Approval to award £1,000,000 of highway improvement works to M Group utilising the Highways Term Service Contract

Decided Executive 1 paper

AI summaryPeterborough Cabinet awards up to £1,000,000 of highway repair work to M Group Highways Limited for the Extreme Weather project, using the existing Highways Term Service Contract.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedUp to £1m to M Group Highways Limited
Money£1,000,000From 2026/2027 corporate budget
What happens nextScope can be variedBy Executive Director, Place and Economy
Who it affectsPeterborough road networkRural and fenland roads damaged by weather

What was decided

Cabinet approved awarding the works order to M Group Highways Limited via the Peterborough Highways Term Service Contract for the Extreme Weather project. Report P2

The Executive Director, Place and Economy, was authorised to vary the scope of the works to cover other related highway works. Report P3

Why

Drier winters and warmer summers are causing major deterioration of highway surfaces, especially on rural roads, with cracks widening and surfaces falling away. Report 2.3

Officers said using the existing contract saves time and money, gives access to agreed financial rebates, and uses a contractor with a proven track record in the city. Report 2.6, 7.5

If the project is not delivered, roads would continue to deteriorate and could become impassable, affecting connectivity, journey times and congestion. Report 3.2, 5.1, 5.3

What happens next

M Group will deliver jobs across the authority area, with the total value not exceeding the £1,000,000 allocated budget. Report 2.5

Works will fall under the Major Projects arm of the contract, attracting a year-end financial rebate on a sliding scale. Report 7.3

Residents will be notified by letter of any temporary disruption from the works; no formal consultation is planned. Report 6.1

The money

  • £1,000,000 Budget allocated for the Extreme Weather project in the 2026/2027 budget Report 2.1, 2.2, 7.1
  • £2 million Social value generated by M Group over the past 12 months, a 12.34% return on investment Report 2.9

Options considered

  • Chosen: Direct award via the existing Highways Term Service Contract. Saves time and cost; provides access to financial rebates; uses a contractor with proven local experience Report 2.6, 3.1, 7.3, 7.5
  • Rejected: Run a full procurement exercise to appoint an alternative contractor. Time and cost of procurement, and the Council would lose the agreed financial rebates Report 3.1
  • Rejected: Do not deliver the project. Roads would continue to deteriorate, potentially becoming impassable and causing congestion Report 3.2

Implications

  • Financial: Works are subject to a sliding-scale financial rebate at year end under the Major Projects arm; the contract operates on an open book basis so costs can be scrutinised. Report 7.3, 7.6
  • Legal: The contract was procured under the Competitive Dialogue Procedure (regulation 18 of the Public Contracts Regulations 2006) and permits call-off of works within its scope. Report 8.1
  • Climate: There will be a negative carbon impact on completion from materials and methods, but more sustainable approaches will be used where possible; failure to act could raise emissions through longer diversions. Report 5.5
  • Equalities: No community, individual or group is expected to be disproportionately affected by the proposed programmes of work. Report 9.1
  • Risk: Failure to deliver the works could lead to more expensive repairs later, with possible emergency temporary repairs creating revenue pressure. Report 7.2
  • Other: There are no expected implications for the Local Government Review and no implications identified for children in care and care leavers. Report 4.1, 5.6

Who and where

  • Road users across the Peterborough authority area, including rural and fenland routes Report 2.4, 2.5, 5.1
  • Peterborough residents, who may experience temporary disruption during works Report 5.3, 6.1
  • Local schools, work experience students and apprenticeship candidates supported by M Group Report 2.7
  • A Peterborough-based charity supported through M Group volunteering, fundraising and other activities Report 2.7

Timeline

  • 2013: Peterborough City Council awarded the original ten-year Peterborough Highway Services Contract after a rigorous procurement exercise Report 7.4
  • 2026/2027: Budget of £1,000,000 for the Extreme Weather project approved in the 2026/2027 budget setting exercise Report 2.1, 2.2
  • 23 June 2026: Cabinet decided to award the works to M Group Highways Limited Report P2
  • 2028: End date of the 5-year contract extension granted on the back of proven good performance Report 7.4

Plain English for the jargon

  • Retread: Process of planing, re-grading and re-profiling an existing road surface on site, then compacting and applying surface dressing; used on low traffic rural roads.
  • Resurfacing: Full removal of the damaged road surface followed by reconstruction and relaying of new materials, used on main B and C class roads on fenland soil.
  • Ex Situ Recycling: Planed surface material is taken to a nearby plant, crushed, screened and mixed with foam bitumen for strength and flexibility, then re-laid as a new base course.
  • LGR: Local Government Review; the report says there are no expected implications from it for this decision.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

Cabinet unanimously RESOLVED to: 1. Award works to M Group Highways Limited utilising the Peterborough Highways Term Service Contract for the delivery of the Extreme Weather project. 2. Authorise the Executive Director, Place and Economy, to vary the scope of the works when required to cover other related highway works.
Word for word from the decision Peterborough published for this meeting. Source: democracy.peterborough.gov.uk

Follow this further

Built from Peterborough's papers

What the report saysPro

Report to Cabinet

Executive summary

This report is seeking approval to direct award a works order up to £1,000,000 to M Group Highways Limited using the Highways Term Service Contract. The works order is for the improvement of highway surfaces that are deteriorating due to the effects of extreme weather.

Recommendations

1. Award works to M Group Highways Limited utilising the Peterborough Highways Term Service Contract for the delivery of the Extreme Weather project

2. Authorise the Executive Director, Place and Economy, to vary the scope of the works when required to cover other related highway works.

1. Purpose / Reason for Decision

1.1The value of the works for which we are seeking approval is considered a key decision. The purpose of this report is to clarify the mechanism for and benefits of a direct award via the existing Highways Term Services Contract.

2. Background and key issues

2.1The budget for the extreme weather project was approved in the 2026/2027 budget setting exercise https://www.peterborough.gov.uk/engagement-hub/members-sign-off- 202627-budget-and-three-year-financial-plan

2.2A budget of £1,000,000 was allocated to make repairs to areas of the highway that have suffered from the effects of extreme weather conditions over recent years.

173 23 June 2026 Cabinet

2.3Drier winters and warmer summers are having a major effect on the condition of our highway surfaces. The biggest impact can be found on the rural road network where extremely dry conditions cause large cracks in the road surface. Over time the cracks become wider and deeper and gradually the road surface starts to fall away from the centre of the carriageway.

2.4The programme of works can be split into three areas.

• Retread - typically used on low traffic rural roads, is a process where an existing road surface is planed, re-graded and re-profiled on site. It is then compacted followed by the application of a surface dressing. It is suitable for roads with low traffic volumes that have deteriorated. • Resurfacing - We intend to resurface some main B and C class roads that are located on fenland type soil. These roads have been majorly affected by the severe drought and require major repair. Resurfacing will remove the entirety of the damaged surface followed by full reconstruction and relaying of new materials. • Ex Situ Recycling - Ex-situ recycling has a similar process to the retread, but the planed surface material is removed to a nearby plant where it is crushed, screened and mixed with a foam bitumen to provide strength and flexibility. It is then transported back to site and re-laid as a new base course. The use of the foam bitumen has been proven to help reduce future maintenance costs as its light and flexible nature should help reduce undulations and cracks.

2.5The project will consist of a number of jobs to treat roads across the authority area. The total value of the jobs will not exceed the allocated budget of £1,000,000.

2.6Delivering the works via the Peterborough Highways Services contract offers significant savings in both time and money, further explained in section 6. Furthermore, M Group Highways Limited have a proven track record delivering a broad spectrum of highways works within the city and have built excellent working relationships with both Council officers and local stakeholders. The combination of experience and collaboration facilitates an effective and efficient working environment conducive to successful project delivery.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to award £1,000,000 of highway improvement works to M Group utilising the Highways Term Service ContractReport 204 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
DS
Councillor Dr Shabina Qayyum Leader of the CouncilChair, present
NB
Councillor Neil Boyce Deputy Leader and Cabinet Member for Adult ServicesVice Chair, present
ZA
Councillor Zameer Ali Cabinet Member for Communities and Public SafetyCommittee Member, present
KC
Councillor Katy Cole Cabinet Member for Children and Young PeopleCommittee Member, present
AE
Councillor Angus Ellis Cabinet Member for TransportCommittee Member, present
CH
Councillor Christian Hogg Cabinet Member for Regulatory Services and EnforcementCommittee Member, present
NA
Councillor Numan Ali Iqbal Cabinet Member for Growth and RegenerationCommittee Member, present
MJ
Councillor Mohammed Jamil Cabinet Member for Finance & Corporate GovernanceCommittee Member, present
AS
Councillor Ann Shaheed Cabinet Member for Public Health, Homelessness and PovertyCommittee Member, present
CW
Councillor Chris WigginCommittee Member, present

More from Peterborough Cabinet

All decisions
MeetingDecisionOutcome
25 Aug 2026 Peterborough Local Plan Proposed Submission Version - Key/06APR26/01Cabinet unanimously RESOLVED to: 1. Approve the Proposed Submission (‘Publication Draft’) Local Plan as attached at A... Approved Open
25 Aug 2026 Youth Guarantee TrailblazerCabinet unanimously RESOLVED to: 1. Approve acceptance of £600,000 grant funding from the Cambridgeshire and Peterbor... Approved Open
25 Aug 2026 Care and Repair - Cabinet Report for a New Open Framework for the Delivery of Disabled Facilities Grants (DFG), Minor and Major Home Adaptations, and the Provision of Aids and Adaptations under the Care Act 2014Cabinet unanimously RESOLVED to: (1) Approve the award of framework agreements under the new Care and Repair Open Fra... Approved Open
25 Aug 2026 Goods Shed (Fletton Quays) DisposalCabinet unanimously RESOLVED to: 1. Authorise the disposal of the Goods Shed on the terms set out in Exempt Annex 2 o... Agreed Open