AI summaryPeterborough Cabinet approved a business loss payment to Landmark Theatres after the Key Theatre's extended closure caused by RAAC roof replacement works, to be funded from council reserves.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCovers income loss and extra costs from closure
MoneyNot disclosed (exempt appendix)Exact amount kept confidential in exempt appendix
What happens nextOfficers to implement the paymentDelegated to relevant Executive Directors
Who it affectsLandmark Theatres and Key Theatre usersAims to keep cultural programme running
What was decided
Cabinet approved the allocation of funding from reserves and authorised the compensation payment to Landmark Theatres for business losses caused by the Key Theatre capital works. Report P3
Authority to implement the payment was delegated to the Executive Director of Place and Economy, working with the Executive Director of Corporate Services. Report P4
Why
The Key Theatre has been unable to fully operate since June 2025 because of urgent roof replacement works needed after RAAC was found in the building, with the closure now extended to April 2026. Report 1.1, 2.2, 2.3
The payment is intended to cover Landmark's lost income, support its operations, and preserve Peterborough's cultural programme, including the seasonal pantomime. Report P14, 2.6
What happens next
Officers will arrange the payment from council reserves once implementation authority is exercised. Report 5.2, P4
Landmark Theatres will handle all communications and engagement with its users about the closure and programming changes. Report 2.5
Options considered
Rejected: Do nothing: no compensation payment. Risk that Landmark would return the asset to the council, leaving the council to run a theatre it cannot operate and face a possible breach of covenant claim. Report P38
Rejected: Make a reduced payment. Landmark's loss has been evidenced and reviewed internally; a lower amount would risk the theatre being handed back to the council. Report P39
Chosen: Pay the agreed business loss compensation from reserves. Secures the lease, avoids asset return, and protects the cultural programme. Report P3, 5.2, 6.1
Implications
Financial: The compensation will be paid from council reserves, with the agreed sum set out only in the exempt appendix. Report 5.1, 5.2
Legal: The council is using its general power of competence under section 1 of the Localism Act 2011, and the payment will be made in line with the Subsidy Control Act 2022. Report 7.2, 7.5
Risk: Without timely payment, Landmark could return the property early, leaving the council to run a specialist cultural asset it lacks capacity to operate. Report 6.1
Equalities: The report identifies no equality impacts from this decision. Report 8.1
Other: Decision supports corporate priorities on culture, community wellbeing, maintaining built assets, and partnerships with operators. Report 3.1, P21
Who and where
Landmark Theatres, which operates the Key Theatre under lease Report 2.1, 7.1
Theatre audiences and the wider Peterborough cultural programme Report P14, 2.6
Timeline
2023: Temporary props installed to Key Theatre roof after RAAC identified. Report 2.2
20 September 2023: Five year lease for the Key Theatre signed between the council and Landmark Venues Development Ltd, ending 19 September 2028. Report 7.1
June 2025: Key Theatre no longer able to fully operate due to roof replacement capital works. Report 1.1, 2.2
20 January 2026: Cabinet approved the business loss payment and delegated implementation. Report P3, P4
6 April 2026: End date of the extended closure period covered by the financial breakdown from Landmark Theatres. Report 2.4
Plain English for the jargon
RAAC: Reinforced Autoclaved Aerated Concrete, a lightweight building material found in the Key Theatre roof that requires replacement.
Business loss payment: Compensation paid to a tenant to cover income lost and extra costs caused by the landlord's building works.
General power of competence: Power under section 1 of the Localism Act 2011 allowing the council to do anything an individual may do, unless forbidden by law.
Subsidy Control Act 2022: UK law setting the rules for public bodies giving financial assistance to businesses.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item95
Resolved
RESOLVED to: 1. Approve the allocation of funding from reserves, creation of the associated budget and authorise the payment of compensation for business losses to Landmark Theatres as set out in the Exempt Annex, for the impacts arising from the Key Theatre capital works. 2. Delegate authority to the Executive Director of Place and Economy and in conjunction with the Executive Director of Corporate Services for the implementation of the payment.
Word for word from the decision Peterborough published for this meeting.Source: democracy.peterborough.gov.uk
This report seeks Cabinet approval for a further business loss payment to Landmark Theatres due to disruptions caused by ongoing capital works at the Key Theatre. The works, which include replacing the roof due to the presence of Reinforced Autoclaved Aerated Concrete (RAAC), have prevented the theatre from being able to fully operate since June 2025. The payment will mitigate income loss, cover additional costs, and support the theatre's operations, ensuring the continuity of Peterborough's cultural programme.
Recommendations
Cabinet is recommended to:
1. Approve the allocation of funding from reserves, creation of the associated budget and authorise the payment of compensation for business losses to Landmark Theatres as set out in the Exempt Annex, for the impacts arising from the Key Theatre capital works.
2. Delegate authority to the Executive Director of Place and Economy and in conjunction with the Executive Director of Corporate Services for the implementation of the payment.
135 20 January 2026 Cabinet Agenda Item 9
1. Purpose
1.1The purpose of this report is to seek Cabinet approval for the payment of a business loss payment to Landmark Theatres, in recognition of the disruption and additional responsibilities arising from the ongoing capital works at the Key Theatre. This includes the requirement to replace the roof following the identification of RAAC and the resulting impact on programming.
2. Background and key issues
2.1The Key Theatre is operated by Landmark Theatres under a lease agreement with the council.
2.2The council has commissioned urgent and essential works to the Key Theatre’s roof due to the presence of RAAC. Props were installed to the theatre in 2023 but due to the temporary nature of the works, a scheme for remediation of RAAC and replacement of the roof was prepared. These works, while necessary to safeguard the building, have disrupted business operations at the site, limiting Landmark Theatre’s ability to deliver its programme and generate income since June 2025. Due to unforeseen complexities in the project, there has been an overrun of the programme beyond this date.
2.3As a result of the extended closure of the theatre to April 2026, planned performances have had to be either relocated or postponed.
2.4Landmark Theatres has supplied the council with a financial breakdown regarding the extended closure period up to and including 6 April 2026. The spreadsheet is included in the exempt appendix.
2.5Landmark Theatres has confirmed that it will assume full responsibility for all relevant stakeholder engagement and manage communications with its users. The payment of the business loss payment to Landmark Theatres will enable:
• Mitigation of loss of income resulting from the Key Theatre’s extended closure • Support for Landmark Theatres in resource allocation, logistics, and public communications • Retention of the city’s seasonal cultural programme, ensuring continuity for audiences and stakeholders
2.6This business loss payment ensures the continued delivery of Peterborough’s cultural programme despite the capital works at the Key Theatre. It supports the sustainability of theatre operations, maintains public
136 20 January 2026 Cabinet Agenda Item 9
confidence and upholds the city’s reputation as a destination for high-quality performing arts.
2.7This report and its appendix is exempt from publication in accordance with Paragraphs 3 and 5 of Schedule 12A of Part 1 to the Local Government Act 1972 because it relates to financial and business affairs of the Council and contains information in respect of which a claim to legal professional privilege could be maintained in legal proceedings.
3. Corporate Priorities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Goods Shed (Fletton Quays) DisposalCabinet unanimously RESOLVED to: 1. Authorise the disposal of the Goods Shed on the terms set out in Exempt Annex 2 o...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.