshire and Peterbor... Approved Open
25 Aug 2026 Care and Repair - Cabinet Report for a New Open Framework for the Delivery of Disabled Facilities Grants (DFG), Minor and Major Home Adaptations, and the Provision of Aids and Adaptations under the Care Act 2014Cabinet unanimously RESOLVED to: (1) Approve the award of framework agreements under the new Care and Repair Open Fra... Approved Open
25 Aug 2026 Goods Shed (Fletton Quays) DisposalCabinet unanimously RESOLVED to: 1. Authorise the disposal of the Goods Shed on the terms set out in Exempt Annex 2 o... Agreed Open